Federal contract award
70B01C23F00000890
CONSTRUCTION SERVICES OF THE INSTITUTE BUILDING AT CBP ADVANCED TRAINING CENTER, HARPERS FERRY, WV
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | ADMINISTRATION FACILITIES TRAINING CONTRACTING DIVISION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | 70Z04718DMORTSN00 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $36.1M |
| Current contract value | $36.1M |
| Potential contract value / ceiling | $36.1M |
| Start date | Sep 8, 2023 |
| Current end date | Feb 19, 2026 |
| Potential end date | Feb 19, 2026 |
| Latest award activity | May 6, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 6, 2026 | P00012 | $-175.1K | DE-OBLIGATION OF EXCESS FUNDS IN THE AMOUNT OF $178,098.00. |
| Sep 12, 2025 | P00011 | $39.7K | ADDITIONAL WORK WITHIN SCOPE OF THE CONTRACT FOR CONSTRUCTION OF APPALACHIAN HALL, AT THE CUSTOMS AND BORDER PROTECTION (CBP) ADVANCED TRAINING CENTER. |
| May 1, 2025 | P00010 | $48.5K | FUNDING PROVIDED AS AN EQUITABLE ADJUSTMENT DUE TO UNFORESEEN SITE CONDITIONS AT THE CONSTRUCTION SITE OF THIS CBP ADVANCED TRAINING CENTER BUILDING. |
| Jan 27, 2025 | P00009 | $0 | ADMINISTRATIVE FUNDING MODIFICATION - NO NET CHANGE IN CONTRACT VALUE |
| Sep 16, 2024 | P00007 | $3.4M | ADDITIONAL WORK TO ADDRESS SOIL CONDITIONS ON SITE |
| Sep 16, 2024 | P00008 | $6.3K | ATC HARPERS FERRY - THE INSTITUTE BUILDING, ADD'L WORK |
| Jul 23, 2024 | P00006 | $138.0K | ADDED WORK WITHIN SCOPE OF CONSTRUCTION PROJECT |
| May 31, 2024 | P00005 | $9.7K | MODIFICATION ADDS A WELLNESS ROOM AND ASSOCIATED FUNDING TO THE CONTRACT |
| Apr 4, 2024 | P00004 | $98.1K | ADDED WORK WITHIN SCOPE OF THE CONTRACT. |
| Feb 8, 2024 | P00003 | $529.2K | ADDITIONAL WORK WITHIN SCOPE OF THE CONTRACT TO BUILD THE ADVANCED TRAINING CENTER INSTITUTE BUILDING AT HARPERS FERRY, WV. |
| Nov 17, 2023 | P00002 | $85.9K | ADDITIONAL FUNDING PROVIDED FOR FEASIBILITY STUDY (WORK WITHIN SCOPE). |
| Oct 17, 2023 | P00001 | $0 | ADMINISTRATIVE MODIFICATION TO CHANGE THE CONTRACTING OFFICERS REPRESENTATIVE |
| Sep 7, 2023 | 0 | $31.9M | CONSTRUCTION SERVICES OF THE INSTITUTE BUILDING AT CBP ADVANCED TRAINING CENTER, HARPERS FERRY, WV |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.