Federal contract award
75N99024F00002
C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A CS: CHRIS HSU CO: ZACH PRICE COR: FERDINAND REYES
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Health and Human Services |
| Office | NIH A E CONSTRUCTION |
| NAICS | 541330 — Engineering Services |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | 75N99020D00010 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $397.9K |
| Current contract value | $397.9K |
| Potential contract value / ceiling | $397.9K |
| Start date | Aug 29, 2024 |
| Current end date | Jun 1, 2026 |
| Potential end date | Jun 1, 2026 |
| Latest award activity | Feb 3, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 3, 2026 | P00004 | $7.0K | C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A. THE REASON FOR THIS CHANGE IS TO BALANCE THE WATER FLOW (GPM) OF THE COILS BEFORE AND AFTER INSTALLATION (NO CALCULATIONS REQUIRED). THE PROJECT IS NOT COMPLETE AND USABLE WITHOUT THIS CHANGE. |
| Nov 28, 2025 | P00003 | $36.9K | C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A. THE REASON FOR THIS CHANGE IS TO INCLUDE RECIRCULATING PUMP TO BE INCLUDED FOR 100% DESIGN OF AHU. THE PROJECT IS NOT COMPLETE AND USABLE WITHOUT THIS CHANGE. |
| Sep 25, 2025 | P00002 | $31.4K | C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A. THE REASON FOR THIS CHANGE IS TO INCLUDE INTEGRATED HUMIDIFICATION TO SUPPORT ENVIRONMENTAL QUALITY REQUIREMENTS, SEASONAL PERFORMANCE TARGETS, AND PROGRAMMATIC NEEDS. |
| Mar 19, 2025 | P00001 | $0 | C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A CS: CHRIS HSU CO: ZACH PRICE COR: FERDINAND REYES |
| Sep 3, 2024 | 0 | $322.5K | C112354 - BUILDING 4 REPLACE AHU 3, 4 AND 4A CS: CHRIS HSU CO: ZACH PRICE COR: FERDINAND REYES |