Federal contract award

70Z05022F43000013

THE PURPOSE OF THIS TASK ORDER IS TO PROVIDE A/E DESIGN, AND DEVELOP OF CONSTRUCTION DOCUMENTS TO CONSTRUCT NEW COVERED MOORINGS, FLOATING DOCK, AND CORRECT SHORELINE EROSION AT THE USCG STATION, SIUSLAW RIVER IN FLORENCE, OR.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeFDCC DET SEATTLE(00050)
NAICS541330 — Engineering Services
PSCR425 — Engineering and Technical Services
Parent award / vehicle70Z05018DTRANSY01
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.4M
Current contract value$2.4M
Potential contract value / ceiling$2.4M
Start dateSep 16, 2022
Current end dateFeb 15, 2026
Potential end dateFeb 15, 2026
Latest award activityDec 20, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 20, 2025P00011$100.0KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REA-08 FOR THE VALUE OF $99,954.44.
Aug 20, 2025P00010$98.1KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CMR-06 FOR THE VALUE OF $98,130.36.
Dec 18, 2024P00009$-37.1KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF -$37,064.78 FROM THE AWARD AND PROVIDE A NO COST EXTENSION OF THE PERIOD OF PERFORMANCE TO END ON FEBRUARY 15, 2026.
Sep 26, 2024P00008$111.4KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSAL DESIGN B CHANGES IN SCOPE TO STA SIUSLAW MLB MOORING PROJECT FOR THE VALUE OF $111,379.58.
Apr 23, 2024P00007$29.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED 100% SCOPE FOR THE VALUE OF $38,845.14.
Apr 10, 2024P00006$38.8KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED 100% SCOPE FOR THE VALUE OF $38,845.14.
Feb 15, 2024P00005$25.2KTHE PURPOSE OF THIS MODIFICATION IS FOR ADDITIONAL PERMITTING CONSULTATION AND AGENCY FEES AND CHANGE THE PERIOD OF PERFORMANCE DATE TO END ON MARCH 21, 2024.
May 25, 2023P00004$1.1KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE DEQ FEES FOR THE VALUE OF $1,145.56.
Apr 28, 2023P00003$7.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE GEOTECHNICAL PERMITTING CONSULTATION FOR $7,940.27 RELATED TO THE USCG STATION SIUSLAW PROJECT.
Apr 20, 2023P00002$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE UNI OF MEASURE (UOM) IN THE LINES TAB. THIS A NO COST MODIFICATION.
Apr 13, 2023P00001$32.5KTHE PURPOSE OF THIS MODIFICATION TO PROVIDE ADDITIONAL SCOUR STUDY FOR $32,511.94 FOR THE STATION SIUSLAW PROJECT.
Mar 13, 2023A00001$0THE PURPOSE OF THIS MODIFICATION IS TO PUSH THE IPP TO VERIFY THE CONTRACTOR, AS PER FSMS INCIDENT 0124519. THIS IS A NO COST ADMINISTRATIVE MODIFICATION.
Sep 16, 20220$2.0MTHE PURPOSE OF THIS TASK ORDER IS TO PROVIDE A/E DESIGN, AND DEVELOP OF CONSTRUCTION DOCUMENTS TO CONSTRUCT NEW COVERED MOORINGS, FLOATING DOCK, AND CORRECT SHORELINE EROSION AT THE USCG STATION, SIUSLAW RIVER IN FLORENCE, OR.