Federal contract award
88310321F00171
THIS TASK ORDER IS FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | National Archives and Records Administration |
| Office | NARA CONTRACTING OFFICE |
| NAICS | 561210 — Facilities Support Services |
| PSC | S201 — Custodial Janitorial Services |
| Parent award / vehicle | 47QSHA19D0044 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $73.1M |
| Current contract value | $94.6M |
| Potential contract value / ceiling | $94.6M |
| Start date | Oct 1, 2021 |
| Current end date | Jul 31, 2027 |
| Potential end date | Jul 31, 2027 |
| Latest award activity | Aug 1, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 49 of 49 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 1, 2026 | P00048 | $2.9M | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO EXERCISE OPTION YEAR IV WITH A PERIOD OF PERFORMANCE OF AUGUST 1 2026 THROUH JULY 31, 2027. |
| Jul 28, 2026 | P00047 | $-76.0K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO DEOBLIGATE FY 2026 FUNDING DUE TO PENALTY FEES FOR NON-PERFORMANCE |
| Jul 24, 2026 | P00046 | $695.0K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING FOR ADDITIONAL SERVICES |
| Jun 7, 2026 | P00045 | $19.9K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING FOR ADDITIONAL SERVICES |
| May 18, 2026 | P00044 | $42.6K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING FOR ADDITIONAL SERVICES |
| May 1, 2026 | P00043 | $5.8M | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING. |
| Mar 19, 2026 | P00042 | $1.5M | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I,WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING FROM ONE MONTH (MARCH 2026) |
| Mar 17, 2026 | P00041 | $6.2M | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT ARCHIVES I,WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD IS TO OBLIGATE FY 2026 FUNDING FROM OCTOBER 1, 2025 TO FEBRUARY 28, 2026. |
| Sep 29, 2025 | P00040 | $11.0K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR ADDITIONAL IDIQ WORK |
| Sep 17, 2025 | P00039 | $246.7K | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO EXERCISE OPTION YEAR III. |
| Aug 21, 2025 | P00038 | $3.1M | THE PURPOSE OF THIS MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO EXERCISE OPTION YEAR III. |
| Jul 24, 2025 | P00037 | $37.8K | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING |
| Jul 3, 2025 | P00036 | $2.3M | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING |
| Jun 3, 2025 | P00035 | $50.0K | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR NARA-SPONSORED IDIQ WORK. |
| May 21, 2025 | P00034 | $1.4M | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR ONE MONTH. |
| Apr 23, 2025 | P00033 | $1.4M | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR ONE MONTH. |
| Mar 28, 2025 | P00032 | $1.4M | THE PURPOSE OF THIS TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR ONE MONTH. |
| Mar 1, 2025 | P00031 | $705.9K | THE PURPOSE OF THE BILATERAL TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING FOR TWO WEEKS. |
| Feb 9, 2025 | P00030 | $2.8M | THE PURPOSE OF THE BILATERAL TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE FISCAL YEAR 2025 FUNDING. |
| Jan 31, 2025 | P00029 | $35.2K | THE PURPOSE OF THE BILATERAL TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE *FISCAL YEAR 2025 FUNDING FOR ADDITIONAL SERVICES. |
| Oct 30, 2024 | P00028 | $4.5M | THE PURPOSE OF THE BILATERAL TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE *FISCAL YEAR 2025 FUNDING. |
| Sep 27, 2024 | P00027 | $55.0K | THE PURPOSE OF THE BILATERAL TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE *FISCAL YEAR 2024 FUNDING FOR ADDITIONAL SERVICES. |
| Aug 31, 2024 | P00026 | $0 | THE PURPOSE OF THE ADMINISTRATIVE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCORPORATE IS TO CORRECT THE LINE OF ACCOUNTING (LOA) TO CL |
| Aug 30, 2024 | P00025 | $18.3K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCORPORATE OYII WAGE ADJUSTMENTS |
| Aug 6, 2024 | P00024 | $0 | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO CORRECT THE FUNDING SPLITS ON LINE 0019. |
| Aug 1, 2024 | P00023 | $3.2M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE ADDITIONAL FUNDING FOR TWO MONTHS (JUNE 1, 2024 TO JULY 31, 2024 |
| Jul 7, 2024 | P00022 | $2.7M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE ADDITIONAL FUNDING FOR TWO MONTHS (JUNE 1, 2024 TO JULY 31, 2024 |
| May 2, 2024 | P00021 | $3.1M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE ADDITIONAL FUNDING FOR TWO MONTHS (APRIL 1, 2024 TO MAY 31, 2024 |
| Apr 15, 2024 | P00020 | $21.5K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO OBLIGATE ADDITIONAL FUNDING TO IDIQ WORK. |
| Apr 8, 2024 | P00019 | $1.4M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCREMENTALLY FUND FOR ONE MONTH (MARCH 1, TO MARCH 31, 2024). |
| Feb 23, 2024 | P00018 | $3.0M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCREMENTALLY FUND FOR TWO MONTHS (JANUARY 1, TO FEBRUARY 29, 2024) AND T |
| Nov 21, 2023 | P00017 | $2.7M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCREMENTALLY FUND FOR TWO MONTHS (NOVEMBER 1, TO DECEMBER 31, 2023). |
| Nov 17, 2023 | P00016 | $1.3M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO INCREMENTALLY FUND FOR OCTOBER 2023. |
| Sep 29, 2023 | P00015 | $190.0K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO: (A) ADJUST PRIOR YEAR PERIOD OF PERFORMANCE AND WAGE DETERMINATION AND F |
| Sep 20, 2023 | P00014 | $37.8K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO: (A) ADJUST PRIOR YEAR PERIOD OF PERFORMANCE AND WAGE DETERMINATION AND F |
| Aug 31, 2023 | P00013 | $3.0M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO: (A) EXERCISE OPTION YEAR 1 BY EXTENDING THE PERIOD OF PERFORMANCE OF AUG |
| Aug 14, 2023 | P00012 | $294.7K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO ADD FY 2023 FUNDING FOR ADDITIONAL SERVICES |
| Jul 6, 2023 | P00011 | $322.3K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO ADD FY 2023 FUNDING FOR ADDITIONAL SERVICES |
| Apr 5, 2023 | P00010 | $5.3M | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS ADD FY 2023 FUNDING TO FULLY FUND CLINS 0001-0003. |
| Mar 17, 2023 | P00009 | $96.3K | THE PURPOSE OF THE TASK ORDER MODIFICATION FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS ADD FY 2023 FUNDING FOR ADDITIONAL SERVICES. |
| Mar 3, 2023 | P00008 | $2.7M | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS ADD FY 2023 FUNDING FOR 2 MONTHS FEBRUARY 1, 2023 TO MARCH 31, 2023. |
| Jan 23, 2023 | P00007 | $1.3M | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS ADD FY 2023 FUNDING FOR 1 MONTH JANUARY 1, 2023 TO JANUARY 31, 2023. |
| Nov 1, 2022 | P00006 | $4.1M | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS ADD FUNDING FOR 3 MONTHS OCTOBER 1, 2022 TO DECEMBER 31, 2022. |
| Sep 30, 2022 | P00005 | $32.8K | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO RENOVATE ROOM 2800 OIG SUITE PHYSICAL SECURITY RENOVATIONS AT ARCHIVES II. |
| Sep 27, 2022 | P00004 | $50.0K | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO FUND ADDITIONAL SERVICES FOR THE NARA TRUEST FUNDS AND FOUNDATION EVENTS. |
| Sep 26, 2022 | P00003 | $3.0M | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO (A) FUND THE BASE YEAR FOR TWO(2) MONTHS (B) INCORPORATE CBA AND DOL WD AND (C) ADDITION |
| Sep 6, 2022 | P00002 | $60.0K | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES TO PURCHASE AND REPLACE 128 EXISTING BATTERIES FOR THE AII FOURTH FLOOR DATA CENTER. |
| Jul 18, 2022 | P00001 | $0 | THE PURPOSE OF THE TASK ORDER FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES IS TO CHANGED THE BASE AND FOUR (4) OPTION PERIODS. |
| Sep 9, 2021 | 0 | $0 | THIS TASK ORDER IS FOR COMPLETE FACILITIES MAINTENANCE (CFM) AT NATIONAL ARCHIVES I, WASHINGTON, DC AND ARCHIVES II, COLLEGE PARK, MD FACILITIES. |
Estimated positioning window
Nov 1, 2026 – Jan 31, 2027
85/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 85/100. Available recorded signals: 80 points.
- Contract end 2027-07-31 (272 days from calculation)
- +35 points
- 4 historical awards in this buyer and category group
- +15 points
- 49 recorded award transactions
- +10 points
- Latest award action: 2026-08-01
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.