Federal contract award

89243324FFE400606

TASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeNATIONAL ENERGY TECHNOLOGY LABORATORY
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS
Parent award / vehicle89243323DFE000021
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$10.1M
Current contract value$10.1M
Potential contract value / ceiling$10.1M
Start dateAug 7, 2024
Current end dateJun 30, 2026
Potential end dateJun 30, 2026
Latest award activityMay 26, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 26, 2026P00004$66.3KTASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT MODIFICATION 0004 - THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK WITHIN SCOPE AND EXTEND THE
Mar 9, 2026P00003$0TASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT MODIFICATION 0003 - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE.
Dec 18, 2025P00002$0TASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT MODIFICATION 0002 - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE.
Oct 15, 2025P00001$0TASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT MODIFICATION 0001 - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE.
Aug 7, 20240$10.0MTASK ORDER 6 - CONSTRUCTION: ENVIRONMENTAL SKID ROOMS FOR 89243323DFE000021 IDIQ DESIGN/BUILD CONTRACT OF THE DIRECT AIR CAPTURE CENTER (DACC) PROJECT

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.