Federal contract award
75H70118F30001
IGF::OT::IGF TASK ORDER FOR AE DESIGN SERVICES FOR DESIGN OF APARTMENT COMPLEX FOR THE CROW NORTHERN CHEYENNE HOSPITAL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Health and Human Services |
| Office | DIV OF ENGINEERING SVCS - SEATTLE |
| NAICS | 541330 — Engineering Services |
| PSC | C1FZ — ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER RESIDENTIAL BUILDINGS |
| Parent award / vehicle | 75H70118D00005 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $694.5K |
| Current contract value | $694.5K |
| Potential contract value / ceiling | $694.5K |
| Start date | Sep 26, 2018 |
| Current end date | Jul 1, 2026 |
| Potential end date | Jul 1, 2026 |
| Latest award activity | Mar 17, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 17, 2026 | P00009 | $5.3K | DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Jul 22, 2025 | P00008 | $21.5K | DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Sep 23, 2024 | P00007 | $63.9K | DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Feb 14, 2024 | P00006 | $21.4K | MOD6 PIER TESTING - DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Nov 30, 2023 | P00005 | $0 | MOD5 ADD IPP UPDATE COR (ADMINISTRATIVE) DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Sep 19, 2023 | P00004 | $0 | MOD4 TO EXTEND THE PERIOD OF PERFORMANCE FOR DESIGN FOR AN 18-UNIT APARTMENT BUILDING, CROW, MT |
| Jan 26, 2021 | P00003 | $0 | MOD TO EXTEND THE PERIOD OF PERFORMANCE |
| Jun 12, 2019 | P00002 | $2.9K | THE DESIGN PROCESS IDENTIFIED A FAILED SEWER LINE REQUIRING ANOTHER ROUND OF SURVEY WORK BEYOND THE ORIGINAL SOW AND MOD 1. THE EXPANDED SURVEY SCOPE SURVEYS AN EXISTING SANITARY SEWER LINE REQUIRING REPAIR, AND ADDITIONAL PROPERTY TO THE SOUTH OF MOD 1 SURVEY. |
| Dec 20, 2018 | P00001 | $149.1K | IGF::OT::IGF TASK ORDER FOR AE DESIGN SERVICES FOR DESIGN OF APARTMENT COMPLEX FOR THE CROW NORTHERN CHEYENNE HOSPITAL |
| Sep 26, 2018 | 0 | $430.4K | IGF::OT::IGF TASK ORDER FOR AE DESIGN SERVICES FOR DESIGN OF APARTMENT COMPLEX FOR THE CROW NORTHERN CHEYENNE HOSPITAL |