Federal contract award
70Z05022F43000013
THE PURPOSE OF THIS TASK ORDER IS TO PROVIDE A/E DESIGN, AND DEVELOP OF CONSTRUCTION DOCUMENTS TO CONSTRUCT NEW COVERED MOORINGS, FLOATING DOCK, AND CORRECT SHORELINE EROSION AT THE USCG STATION, SIUSLAW RIVER IN FLORENCE, OR.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | FDCC DET SEATTLE(00050) |
| NAICS | 541330 — Engineering Services |
| PSC | R425 — Engineering and Technical Services |
| Parent award / vehicle | 70Z05018DTRANSY01 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.4M |
| Current contract value | $2.4M |
| Potential contract value / ceiling | $2.4M |
| Start date | Sep 16, 2022 |
| Current end date | Feb 15, 2026 |
| Potential end date | Feb 15, 2026 |
| Latest award activity | Dec 20, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 20, 2025 | P00011 | $100.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REA-08 FOR THE VALUE OF $99,954.44. |
| Aug 20, 2025 | P00010 | $98.1K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CMR-06 FOR THE VALUE OF $98,130.36. |
| Dec 18, 2024 | P00009 | $-37.1K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF -$37,064.78 FROM THE AWARD AND PROVIDE A NO COST EXTENSION OF THE PERIOD OF PERFORMANCE TO END ON FEBRUARY 15, 2026. |
| Sep 26, 2024 | P00008 | $111.4K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSAL DESIGN B CHANGES IN SCOPE TO STA SIUSLAW MLB MOORING PROJECT FOR THE VALUE OF $111,379.58. |
| Apr 23, 2024 | P00007 | $29.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED 100% SCOPE FOR THE VALUE OF $38,845.14. |
| Apr 10, 2024 | P00006 | $38.8K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED 100% SCOPE FOR THE VALUE OF $38,845.14. |
| Feb 15, 2024 | P00005 | $25.2K | THE PURPOSE OF THIS MODIFICATION IS FOR ADDITIONAL PERMITTING CONSULTATION AND AGENCY FEES AND CHANGE THE PERIOD OF PERFORMANCE DATE TO END ON MARCH 21, 2024. |
| May 25, 2023 | P00004 | $1.1K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE DEQ FEES FOR THE VALUE OF $1,145.56. |
| Apr 28, 2023 | P00003 | $7.9K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE GEOTECHNICAL PERMITTING CONSULTATION FOR $7,940.27 RELATED TO THE USCG STATION SIUSLAW PROJECT. |
| Apr 20, 2023 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE UNI OF MEASURE (UOM) IN THE LINES TAB. THIS A NO COST MODIFICATION. |
| Apr 13, 2023 | P00001 | $32.5K | THE PURPOSE OF THIS MODIFICATION TO PROVIDE ADDITIONAL SCOUR STUDY FOR $32,511.94 FOR THE STATION SIUSLAW PROJECT. |
| Mar 13, 2023 | A00001 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO PUSH THE IPP TO VERIFY THE CONTRACTOR, AS PER FSMS INCIDENT 0124519. THIS IS A NO COST ADMINISTRATIVE MODIFICATION. |
| Sep 16, 2022 | 0 | $2.0M | THE PURPOSE OF THIS TASK ORDER IS TO PROVIDE A/E DESIGN, AND DEVELOP OF CONSTRUCTION DOCUMENTS TO CONSTRUCT NEW COVERED MOORINGS, FLOATING DOCK, AND CORRECT SHORELINE EROSION AT THE USCG STATION, SIUSLAW RIVER IN FLORENCE, OR. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.