Federal contract award
70Z08324FYARD0002
ROOF REPAIRS (FY23) U.S. COAST GUARD YARD BALTIMORE, MARYLAND
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | CEU CLEVELAND(00083) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | 70Z08318DPCR07100 |
| Set-aside | SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.3M |
| Current contract value | $1.3M |
| Potential contract value / ceiling | $1.3M |
| Start date | Jul 26, 2024 |
| Current end date | Sep 30, 2025 |
| Potential end date | Sep 30, 2025 |
| Latest award activity | Jul 23, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 23, 2025 | P00005 | $83.4K | EXTEND THE POP TO 9/30/25 AND PROVIDE COMPREHENSIVE REPAIRS TO BUILDING 3. |
| May 5, 2025 | P00004 | $0 | MOD IS TO: EXTEND THE POP TO 6/30/25.THIS MODIFICATION CONSTITUTES FULL AND COMPLETE COMPENSATION FOR ALL COSTS AND DELAYS ARISING FROM THIS CHANGE. |
| Feb 27, 2025 | P00003 | $0 | MOD IS TO: CHANGE KO TO CHERYL BERRY; EXTEND THE POP TO 5/2/25.THIS MODIFICATION CONSTITUTES FULL AND COMPLETE COMPENSATION FOR ALL COSTS AND DELAYS ARISING FROM THIS CHANGE. |
| Nov 26, 2024 | P00002 | $0 | MOD IS TO: CHANGE KO TO CHAD MESSER; EXTEND THE POP TO 2/18/25.THIS MODIFICATION CONSTITUTES FULL AND COMPLETE COMPENSATION FOR ALL COSTS AND DELAYS ARISING FROM THIS CHANGE. |
| Sep 25, 2024 | P00001 | $275.6K | MOD IS TO: EXERCISE OPTION ITEM 4 INCORPORATE CR #1 OPTION 1 FOR ROOF REPAIRS OF BUILDING 88A EXTEND THE POP TO 12/30/24.THIS MODIFICATION CONSTITUTES FULL AND COMPLETE COMPENSATION FOR ALL COSTS AND DELAYS ARISING FROM THIS CHANGE. |
| Jul 25, 2024 | 0 | $977.3K | ROOF REPAIRS (FY23) U.S. COAST GUARD YARD BALTIMORE, MARYLAND |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.