Federal contract award
75N99024C00091
BLDG. 40 VRC NORTH AREA RESTORATION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Health and Human Services |
| Office | NIH A E CONSTRUCTION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $4.3M |
| Current contract value | $4.3M |
| Potential contract value / ceiling | $4.3M |
| Start date | Sep 30, 2024 |
| Current end date | Oct 1, 2026 |
| Potential end date | Oct 1, 2026 |
| Latest award activity | Jul 9, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 9, 2026 | P00007 | $0 | C103754.5 - THE REASON FOR THIS MOD IS TO EXTEND THE CONSTRUCTION COMPLETION DATE TO ALLOW THE DELIVERY OF MATERIALS. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| Jun 17, 2026 | P00006 | $96.3K | C103754.5: THE REASON FOR THIS MOD IS TO INCLUDE MINOR SCOPE ADJUSTMENTS. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| May 14, 2026 | P00005 | $69.8K | C103754.5: THE REASON FOR THIS MOD IS TO INCLUDE MINOR SCOPE ADJUSTMENTS. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| Apr 9, 2026 | P00004 | $0 | C103754.5: THE REASON FOR THIS MOD IS TO EXTEND THE CONSTRUCTION COMPLETION DATE TO ALLOW FOR THE COMPLETION OF REMAINING WORK. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| Sep 28, 2025 | P00003 | $149.7K | C103754.5 - THE REASON FOR THIS MOD IS TO PROVIDE THE ADDITION OF AN EMERGENCY EXIT FROM BLDG. 40A TO BLDG. 40'S ELECTRICAL ROOMS PER DESIGN REVISION 63. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| Sep 19, 2025 | P00002 | $521.4K | C103754.5 - THE REASON FOR THIS MOD IS TO PROVIDE RE-ROUTING OF THE SUPPLY LINE FROM THE EXTERIOR LN2 BULK TANK TO BLDG 40 AND TO REPLACE THE EXISTING TANK WITH A NEW 6000GAL LN2 TANK. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MI |
| Nov 1, 2024 | P00001 | $0 | BLDG. 40 VRC NORTH AREA RESTORATION |
| Sep 30, 2024 | 0 | $3.4M | BLDG. 40 VRC NORTH AREA RESTORATION |