Federal contract award
70FBR420F00000082
THE PURPOSE OF THIS TASK ORDER FOR RISK MAP IS TO COMPLY WITH THE STANDARDS FOR FLOOD RISK ANALYSIS AND MAPPING AND THE REQUIREMENTS AS SPECIFIED IN THE STATEMENT OF PRIORITIES.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | REGION 4: EMERGENCY PREPAREDNESS AN |
| NAICS | 541330 — Engineering Services |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | HSFE6015D0003 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $2.8M |
| Current contract value | $2.8M |
| Potential contract value / ceiling | $2.8M |
| Start date | May 21, 2020 |
| Current end date | Dec 31, 2024 |
| Potential end date | Dec 31, 2024 |
| Latest award activity | Aug 27, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 27, 2026 | P00006 | $-57.5K | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN ACCORDANCE WITH MEMORANDUM BLANKET DE-OBLIGATION OF EXCESS FUNDS IN PREPARATION FOR FINANCIAL SYSTEM TRANSITION. |
| Apr 3, 2024 | P00005 | $0 | CHANGE ORDER REQUEST THIS NO COST MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE (POP) FOR NINE (9) ADDITIONAL MONTH FROM OCTOBER 31, 2023 TO MARCH 31, 2024, TO: APRIL 01, 2024 THROUGH DECEMBER 31, 2024. SEE ATTACHED CHANGE ORDER REQUEST. |
| Sep 29, 2023 | P00004 | $0 | THE PURPOSE OF THIS "NO COST" MODIFICATION P00004, IS TO: 1. MODIFY THE CURRENT BASELINE TO EXTEND THE SCHEDULE AND THE PERIOD OF PERFORMANCE BY 6 MONTHS. 2. CHANGE THE POC FROM LILLIAN ROBISON TO AMANDA BANKS ALL OTHER TERMS AND CON |
| Dec 21, 2022 | P00003 | $0 | THE PURPOSE OF THIS NO COST MODIFICATION IS TO CORRECT THE PERIOD OF PERFORMANCE (POP) ON P00002 FROM: DECEMBER 31, 2022, THROUGH SEPTEMBER 30, 2023, TO: JANUARY 01, 2023, THROUGH SEPTEMBER 30, 2023. ALSO, TO CORRECT THE CORS NAME IN THE HEADER FROM |
| Dec 1, 2022 | P00002 | $0 | THE PURPOSE OF THIS "NO COST MODIFICATION IS TO MODIFY THE CURRENT BASE LINE TO EXTEND THE SCHEDULE AND THE PERIOD OF PERFORMANCE BY NINE (9) MONTHS IN SUPPORT OF REGION IV. |
| May 21, 2020 | 0 | $2.9M | THE PURPOSE OF THIS TASK ORDER FOR RISK MAP IS TO COMPLY WITH THE STANDARDS FOR FLOOD RISK ANALYSIS AND MAPPING AND THE REQUIREMENTS AS SPECIFIED IN THE STATEMENT OF PRIORITIES. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.