Federal contract award

75N99023F00001

UPGRADING THE PLAYGROUND AND REPLACING PLAYGROUND EQUIPMENT TO SERVE THE TARGETED AGE GROUP ATTENDING THE BUILDING 64 EAST CHILD CARE CENTER. THE UPGRADES ARE AIMED AT MEETING THE NEW NAEYC ACCREDITATION REQUIREMENTS. DRAINAGE AND EROSION ISSUES WILL

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Health and Human Services
OfficeNIH A E CONSTRUCTION
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicle75N99019D00028
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.7M
Current contract value$2.7M
Potential contract value / ceiling$2.7M
Start dateSep 7, 2023
Current end dateJun 1, 2026
Potential end dateJun 1, 2026
Latest award activityMar 23, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 23, 2026P00006$0C109148 MOD. IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE 184 CALENDAR DAYS, FROM 11/29/2025 TO 06/01/2026. THIS TIME EXTENSION IS PROVIDED AT NO COST TO EITHER THE CONTRACTOR OR THE GOVERNMENT.
Sep 30, 2025P00005$144.5KC109148 MOD. IS TO REMOVE EXISTING ASPHALT TO BASE, ADD AGGREGATE TO GRADE, REINSTALL BASE AND SURFACE ASPHALT COURSES. THE CONTRACT ACTION IS ESSENTIAL TO PROCUREMENT TO ADDRESS FLOOD PREVENTION & BACKFLOW OF RAINWATER INTO THE ROAD.
Aug 26, 2025P00004$184.6KTHE REASON FOR MODIFICATION IS TO INCLUDE VARIOUS CONSTRUCTION CHANGE ORDERS DUE TO ADDITIONAL REQUESTED PLAYGROUND UPGRADES AND FLOODING PREVENTION. A 120 CALENDAR DAY EXTENSION IS INCLUDED TO ACCOMMODATE THE REQUESTED CHANGES.
May 20, 2025P00003$140.8KUPGRADING THE PLAYGROUND AND REPLACING PLAYGROUND EQUIPMENT TO SERVE THE TARGETED AGE GROUP ATTENDING THE BUILDING 64 EAST CHILD CARE CENTER.
Sep 24, 2024P00002$68.6KUPGRADING THE PLAYGROUND AND REPLACING PLAYGROUND EQUIPMENT TO SERVE THE TARGETED AGE GROUP ATTENDING THE BUILDING 64 EAST CHILD CARE CENTER. THE UPGRADES ARE AIMED AT MEETING THE NEW NAEYC ACCREDITATION REQUIREMENTS. DRAINAGE AND EROSION ISSUES WILL
Aug 1, 2024P00001$48.6KUPGRADING THE PLAYGROUND AND REPLACING PLAYGROUND EQUIPMENT TO SERVE THE TARGETED AGE GROUP ATTENDING THE BUILDING 64 EAST CHILD CARE CENTER. THE UPGRADES ARE AIMED AT MEETING THE NEW NAEYC ACCREDITATION REQUIREMENTS. DRAINAGE AND EROSION ISSUES WILL
Sep 7, 20230$2.1MUPGRADING THE PLAYGROUND AND REPLACING PLAYGROUND EQUIPMENT TO SERVE THE TARGETED AGE GROUP ATTENDING THE BUILDING 64 EAST CHILD CARE CENTER. THE UPGRADES ARE AIMED AT MEETING THE NEW NAEYC ACCREDITATION REQUIREMENTS. DRAINAGE AND EROSION ISSUES WILL