Federal contract award

70Z08222FABCD0019

DESIGN-BUILD RELOCATE UTILITIES PIER P AT NSC PIER PAPA IN CHARLESTON, SC

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeCEU MIAMI(00082)
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2PZ — REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicle70Z08219DPMV10500
Set-aside8A COMPETED
Pricing typeFIRM FIXED PRICE
Obligations$601.2K
Current contract value$601.2K
Potential contract value / ceiling$601.2K
Start dateJun 15, 2022
Current end dateApr 7, 2025
Potential end dateApr 7, 2025
Latest award activityMar 27, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 27, 2025P00012$20.7KTHIS MODIFICATION IS ISSUED FOR A TIME EXTENSION AND ADDITIONAL COST FOR TEMPORARY LIGHTING ON THE PIER.
Jan 23, 2025P00011$13.8KTHIS MODIFICATION IS ISSUED FOR A TIME EXTENSION AND ADDITIONAL COST FOR TEMPORARY LIGHTING ON THE PIER.
Jul 12, 2024P00010$0THIS NO COST TIME EXTENSION IS BEING ISSUED TO ALLOW THE GOVERNMENT SUFFICIENT TIME TO PROCESS AN UPCOMING MODIFICATION TO EXTEND TERM OF TEMPORARY LIGHTING
Apr 22, 2024P00009$18.9KCONTRACTOR SHALL PROVIDE ALL TOOLS, LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION NECESSARY TO PROVIDE TEMPORARY LIGHTING AT THE WORK SITE.
Apr 2, 2024P00008$0NO COST TIME EXTENSION AN UPDATE COR.
Nov 15, 2023P00007$0DUE TO DIFFERING SITE CONDITIONS, THIS NO COST TIME EXTENSION IS BEING ISSUED TO ALLOW THE CONTRACTOR TO RESUME THE DESIGN-BUILD PROJECT.
Aug 21, 2023P00006$0NO COST TIME EXTENSION TO ALLOW CONTRACTOR TO PREPARE AN RFI REQUIRED FOR THE NEW LOCATION OF CONSTRUCTION.
May 9, 2023P00005$53.6KCONTRACTOR SHALL PROVIDE ALL TOOLS, LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION NECESSARY TO PERFORM ADDITIONAL WORK FOR A TOTAL OF $53,628.90 IN ACCORDANCE WITH THE MODIFICATION SCOPE OF WORK.
Apr 10, 2023P00004$0THIS NO COST TIME EXTENSION IS BEING ISSUED TO ALLOW THE GOVERNMENT SUFFICIENT TIME TO ROUTE THE MODIFICATION PACKET FOR ADDITIONAL WORK.
Mar 4, 2023P00003$0THIS NO COST TIME EXTENSION IS BEING ISSUED TO ALLOW THE GOVERNMENT SUFFICIENT TIME TO OBTAIN FUNDS FOR ADDITIONAL WORK.
Feb 3, 2023P00002$0DESIGN-BUILD RELOCATE UTILITIES PIER P AT NSC PIER PAPA IN CHARLESTON, SC
Dec 13, 2022P00001$0DESIGN-BUILD RELOCATE UTILITIES PIER P AT NSC PIER PAPA IN CHARLESTON, SC
Jun 14, 20220$494.1KDESIGN-BUILD RELOCATE UTILITIES PIER P AT NSC PIER PAPA IN CHARLESTON, SC

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.