Federal contract award

75H70124C00009

THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, SUPPLIES, AND SERVICES TO EXPAND THE EXISTING WAITING ROOM AND PARKING LOT IN ACCORDANCE WITH THE SOW, SPECIFICATIONS, DRAWINGS, AND OTHER DOCUMENTS INCORPORATED VIA AMENDMENT TO THE SOLICITATION.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Health and Human Services
OfficeDIV OF ENGINEERING SVCS - SEATTLE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1DA — CONSTRUCTION OF HOSPITALS AND INFIRMARIES
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$2.2M
Current contract value$2.2M
Potential contract value / ceiling$2.2M
Start dateFeb 16, 2024
Current end dateOct 31, 2025
Potential end dateOct 31, 2025
Latest award activitySep 30, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 30, 2025P00008$0MODIFICATION 8 TO UPDATE PERIOD OF PERFORMANCE END DATE.
Aug 26, 2025P00007$0MODIFICATION 7 TO UPDATE PERIOD OF PERFORMANCE END DATE.
May 30, 2025P00006$0MODIFICATION 6 TO UPDATE PERIOD OF PERFORMANCE END DATE.
Oct 22, 2024P00005$96.7KMODIFICATION 4 FOR ADDITIONAL WORK RELATED TO CORRECT SITE DEFICIENCIES AND INSTALL UTILITIES.
Jul 17, 2024P00004$40.0KMODIFICATION 4 FOR ADDITIONAL WORK RELATED TO CORRECT SITE DEFICIENCIES AND INSTALL UTILITIES.
Jun 21, 2024P00003$463.7KMODIFICATION 3 FOR ADDITIONAL WORK RELATED TO CORRECT SITE DEFICIENCIES AND INSTALL UTILITIES.
Jun 10, 2024P00002$14.3KMODIFICATION 2 FOR ADDITIONAL WORK RELATED TO RFI 8 STRIPING AND RFI 11 GRADING.
Apr 22, 2024P00001$0MODIFICATION 1 TO ADMINISTRATIVELY CORRECT COR OF RECORD IN PRISM.
Feb 16, 20240$1.6MTHE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, SUPPLIES, AND SERVICES TO EXPAND THE EXISTING WAITING ROOM AND PARKING LOT IN ACCORDANCE WITH THE SOW, SPECIFICATIONS, DRAWINGS, AND OTHER DOCUMENTS INCORPORATED VIA AMENDMENT TO THE SOLICITATION.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.