Federal contract award
80KSC021F0108
ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY UPGRADE, KSC INSTITUTIONAL POWER SYSTEMS, PHASE 4, PROJECT CONTROL NUMBER 98966.4.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | National Aeronautics and Space Administration |
| Office | NASA KENNEDY SPACE CENTER |
| NAICS | 541330 — Engineering Services |
| PSC | C223 — ARCHITECT AND ENGINEERING- GENERAL: MECHANICAL SYSTEMS |
| Parent award / vehicle | 80KSC020D0015 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $302.1K |
| Current contract value | $302.1K |
| Potential contract value / ceiling | $302.1K |
| Start date | Jul 1, 2021 |
| Current end date | Jun 30, 2026 |
| Potential end date | Jun 30, 2026 |
| Latest award activity | Oct 28, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 28, 2025 | P00006 | $0 | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY UPGRADE, KENNEDY SPACE CENTER INSTITUTIONAL POWER SYSTEMS, PHASE 4 |
| May 20, 2024 | P00005 | $43.0K | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY UPGRADE, KENNEDY SPACE CENTER INSTITUTIONAL POWER SYSTEMS, PHASE 4 |
| May 2, 2024 | P00004 | $0 | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY POWER UPGRADES, PHASE 4, PCN: 98966.4 |
| Feb 28, 2024 | P00003 | $13.1K | ESDC OF SAFETY AND RELIABILITY UPGRADE, KSC INSTITUTIONAL POWER SYSTEMS, PHASE 4, TASK ORDER MODIFICATION TO ADD SCOPE OF WORK |
| Oct 23, 2023 | P00002 | $23.3K | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY RELIABILITY UPGRADE INSTITUTIONAL POWER SYSTEMS PHASE 4. INCORPORATE TECHNICAL DIRECTIVE 02 AND EXTEND PERIOD OF PERFORMANCE TO APRIL 30, 2024. |
| Dec 20, 2021 | P00001 | $7.8K | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY UPGRADE, KSC INSTITUTIONAL POWER SYSTEMS, PHASE 4. ADDS SERVICES IN ACCORDANCE WITH TECHNICAL DIRECTIVE -01 AND INCREASES AWARD $7,831 TO $222,778.00. |
| Jul 1, 2021 | 0 | $214.9K | ENGINEERING SERVICES DURING CONSTRUCTION OF SAFETY AND RELIABILITY UPGRADE, KSC INSTITUTIONAL POWER SYSTEMS, PHASE 4, PROJECT CONTROL NUMBER 98966.4. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.