Federal contract award

70Z08724FKODI0011

KODIAK GALLEY M&R AWARD

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeCEU JUNEAU(00087)
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AZ — REPAIR OR ALTERATION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicle70Z08718DPJT24300
Set-asideHUBZONE SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$7.0M
Current contract value$7.0M
Potential contract value / ceiling$7.0M
Start dateApr 8, 2024
Current end dateAug 30, 2026
Potential end dateAug 30, 2026
Latest award activityAug 5, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Aug 5, 2026P00012$14.7KTHE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE PERIOD OF PERFORMANCE ON ALL CLINS AND CORRECT THE DISTRIBUTION TAB ON MOD P00010.
Jun 9, 2026P00011$0NO COST TIME EXTENSION
May 27, 2026P00010$0P00010 SETTLEMENT OF REQUEST FOR EQUITABLE ADJUSTMENT
Mar 23, 2026P00009$0P00009 NO COST TIME EXTENSION
Jan 9, 2026P00008$9.5KP00008 EF-8 VFD
Oct 29, 2025P00007$528.4KP00007 WATER LINE MODIFICATION
Sep 16, 2025P00006$64.9KP00005 GLYCOL SYSTEM
May 20, 2025P00005$111.2KP00005 GLYCOL SYSTEM
May 14, 2025P00004$0P00004 CORRECT IPP
May 12, 2025P00003$98.9KP00003 ADD WORK WITHIN SCOPE AND ADD FUNDS
Apr 11, 2025A00001$0A00001 UPDATE UOM AND CHANGE COR
Mar 27, 2025P00002$125.0KMOD P00002 ADD WORK WITHIN SCOPE, ADD FUNDS AND CORRECT PERIOD OF PERFORMANCE.
Aug 28, 2024P00001$128.8KKODIAK GALLEY M&R AWARD
Apr 8, 20240$5.9MKODIAK GALLEY M&R AWARD

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.