Federal contract award

80KSC021CA003

UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3 325 TON CRANE.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyNational Aeronautics and Space Administration
OfficeNASA KENNEDY SPACE CENTER
NAICS333923 — Overhead Traveling Crane, Hoist, and Monorail System Manufacturing
PSCZ1PZ — MAINTENANCE OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$8.2M
Current contract value$8.2M
Potential contract value / ceiling$8.2M
Start dateJun 21, 2021
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityJul 8, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 22 of 22 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 8, 2026P00021$62.9KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB), HIGH-BAY (HB) 3, 325-TON CRANE.
Mar 10, 2026P00020$30.1KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB), HIGH-BAY (HB) 3, 325-TON CRANE.
Feb 25, 2026P00019$56.3KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH-BAY (HB) 3, 325-TON CRANE.
Jan 27, 2026P00018$77.0KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH-BAY (HB) 3, 325-TON CRANE
Sep 25, 2025P00017$1.7MUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE.
May 29, 2025P00016$85.4KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE.
May 8, 2025P00015$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE.
Feb 21, 2025P00014$8.8KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00014: INCORPORATES TECHNICAL NUMBER (TN) 08, AND ESTABLISHES A NEW PERIOD OF PERFORMANCE OF 05/18/2025.
Jan 24, 2025P00013$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00013: INCORPORATES PROCUREMENT CLASS DEVIATION (PCD) 21-01B. THE PERIOD OF PERFORMANCE REMAINS 05/09/2025.
Sep 27, 2024P00012$12.3KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00012:INCORPORATES TECHNICAL NUMBER (TN) 07 AND ESTABLISHES A NEW PERIOD OF PERFORMANCE END DATE OF 05/09/2025.
Aug 27, 2024P00011$8.8KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00010:INCORPORATES REQUEST FOR EQUITABLE ADJUSTMENT (REA) 01 AND ESTABLISHES A NEW PERIOD OF PERFORMANCE END DATE OF 04/09/2025.
Jul 15, 2024P00010$56.3KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00010:INCORPORATES TECHNICAL NUMBER (TN) 06 AND ESTABLISHES A NEW PERIOD OF PERFORMANCE END DATE OF 10/30/2024.
Jul 12, 2024P00009$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00009:INCORPORATES FAR 52.204-30 ALTERNATE I, FEDERAL ACQUISITION SUPPLY CHAIN ACT ORDERS-PROHIBITION (DEC 2023) INTO THE CONTRACT. POP REMAINS 10/30/2024.
May 2, 2024P00008$306.0KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00008: INCORPORATE TECHNICAL NUMBER (TN) 04. ESTABLISHES A NEW POP END DATE OF 10/30/2024.
Jan 26, 2024P00007$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00007: INCORPORATE SUPPLEMENTAL DOCUMENTS IN SUPPORT OF FAR 52.232-5(B)(2)(I), PAYMENTS FOR OFFSITE MATERIAL.
Sep 26, 2023P00006$26.6KUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. P00006: INCORPORATES TRACKING NUMBER (TN) 02 INTO THE CONTRACT.
Jun 22, 2023P00005$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. ADMINISTRATIVE CHANGE TO CLARIFY THE SPECIFICATION OF THE 325-TON CRANE PERFORMANCE REQUIREMENTS. P00005: ADDS CLAUSE 52.204-27 AND REMOVES CLAUSE 52.223-99
Nov 22, 2022P00004$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3, 325 TON CRANE. ADMINISTRATIVE CHANGE TO CLARIFY THE SPECIFICATION OF THE 325-TON CRANE PERFORMANCE REQUIREMENTS.
Aug 8, 2022P00003$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY(HB) 3 325 TON CRANE. CHANGES THE MATERIAL SELECTION TEST (MST) FROM BEFORE THE 30% DESIGN TO AFTER THE 30% DESIGN AND BEFORE THE 60% DESIGN.
Oct 8, 2021P00002$0EO14042 UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY(HB) 3 325 TON CRANE. INCORPORATES 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS. (DEVIATION 21-03)
Jun 3, 20210$5.8MUPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3 325 TON CRANE.
Jun 3, 2021P00001$0UPGRADE VEHICLE ASSEMBLY BUILDING (VAB) HIGH BAY (HB) 3 325 TON CRANE. ESTABLISHES CONTRACT COMPLETION DATE, 5/1/2024, BASED ON THE NOTICE TO PROCEED ISSUED 6/21/2021.

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Anthony M. CaruvanaContactanthony.m.caruvana@nasa.gov
3218673464
SourceJan 15, 2021
C. M. Julius WilliamsContactchristopher.m.williams@nasa.gov
3218612661
SourceJan 15, 2021
Anthony M. CaruvanaContactanthony.m.caruvana@nasa.gov
3218673464
SourceJan 12, 2021
C. M. Julius WilliamsContactchristopher.m.williams@nasa.gov
3218612661
SourceJan 12, 2021
Anthony M. CaruvanaContactanthony.m.caruvana@nasa.gov
3218673464
SourceJan 6, 2021
C. M. Julius WilliamsContactchristopher.m.williams@nasa.gov
3218612661
SourceJan 6, 2021
Anthony M. CaruvanaContactanthony.m.caruvana@nasa.gov
3218673464
SourceDec 15, 2020
C. M. Julius WilliamsContactchristopher.m.williams@nasa.gov
3218612661
SourceDec 15, 2020
Anthony M. CaruvanaContactanthony.m.caruvana@nasa.gov
3218673464
SourceNov 18, 2020
C. M. Julius WilliamsContactchristopher.m.williams@nasa.gov
3218612661
SourceNov 18, 2020

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.