C104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP COR - ANDREW GOMES CO - PETE MILLER CS - DAVID SEID VENDOR POC - DAVID FREDERICK

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Health and Human Services
OfficeNIH A E CONSTRUCTION
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$5.2M
Current contract value$5.2M
Potential contract value / ceiling$5.2M
Start dateSep 14, 2021
Current end dateJan 31, 2026
Potential end dateJan 31, 2026
Latest award activityDec 3, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 3, 2025P00008$0C104037/C112350 MOD 07 TO EXTEND THE PERIOD OF PERFORMANCE THROUGH 6/30/2025 AT NO COST TO THE GOVERNMENT. COR - ANDREW GOMES CO - CHRIS POSTEK VENDOR POC - DAVID FREDERICK
Nov 14, 2024P00007$0C104037/C112350 MOD 07 TO EXTEND THE PERIOD OF PERFORMANCE THROUGH 6/30/2025 AT NO COST TO THE GOVERNMENT. COR - HAITAO MA CO - DAN BURK CS - DAVID SEID VENDOR POC - DAVID FREDERICK
Mar 25, 2024P00006$0C104037/C112350 MOD 06 TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO4 SOW AND EXTEND THE PERIOD OF PERFORMANCE THROUGH 10/15/2024. COR - HAITAO MA CO - DAN BURK CS - DAVID SEID VENDOR POC - DAVID FREDERICK
Jan 8, 2024P00005$29.8KC104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP MOD 05 TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO3 SOW AND EXTEND THE PERIOD OF PERFORMANCE THROUGH 6/30/2024.
Sep 18, 2023P00004$66.3KC104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP MOD 04 TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO2 SOW AND EXTEND THE PERIOD OF PERFORMANCE THROUGH 2/29/2024.
Dec 5, 2022P00003$0C104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP MOD 03 TO ADD IPP LANGUAGE AND EXTEND POP AT NO COST. COR - ANDREW GOMES CO - DAN BURK CS - DAVID SEID VENDOR POC -
Jun 28, 2022P00002$89.2KC104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP MOD 02 TO ADD SUPPLEMENTAL WORK WITHIN SCOPE AS OUTLINED IN THE CO#1 SOW. COR - ANDREW GOMES CO - DAN BURK CS - DAVI
Nov 2, 2021P00001$0EO14042 C104037/C112350 MOD 01 TO ADD COVID CLAUSE PER EO14042. COR - ANDREW GOMES CO - DAN BURK CS - DAVID SEID VENDOR POC - DAVID FREDERICK
Sep 14, 20210$5.0MC104037/C112350 CONSTRUCT FULLY FUNCTIONAL AND OPERATIONAL SIDE STREAM FILTERS FOR GROUPS 2 AND 3 COOLING TOWERS, BUILDING 11, CUP COR - ANDREW GOMES CO - PETE MILLER CS - DAVID SEID VENDOR POC - DAVID FREDERICK

Research next steps