Federal contract award
89243324CFE000084
NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | NATIONAL ENERGY TECHNOLOGY LABORATORY |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $5.0M |
| Current contract value | $5.0M |
| Potential contract value / ceiling | $5.0M |
| Start date | Feb 8, 2024 |
| Current end date | Dec 31, 2025 |
| Potential end date | Dec 31, 2025 |
| Latest award activity | Sep 19, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 19, 2025 | P00006 | $100.0K | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0006 - THE PURPOSE OF THIS MODIFICATION IS A SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE AND INCREASE THE TOTAL CONTRACT VALUE AND OBLIGATIONS. |
| Jan 8, 2025 | P00005 | $87.7K | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0005 - THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK WITHIN SCOPE AND INCREASE THE TOTAL CONTRACT VALUE AND OBLIGATIONS. |
| Nov 18, 2024 | P00004 | $6.1K | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0004 - THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK WITHIN SCOPE AND INCREASE THE TOTAL CONTRACT VALUE AND OBLIGATIONS. |
| Jul 15, 2024 | P00003 | $146.0K | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0003 - THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK WITHIN SCOPE AND INCREASE THE TOTAL CONTRACT VALUE AND OBLIGATIONS. |
| May 14, 2024 | P00002 | $97.2K | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0002 - THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK WITHIN SCOPE AND INCREASE THE TOTAL CONTRACT VALUE AND OBLIGATIONS. |
| Mar 15, 2024 | P00001 | $0 | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 MODIFICATION 0001 - THE PURPOSE OF THIS MODIFICATION IS TO ISSUE TO NOTICE TO PROCEED AND ESTABLISH THE PERIOD OF PERFORMANCE |
| Feb 8, 2024 | 0 | $4.6M | NETL ALBANY, OR BUILDING 28 ARCHITECTURAL & HVAC UPGRADES - PHASE 2 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.