Federal contract award
70Z05021FKODHP100
CONSTRUCT OPC/FRC HOMEPORT BASE KODIAK PHASE 1 AT KODIAK, AK.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | FDCC DET SEATTLE(00050) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | 70Z04718DWALSH100 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $34.8M |
| Current contract value | $34.8M |
| Potential contract value / ceiling | $36.0M |
| Start date | Aug 25, 2021 |
| Current end date | Jan 12, 2025 |
| Potential end date | Jan 12, 2025 |
| Latest award activity | Jan 23, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 19 of 19 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jan 23, 2026 | P00018 | $-0 | DEOBLIGATION OF REMAINING FUNDS DUE TO ROUNDING ERROR OF PRIOR INVOICES. TOTAL FUNDS TO DEOBLIGATE IS -$0.45. TOTAL CONTRACT NEEDS TO BE TOTALLY DEOBLIGATED TO FULLY CLOSE FILE. |
| Dec 2, 2025 | P00017 | $-36.3K | $36,284.46 DEOBLIGATION OF REMAINING UNUSED FUNDS FOR THE CONSTRUCT OPC FRC HOMEPORT BASE KODIAK PHASE 1, KODIAK, AK. RTWS INITIATIVE. |
| Jan 16, 2025 | P00016 | $-1.4M | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE $1,369,961.70. INCLUDED IN THIS DEOBLIGATION IS THE PFS AND CCTV LABOR EFFORTS. |
| Sep 4, 2024 | P00015 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE END DATE TO JANUARY 12, 2025. THIS IS A NO COST TASK ORDER CHANGE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Aug 29, 2024 | P00014 | $116.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CMR-32 FOR THE VALUE OF $116,571.00. |
| Jun 12, 2024 | P00013 | $4.3K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CMR-31 FOR THE VALUE OF $4,323.00. |
| May 28, 2024 | P00012 | $1.1M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CMR 30 FOR THE VALUE OF $1,055,695.00. |
| Apr 17, 2024 | P00011 | $31.8K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Mar 13, 2024 | P00010 | $36.3K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Mar 12, 2024 | P00009 | $-5.8K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Feb 28, 2024 | P00008 | $-289.8K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Feb 14, 2024 | P00007 | $114.9K | MOD P00007 FOR IN-SCOPE CHANGES CMR 28 |
| Jan 12, 2024 | P00006 | $99.4K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Sep 12, 2023 | P00005 | $856.1K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Aug 11, 2023 | P00004 | $199.0K | MOD P00004 FOR IN-SCOPE CHANGES CMRS 1, 15 17, 20, AND 21. |
| Feb 2, 2023 | P00003 | $97.3K | MOD P00003 FOR IN-SCOPE CHANGES CMRS 9, 11 12, AND 13. |
| Sep 30, 2022 | P00002 | $55.5K | MOD P0002 TO ISSUE THE FOLLOWING CMRS UNDER 52,243-4: CMR 3 - SURVEY COORDINATION WITH BASE KODIAK FOR MODIFIED NAD 26 DATUM - $34,553.00 CMR 6 - BUOY YARD STORM DRAINAGE CHANGE - $20,960.59 |
| Feb 3, 2022 | P00001 | $0 | ADMIN MOD TO AMEND KO INFORMATION IAW FSMS UPGRADE REQUIREMENTS. |
| Aug 25, 2021 | 0 | $33.8M | CONSTRUCT OPC/FRC HOMEPORT BASE KODIAK PHASE 1 AT KODIAK, AK. |