THE PURPOSE OF THIS CONTRACT IS TO PROCURE DOCKSIDE REPAIRS FOR THE USCGC BERTHIOLF IN ACCORDANCE WITH THE USCGC BERTHOLF (WMSL 750) SPECIFICATION FOR DOCKSIDE REPAIRS FY2026 DATED 09 OCTOBER 2025.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Homeland Security |
| Office | SFLC PROCUREMENT BRANCH 2(00085) |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | J999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.6M |
| Current contract value | $1.6M |
| Potential contract value / ceiling | $1.6M |
| Start date | Apr 21, 2026 |
| Current end date | Jun 20, 2026 |
| Potential end date | Jun 20, 2026 |
| Latest award activity | Jun 25, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 25, 2026 | P00005 | $106.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CHANGE REQUESTS 013 THROUGH 021. |
| Jun 16, 2026 | P00003 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE POP TO 18 JUNE 2026. VERBAL AUTHORIZATION GIVEN ON 10 JUNE 2026. |
| May 10, 2026 | P00002 | $208.7K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CR-002, CR-003, CR-006, CR-007, CR-008, CR-009, CR-010, CR-011, AND CR-012, RESULTING IN A NET CONTRACT INCREASE OF $208,662.00. |
| Apr 24, 2026 | P00001 | $-57.7K | THE PURPOSE OF THIS MODIFICATION IS TO REVISE WORK ITEM (WI) D-10 TO REMOVE THE REQUIREMENT FOR AC VALVES FROM THE SCOPE OF WORK. THE COAST GUARD WILL FURNISH THE AC VALVES AS GOVERNMENT-FURNISHED MATERIEL (GFM).NO OTHER CHANGES ARE MADE. |
| Feb 18, 2026 | 0 | $1.3M | THE PURPOSE OF THIS CONTRACT IS TO PROCURE DOCKSIDE REPAIRS FOR THE USCGC BERTHIOLF IN ACCORDANCE WITH THE USCGC BERTHOLF (WMSL 750) SPECIFICATION FOR DOCKSIDE REPAIRS FY2026 DATED 09 OCTOBER 2025. |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Wayne Gutman | Contact | wayne.m.gutman@uscg.mil 8327093439 | Source | Jan 12, 2026 |
| Robin B. Kloeppel | Contact | robin.b.kloeppel@uscg.mil 2068274342 | Source | Jan 12, 2026 |
| Wayne Gutman | Contact | wayne.m.gutman@uscg.mil 8327093439 | Source | Jan 8, 2026 |
| Robin B. Kloeppel | Contact | robin.b.kloeppel@uscg.mil 2068274342 | Source | Jan 8, 2026 |
| Wayne Gutman | Contact | wayne.m.gutman@uscg.mil 8327093439 | Source | Jan 8, 2026 |
| Robin B. Kloeppel | Contact | robin.b.kloeppel@uscg.mil 2068274342 | Source | Jan 8, 2026 |
| Wayne Gutman | Contact | wayne.m.gutman@uscg.mil 8327093439 | Source | Dec 12, 2025 |
| Robin B. Kloeppel | Contact | robin.b.kloeppel@uscg.mil 2068274342 | Source | Dec 12, 2025 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.