Federal contract award
70Z04721FPONCRO00
REBUILD FACILITIES RESIDENT INSPECTION OFFICE (RIO) PONCE, PONCE, PUERTO RICO
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | FDCC(00047) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | 70Z04718DRQAECM00 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $21.4M |
| Current contract value | $21.4M |
| Potential contract value / ceiling | $21.4M |
| Start date | Jun 22, 2021 |
| Current end date | Nov 28, 2025 |
| Potential end date | Nov 28, 2025 |
| Latest award activity | Mar 12, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 20 of 20 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 12, 2026 | P00020 | $209.4K | P00020-THIS MODIFICATION IS BEING ISSUED TO PROVIDE ALL DESIGN, MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION NECESSARY, ASSOCIATED WITH THE INSTALLATION AND CONNECTION OF THE NEW 150 KVA PAD MOUNTED TRANSFORMER. |
| Dec 19, 2025 | P00019 | $0 | P00019-THIS MODIFICATION IS BEING ISSUED TO ACCESS LIQUIDATED DAMAGES IN THE AMOUNT OF $2,089.00 PER CALENDAR DAY. |
| Mar 18, 2025 | P00018 | $519.5K | P00018-THIS MODIFICATION IS BEING ISSUED TO AWARD THE REMAINING NEGOTIATED AMOUNT TO COMPLETELY COMPENSATE THE CONTRACTOR. SECTION 2.D OF IMPLEMENTING DEPARTMENT OF GOVERNMENT'S EFFICIENCY APPLIES TO THIS ACTION. |
| Mar 5, 2025 | P00017 | $1.0M | P00017-THIS MODIFICATION IS BEING ISSUED FOR ENVIRONMENTAL PERMITTING AND THE UNFORESEEN UNDERGROUND STORAGE TANK. |
| Dec 18, 2024 | P00016 | $0 | P00016- BILATERAL MODIFICATION TO EXTEND THE CCD TO FEBRUARY 26, 2025 AT NO COST TO THE GOVERNMENT.. |
| Sep 4, 2024 | P00015 | $0 | P00015- UNILATERAL MODIFICATION TO CHANGE THE COR TO LCDR JUAN FITZPATRICK. |
| Jun 4, 2024 | P00014 | $0 | P00014- UNILATERAL MODIFICATION TO CHANGE THE COR TO JOSHUA AGANON. |
| Apr 15, 2024 | P00013 | $36.9K | P00013- REA003/RQ PCO #10 UNFORESEEN CONTAMINATED SOILS AND WATER AT BOAT BAY.. |
| Mar 6, 2024 | P00012 | $9.8K | P00012- CMR005/RQ PCO #11 SUBSURFACE UTILITY SURVEY IAW PRASA REQUIREMENTS IN PR. |
| Mar 4, 2024 | P00011 | $23.6K | P00011- REA002/RQ PCO #09 UNFORESEEN ARCHEOLOGICAL BRICK PIPING DISCOVERY |
| Jan 30, 2024 | P00010 | $70.8K | P00010- REA001 DESIGN AND PROCUEMENT AND INSTALLATION OF A 150KVA PAD MOUNTED TRANSFORMER. |
| Sep 29, 2023 | P00009 | $642.8K | P00009- REMOVAL OF UNFORESEEN UNDERGROUND STORAGE TANK. |
| Apr 25, 2023 | P00008 | $11.8K | P00008- UNFORESEEN UNDERGROUND STORAGE TANK. |
| Apr 10, 2023 | P00006 | $0 | P00006 - ENVIRONMENTAL PERMIT DELAYS |
| Jan 17, 2023 | P00005 | $1.0M | P00005 - CORRECT FINAL DESIGN PACKAGE |
| Jun 1, 2022 | P00004 | $65.0K | P00004- CHANGES TO 2ND FLOOR LAYOUT. |
| Apr 19, 2022 | P00003 | $2.2M | P00003- CONVERT BOAT STORAGE BAY INTO A BOAT MAINTENANCE BAY. |
| Mar 17, 2022 | P00002 | $0 | P00002- SPEC CHANGE FROM ANODIZED ALUMINUM TO FIBER REINFORCED PLASTICS |
| Feb 15, 2022 | P00001 | $129.6K | P00001- DIFFERING SITE CONDITIONS |
| Jun 22, 2021 | 0 | $15.5M | REBUILD FACILITIES RESIDENT INSPECTION OFFICE (RIO) PONCE, PONCE, PUERTO RICO |
Research next steps