Federal contract award

70Z0G121C3RX00100

PLYMOUTH GURNET LIGHT - PHASE I AND II SITE INVESTIGATION AND SOIL REMEDIATION

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeCEU PROVIDENCE(000G1)
NAICS562910 — Remediation Services
PSCZ1QA — MAINTENANCE OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$1.4M
Current contract value$1.4M
Potential contract value / ceiling$1.4M
Start dateDec 23, 2020
Current end dateDec 31, 2025
Potential end dateDec 31, 2025
Latest award activityOct 23, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Oct 23, 2025P00013$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE THROUGH DECEMBER 31, 2025 TO OBTAIN THE CERTIFICATE OF COMPLIANCE REQUIRED TO FILE WITH THE PLYMOUTH COUNTY REGISTRY OF DEEDS.
Aug 29, 2025P00012$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE THROUGH OCTOBER 31, 2025 DUE TO DRY SOIL PREVENTING SEEDLING GROWTH.
Jun 17, 2025P00011$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE THROUGH AUGUST 31, 2025, DUE TO INCLEMENT WEATHER POSTPONING THE INSTALLATION OF PLANTINGS TO BE IN COMPLIANCE WITH THE PLYMOUTH CONSERVATION COMMISSION.
Jan 23, 2025P00010$0THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO CHANGE THE COR TO NICOLE WAGNER.
Dec 5, 2024P00009$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO JUNE 30, 2025 TO ALLOW SUFFICIENT TIME TO ESTABLISH FULL GRASS GROWTH AND INSTALL PLANTINGS IN ORDER TO BE COMPLIANT WITH THE PLYMOUTH CONSERVATION COMMISSION.
Aug 5, 2024P00008$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE THROUGH OCTOBER 31, 2024 IN ORDER TO ALLOW SUFFICIENT TIME TO ESTABLISH FULL GRASS GROWTH AND INSTALL PLANTINGS.
Feb 28, 2024P00007$14.4KTHE PURPOSE OF THIS MODIFICATION IS TO INCREASE FUNDING IN THE AMOUNT OF $14,416.00 FOR A SOIL DISPOSAL FEE TO DISPOSE OF 155 TONS OF CONTAMINATED SOIL TO A LANDFILL IN NEW HAMPSHIRE.
Aug 30, 2023P00006$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO INCREASE FUNDING IN THE AMOUNT OF $1,061,011.00 TO CONDUCT THE SOIL REMEDIATION AT PLYMOUTH GURNET LIGHT IN PLYMOUTH, MA.
Feb 13, 2023P00005$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE TO MARCH 31, 2023 TO AWAIT COMMENT ON THE ARCHEOLOGICAL REPORT SUBMITTED TO THE MASSACHUSETTS HISTORICAL COMMISSION (MHC) FOR REVIEW.
Sep 14, 2022P00004$7.2KTHE PURPOSE OF THIS MODIFICATION IS TO ADD AN ADDITIONAL 1,000 ARTIFACTS FOR COLLECTION AND PROCESSING DUE TO THE DISCOVERY OF ARTIFACT RICH DEPOSITS AT THE SITE AND EXTEND CONTRACT COMPLETION DATE TO JANUARY 31, 2023.
May 24, 2022P00003$103.6KTO CONDUCT A SITE EXAMINATION ARCHAEOLOGICAL SURVEY FOR THE CURRENT PROJECTED REMEDIATION LOCATIONS AT PLYMOUTH GURNET LIGHT SITE WHICH IS MANDATED BY THE MASSACHUSETTS HISTORICAL COMMISSION (MHC).
Aug 26, 2021P00002$37.5KPHASE I AND PHASE II ENVIRNOMENTAL SITE ASSESSMENT AND REMEDIATION FOR PLYMOUTH GURNET LIGHT AND POTENTIAL REMEDIATION - PSN 15477979.
Jun 3, 2021P00001$37.1KPHASE I AND PHASE II ENVIRNOMENTAL SITE ASSESSMENT AND REMEDIATION FOR PLYMOUTH GURNET LIGHT AND POTENTIAL REMEDIATION - PSN 15477979.
Dec 23, 20200$116.4KPLYMOUTH GURNET LIGHT - PHASE I AND II SITE INVESTIGATION AND SOIL REMEDIATION