Federal contract award
75N99023C00070
C107747 - CONSTRUCTION SERVICES - NHLBI BLDG 14E MURINE PHENOTYPING CORE (MPC) RENOVATION - CHETNA GOLA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Health and Human Services |
| Office | NIH A E CONSTRUCTION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.7M |
| Current contract value | $2.7M |
| Potential contract value / ceiling | $2.7M |
| Start date | Sep 15, 2023 |
| Current end date | Sep 1, 2026 |
| Potential end date | Sep 1, 2026 |
| Latest award activity | Feb 25, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 25, 2026 | P00003 | $202.0K | C107747 - THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CHANGES RELATED TO RFI 037 RESPONSES AND ADDITIONAL EFFORTS REQUIRED FOR CONCEALED UTILITY LINE RELOCATION. THE PERIOD OF PERFORMANCE IS ALSO EXTENDED 184 CALENDAR DAYS TO ACCOMMODATE THE C |
| Aug 27, 2025 | P00002 | $271.5K | THE CONTRACT ACTION IS ESSENTIAL TO PROCUREMENT AND ALLOWED TO PROCEED AS A CONSTRUCTION CHANGE ORDER TO ADDRESS INCORPORATION OF REVISED DRAWINGS AND SPECIFICATIONS ISSUED 30 JAN 24 AND SETTLEMENT OF REQUESTED FOR EQUITABLE ADJUSTMENT. |
| Mar 6, 2025 | P00001 | $0 | C107747 - CONSTRUCTION SERVICES - NHLBI BLDG 14E MURINE PHENOTYPING CORE (MPC) RENOVATION - CHETNA GOLA |
| Sep 18, 2023 | 0 | $2.2M | C107747 - CONSTRUCTION SERVICES - NHLBI BLDG 14E MURINE PHENOTYPING CORE (MPC) RENOVATION - CHETNA GOLA |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.