Federal contract award
70Z08523CIBCT0025
USCGC SMILAX DRYDOCK REPAIRS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | SFLC PROCUREMENT BRANCH 2(00085) |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | J998 — Non-nuclear Ship Repair (East) Ship repair (including overhauls and conversions) performed on non-nuclear propelled and nonpropelled ships east of the 108th meridian |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.2M |
| Current contract value | $2.2M |
| Potential contract value / ceiling | $2.2M |
| Start date | Jun 19, 2023 |
| Current end date | Aug 21, 2026 |
| Potential end date | Aug 21, 2026 |
| Latest award activity | Jul 23, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 23, 2026 | P00009 | $-360 | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION P00009 MODIFICATION TO DE-OBLIGATE FUNDS NO LONGER NEEDED. |
| Dec 11, 2023 | P00008 | $605 | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION P00008 FOR REPLACEMENT OF BULKHEAD SEALS AND CONTRACT EXTENSION. |
| Nov 3, 2023 | P00007 | $14.1K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION P00007 FOR BERTHING/AMR HOLES BELZONA, HPU SEA VALES SPACER GASKET AND CRANE PIPE REPAIR AND SPILL CLEAN UP. |
| Oct 23, 2023 | P00006 | $-56.0K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION P00006 TO EXTEND THE PERIOD OF PERFORMANCE END DATE TO 7 NOVEMBER 23 AND TO DEOBLIGATE $55,963.76 FROM LINE 013 FOR CONTRACT CHANGE REQUEST 023 |
| Sep 26, 2023 | P00004 | $61.5K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION FOR PORT AND STARBOARD SHAFT SEALS AND INSTALLATION. |
| Sep 26, 2023 | P00005 | $26.6K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION FOR PORT AND STARBOARD COOPER BEARINGS INSTALLATION AND PORT FUEL TANK WELD REPAIRS. |
| Sep 8, 2023 | P00003 | $684.1K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION FOR PORT STERN TUBES BELZONA REPAIRS, UW HULL REPLACEMENT, PIPE CLEANING, PBM BALL VALVES, SUCTION STRAINER WITH AN CONTRACT EXTENSION TO OCTOBER 31, 2023. |
| Aug 14, 2023 | P00002 | $27.4K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION FOR NEW SEA VALVES, WASTER PIECE, FOREPEAK POTABLE WATER TANK GOOSENECK, BUOY DECK HATCH AND DUPLEX STOCK STRAINER STRONG BACK BOLTS. |
| Jun 1, 2023 | 0 | $1.4M | USCGC SMILAX DRYDOCK REPAIRS |
| Jun 1, 2023 | P00001 | $92.8K | USCGC SMILAX DRYDOCK REPAIRS MODIFICATION FOR ADDITIONAL FUEL ONBOARD, CUTLASS BEARINGS AND REPLACEMENT OF PORT & STARBOARD RUDDER UPPER CARRIER BEARINGS. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.