Federal contract award

6982AF25C000020

UT NP BRCA PATH (3) BRYCE CANYON SHARED USE PATH MULTI-USE PATH CONSTRUCTION AND DRAINAGE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6982AF CENTRAL FEDERAL LANDS DIVISI
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$2.9M
Current contract value$2.9M
Potential contract value / ceiling$2.9M
Start dateApr 1, 2025
Current end dateJul 17, 2026
Potential end dateJul 17, 2026
Latest award activityFeb 3, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 3, 2026P00003$0BRYCE CANYON SHARED USE PATH
Jul 29, 2025P00002$300.0KTHIS UNILATERAL CHANGE ORDER DIRECTS THE CONTRACTOR TO COMPLETE THE CONSTRUCTION OF THE BRYCE CANYON SHARED USE PATH, TO INCLUDE REVISED PLAN SHEETS, CROSS SECTIONS, AND QUANTITIES FOR CLEARING AND GRUBBING, EARTHWORK, DRAINAGE, AND REVEGETATION. THE
Jul 10, 2025P00001$170.3KTHIS CONTRACT MODIFICATION WILL ADD PAY ITEMS FOR TREE REMOVALS, REVISE VERBIAGE IN SUBSECTION 108.01, INCREASE QUANTITIES FOR TRAFFIC CONTROL LINE ITEMS, AND ADJUST THE FIXED COMPLETION DATE.
Apr 1, 20250$2.5MUT NP BRCA PATH (3) BRYCE CANYON SHARED USE PATH MULTI-USE PATH CONSTRUCTION AND DRAINAGE