Federal contract award
70Z05021FOPCLA100
THE PURPOSE OF THIS TASK ORDER IS TO SUPPORT THE UNITED STATES COAST GUARD (USCG) THROUGH THE PROVISION OF DESIGN-BUILD CONSTRUCTION SERVICES FOR LALB OPC WATERFRONT CONSTRUCTION.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | FDCC DET SEATTLE(00050) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | 70Z04718DGILBAN00 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $37.2M |
| Current contract value | $37.2M |
| Potential contract value / ceiling | $37.2M |
| Start date | Oct 15, 2020 |
| Current end date | Dec 31, 2026 |
| Potential end date | Dec 31, 2026 |
| Latest award activity | Jul 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 29 of 29 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 14, 2026 | P00028 | $0 | NO COST MODIFICATION EXTENDING PERIOD OF PERFORMANCE ONLY TO ADDRESS ADMINISTRATIVE ITEMS. |
| Jun 11, 2026 | P00027 | $44.4K | TECHNICAL ACCEPTANCE OF CMR 39, PAYMENT TO LADWP. |
| Apr 23, 2026 | P00026 | $0 | NO COST EXTENSION FROM MARCH 31, 2026 TO JUNE 30, 2026. . |
| Mar 6, 2026 | P00025 | $204.4K | TECHNICAL ACCEPTANCE OF CMR 35-1 EXTENDED GC'S. |
| Feb 12, 2026 | P00024 | $95.2K | TECHNICAL ACCEPTANCE OF CMR 35 FOR TASKS ONLY - DOES NOT INCLUDE EXTENDED GENERAL CONDITIONS. TECHNICAL ACCEPTANCE FOR CMR 38 PROCESS PAYMENT TO LADWP. |
| Jan 28, 2026 | P00023 | $87.0K | TECHNICAL APPROVAL/ACCEPTANCE OF PROPOSAL FOR CMR 37_SUPPLEMENTAL PAYMENT TO LADWP. |
| Jun 23, 2025 | P00022 | $686.6K | UNILATERAL MODIFICATION: ACCEPTANCE OF PROPOSAL AMOUNT OF $686,579.83 FOR CMR 34: KTR FACILITATING $600,000.00 PAYMENT TO LADWP ON BEHALF OF THE CG. |
| Apr 9, 2025 | P00021 | $10.8K | ACCEPTANCE OF GILBANE PROPOSAL AMOUNT FOR CMR 33/REA 10 $10,759.42. |
| Jan 27, 2025 | P00020 | $4.2M | ACCEPT GILBANE CMR 15 12.20.24 PROPOSAL. POP EXTENDED TO 11.17.25. CLIN 0001 GILBANE SUBSTATION, $4,116,329.05, CLIN 0002, LADWP TRANSFORMER INSTALL 148 CALENDAR DAYS (SUBJECT TO LADWP PERFORMANCE) AT $303.85 PER DAY, $44,969.80. TOTAL $4,161,298.85 |
| Oct 28, 2024 | P00019 | $331.8K | $331,771.32 REA 11, MOD DEV, PREP, IMPLEMENT, ADV. ELECT, CLARK NEXSEN DESIGN, BOND, .66%, G&A 6.96%, PROFIT 10.28%, BOND PREM ADJUST 1.25%. |
| Oct 17, 2024 | P00018 | $455.9K | CMR 30: ACCEPTANCE OF CONTRACTOR PROPOSAL DATED 10SEP24 IN THE AMOUNT OF $455,926.39. |
| Jul 12, 2024 | P00017 | $0 | THE GOVT AND KTR RELEASE EACH OTHER FROM ANY AND ALL LIABILITY FOR FURTHER EQUITABLE ADJUSTMENTS ATTRIBUTABLE TO SUCH FACTS OR CIRCUMSTANCES GIVING RISE TO REA 13, REA 14, REA 15 AND MODIFICATION P00017 DATED 12 JUL 2024. |
| Jun 28, 2024 | P00016 | $89.0K | 89,000.00 IAW STORMWATER DRAINAGE DESIGN AND CONSTRUCTION DATED NOVEMBER 7, 2023 AND CIVILIAN BOARD OF CONTRACTS APPEAL #8065 DATED MARCH 29, 2024 |
| Jun 11, 2024 | P00015 | $483.0K | NOTICE TO PROCEED IN ACCORDANCE WITH CMR 15 TO PROVIDE A NEW SUBSTATION ENCLOSURE PER LAWPD APPROVED DESIGN DRAWINGS PROVIDED UNDER CMR-30. |
| Jun 6, 2024 | P00014 | $595.5K | IN ACCORDANCE WITH GILBANE'S SETTLEMENT LETTER DATED 24 MAY 2024, SERIAL LETTER NO. J35000TO03.098.1 TO SETTLE CLAIM AND APPEAL FOR THE AMOUNT OF $595,516.00, 85 CALENDAR DAYS FROM 15 OCT 2022 TO 09 JAN 2023. |
| Mar 4, 2024 | P00013 | $440.9K | REA 12, PILE OBSTRUCTION $440,922.81, NO EXTENDED GENERAL CONDITIONS, NO EXTENDED PERIOD OF PERFORMANCE. |
| Sep 11, 2023 | P00012 | $126.1K | CMR 30 $132,064.07 (UNILATERAL MODIFICATION) AND CMR 31 CREDIT $6,003.67 |
| Jul 20, 2023 | P00011 | $20.0K | SETTLEMENT, REA 7 SANDBLASTING EQUIPMENT CLAIM |
| Jun 2, 2023 | P00010 | $0 | NO COST UNILATERAL MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE FROM 22 JUNE 2023 TO 3 AUG 2024 DUE TO COVID CAUSED DELAYS FOR THE DELIVERY, COMMISSION, AND FINAL INSPECTION OF HITACHI TRANSFORMERS. |
| Feb 16, 2023 | P00009 | $12.4K | CMR 26 |
| Feb 13, 2023 | P00008 | $104.7K | CMR 23 |
| Jan 30, 2023 | P00007 | $92.5K | CMR 23 |
| Jan 18, 2023 | P00006 | $52.8K | CMR 24 |
| Sep 28, 2022 | P00005 | $0 | NO COST MODIFICATION TO EXTEND PERIOD OF PERFORMANCE FROM OCT. 2022 TO JUNE 2023. |
| Sep 2, 2022 | P00004 | $309.1K | CMR 7, 14, 17, 18/19 (REA 4/5), CMR20/REA 06 |
| Jun 24, 2022 | P00003 | $80.7K | MODIFICATION FOR CMR'S 05, 06, 07, 11, 13 AND REA 02 AND 03. |
| May 2, 2022 | P00002 | $307.9K | MODIFICATION TO EXTEND PERIOD OF PERFORMANCE TO 15 OCT 22 AND CMR 01: $295,877.63, CMR 02: CREDIT -$17,384.51, CMR 03: CREDIT $0.00, CMR 09: $2,497.56, CMR 10: CREDIT -$9,722.97, AND REA 1: $36,667.45. |
| Feb 1, 2022 | P00001 | $0 | OPC LALB WATERFRONT CONSTRUCTION: FSMS ADMIN MOD. |
| Oct 15, 2020 | 0 | $28.5M | THE PURPOSE OF THIS TASK ORDER IS TO SUPPORT THE UNITED STATES COAST GUARD (USCG) THROUGH THE PROVISION OF DESIGN-BUILD CONSTRUCTION SERVICES FOR LALB OPC WATERFRONT CONSTRUCTION. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
85/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 85/100. Available recorded signals: 80 points.
- Contract end 2026-12-31 (67 days from calculation)
- +35 points
- 14 historical awards in this buyer and category group
- +15 points
- 29 recorded award transactions
- +10 points
- Latest award action: 2026-07-14
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Gabriel D. Perez | Contact | gabriel.d.perez@uscg.mil 2062207424 | Source | Jul 1, 2020 |
| Gabriel D. Perez | Contact | gabriel.d.perez@uscg.mil 2062207424 | Source | Jun 10, 2020 |
| Gabriel D. Perez | Contact | gabriel.d.perez@uscg.mil 2062207424 | Source | Jun 10, 2020 |
| Gabriel D. Perez | Contact | gabriel.d.perez@uscg.mil 2062207424 | Source | Apr 7, 2020 |
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.