Federal contract award
89233119FNA400241
DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1; REFERENCE MIDDLE EAST REGION 2 SOW, ATTACHMENT 1.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | NNSA NON-MO CNTRCTNG OPS DIV |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | DENA0003363 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $3.1M |
| Current contract value | $3.1M |
| Potential contract value / ceiling | $3.1M |
| Start date | Sep 30, 2019 |
| Current end date | Dec 31, 2023 |
| Potential end date | Dec 31, 2023 |
| Latest award activity | Dec 8, 2023 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 8, 2023 | P00010 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CO ON THIS TASK ORDER. |
| Sep 27, 2023 | P00009 | $9.8K | DESIGN INTEGRATION CONSTRUCTION COMMUNICATION AND ENGINEERING |
| Jun 17, 2022 | P00008 | $0 | PERIOD OF PERFORMANCE EXTENSION THROUGH 10/31/2023 |
| Jan 28, 2022 | P00007 | $0 | PERIOD OF PERFORMANCE EXTENSION THROUGH 5/31/2022 |
| Oct 22, 2021 | P00006 | $0 | ADMINISTRATIVE ACTION TO CHANGE INVOICE REVIEWING SPECIALIST OFFICIAL IN STRIPES |
| Jun 24, 2021 | P00005 | $324.1K | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1. INCORPORATE SAI ESTIMATE AT COMPLETION (EAC) FOR KUWAIT G1 CLIN 0001, INCORPORATE REVISED SOW AND EXTEND POP. |
| Apr 15, 2021 | P00004 | $196.0K | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1. INCORPORATE ESTIMATE AT COMPLETION (EAC) FOR KUWAIT G1 CLIN 0001 AND EXTEND POP DATE TO 30 JUNE 2021. |
| Feb 12, 2021 | P00003 | $159.9K | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1. INCORPORATE ESTIMATE AT COMPLETION (EAC) FOR KUWAIT G1 CLIN 0001. |
| Sep 18, 2020 | P00002 | $208.4K | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1. MODIFICATION P00002 INCREASES THE CEILING FOR THE ESTIMATE AT COMPLETION (EAC) COST OVERRUN. |
| Jul 1, 2020 | P00001 | $245.1K | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1; MOD 1 INCORPORATE DRD ADD 001. |
| Sep 30, 2019 | 0 | $1.9M | DESIGN, INTEGRATION, CONSTRUCTION, COMMUNICATIONS, AND ENGINEERING 2 (DICCE2)MIDDLE EAST REGIONAL, KUWAIT GROUP 1; REFERENCE MIDDLE EAST REGION 2 SOW, ATTACHMENT 1. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.