AWARD OF DESIGN BUILD OF SECTOR CHARLESTON CONSTRUCT CONSOLIDATED ADMIN FACILITY, USCG BASE CHARLESTON, CHARLESTON, SC

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeFDCC(00047)
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicle70Z04718DRQAECM00
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$61.9M
Current contract value$61.9M
Potential contract value / ceiling$61.9M
Start dateJul 10, 2023
Current end dateOct 25, 2026
Potential end dateOct 25, 2026
Latest award activityJul 28, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 15 of 15 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 28, 2026P00014$289.2KMODIFICATION P00014 IS ISSUED FOR CMR 011- CAC ENABLED ENTRYWAYS AND OTHER CHANGES WITHIN SCOPE AT CHARLESTON BASE BUILDING, CHARLESTON, SC.
Feb 12, 2026P00013$2.6MMODIFICATION P00013 IS ISSUED FOR CMR 010- DIFFERING SITE CONDITIONS FOR EXCAVATION, SAMPLE, DISPOSE OF HAZARDOUS WASTE AT CHARLESTON BASE BUILDING, CHARLESTON, SC.
Dec 4, 2025P00012$3.3MMODIFICATION P00012 IS ISSUED FOR CMR 009- DIFFERING SITE CONDITIONS FOR REMOVAL OF EXCESS NON-HAZARDOUS UNSUITABLE SOILS AT CHARLESTON BASE BUILDING, CHARLESTON, SC.
Sep 19, 2025P00011$621.7KMODIFICATION P00011 IS ISSUED FOR CMR 006- UNFORESEEN SITE CONDITIONS FOR SEWER SURVEY, WATER TREATMENT, DUCT BANK REMOVAL, LAYERING ROAD AND SINK HOLES AT SOUTH HOBSON RD, CHARLESTON BASE BUILDING.
Sep 10, 2025P00010$464.0KMODIFICATION P00010 IS ISSUED FOR CMR 008-DIFFERING IN SITE CONDITIONS AT SOUTH HOBSON RD, CHARLESTON BASE BUILDING.
May 15, 2025P00009$602.1KMODIFICATION P00009 IS ISSUED FOR REA 001- SCHEDULE DELAYS AND CMR 007-RAILROAD AND PILE REMOVAL AT CHARLESTON BASE BUILDING.
Nov 21, 2024P00008$0MODIFICATION P00008 IS ISSUED TO ADDRESS THE ADDED TEXT TO THE RFP SPECIFICATIONS CONCERNING ELEC VEHICLE CHARGING HARDWARE REQUIREMENTS..
Oct 22, 2024P00007$676.2KMODIFICATION P00007 IS ISSUED TO ADDRESS CMR004 WITH PCO 4 METHANE MITIGATION.
Jun 12, 2024P00006$36.5KMODIFICATION P00006 IS ISSUED TO ADDRESS DESIGN SCOPE CHANGES WITH CMR003 AND INTERIOR STORAGE CHANGES.
May 28, 2024P00005$823.1KMODIFICATION P00005 IS ISSUED TO ADDRESS DESIGN SCOPE CHANGES WITH CMR002.
May 20, 2024P00004$587.5KMODIFICATION P00004 IS ISSUED FOR CMR001 TO ADDRESS DESIGN SCOPE CHANGES.
Mar 7, 2024P00003$0MODIFICATION P00003 IS ISSUED AS A UNILATERAL MOD TO CHANGE THE COR FROM ROB HAUPT TO LCDR HOUK.
Jul 12, 2023P00002$0MODIFICATION P00002 IS ISSUED AS A UNILATERAL MOD TO INCORPORATE FAR CLAUSE 52.222-55 EXECUTIVE ORDER 14026.
Jul 6, 2023P00001$0MODIFICATION P00001 IS ISSUED AS A UNILATERAL MOD TO INCORPORATE DEVIATION TO FAR CLAUSE 52.228-15.
Jun 26, 20230$51.9MAWARD OF DESIGN BUILD OF SECTOR CHARLESTON CONSTRUCT CONSOLIDATED ADMIN FACILITY, USCG BASE CHARLESTON, CHARLESTON, SC

Research next steps