75N99023F00003
C112405- BLDG. 49 EXTERIOR ENVELOP REPAIRS: THIS PROJECT CONSISTS OF PROVIDING A DESIGN TO ADDRESS DEFICIENCY FOUND IN THE SMITH GROUP FINAL ASSESSMENT REPORT FOR BLDG. 49.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Health and Human Services |
| Office | NIH A E CONSTRUCTION |
| NAICS | 541330 — Engineering Services |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | 75N99020D00011 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $553.7K |
| Current contract value | $553.7K |
| Potential contract value / ceiling | $553.7K |
| Start date | Sep 20, 2023 |
| Current end date | Oct 15, 2025 |
| Potential end date | Oct 15, 2025 |
| Latest award activity | Sep 10, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 10, 2025 | P00003 | $35.5K | C112405- BLDG. 49 EXTERIOR ENVELOPE REPAIRS. THE REASON FOR THIS CHANGE IS TO INCLUDE ADDITIONAL DESIGN MEETINGS THAT CONTRACTOR PROVIDED DURING DESIGN. |
| Sep 24, 2024 | P00002 | $314.4K | C112405- BLDG. 49 EXTERIOR ENVELOP REPAIRS: THIS PROJECT CONSISTS OF PROVIDING A DESIGN TO ADDRESS DEFICIENCY FOUND IN THE SMITH GROUP FINAL ASSESSMENT REPORT FOR BLDG. 49. |
| May 17, 2024 | P00001 | $0 | C112405- BLDG. 49 EXTERIOR ENVELOP REPAIRS: THIS PROJECT CONSISTS OF PROVIDING A DESIGN TO ADDRESS DEFICIENCY FOUND IN THE SMITH GROUP FINAL ASSESSMENT REPORT FOR BLDG. 49. |
| Sep 20, 2023 | 0 | $203.9K | C112405- BLDG. 49 EXTERIOR ENVELOP REPAIRS: THIS PROJECT CONSISTS OF PROVIDING A DESIGN TO ADDRESS DEFICIENCY FOUND IN THE SMITH GROUP FINAL ASSESSMENT REPORT FOR BLDG. 49. |