Federal contract award
89243421FEE400222
FEMP PROJECT FACILITATION (PF) SERVICES FOR ENERGY SAVINGS PERFORMANCE CONTRACT (ESPC) PROJECT PF 505, NATIONAL RENEWABLE ENERGY LABORATORY (NREL) ESPC, GOLDEN, CO ___
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | GOLDEN FIELD OFFICE |
| NAICS | 541690 — Other Scientific and Technical Consulting Services |
| PSC | R425 — Engineering and Technical Services |
| Parent award / vehicle | GS21F055AA |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $0 |
| Current contract value | $158.2K |
| Potential contract value / ceiling | $164.7K |
| Start date | Aug 12, 2021 |
| Current end date | Feb 11, 2027 |
| Potential end date | Feb 11, 2027 |
| Latest award activity | Aug 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 14, 2026 | P00007 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NLR ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE BY 6 MONTHS, EXERCISE TASK A5 FOR BOTH TO #1 AND TO #2 AND CHANGE THE PROJECT TITLE. ___ |
| Jul 3, 2025 | P00006 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO RENUMBER THE PROJECTS, CHANGE THE SCOPE BY ADDING TASKS A3.1 AND A3.2 TO THE HPCDC PROJECT, EXERCISE OPTION PERIOD 4 AND EXERCISE TASK A4 UNDER THE |
| Jan 15, 2025 | P00005 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO ADD A FOURTH ESPC PROJECT TO THE SCOPE AND ADD A NTE COST FOR ADDITIONAL TRAVEL TO THE SCOPE OF THE PROJECT. ___ |
| May 17, 2024 | P00004 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 3, EXERCISE TASK A4 ON 2ND ESPC TO (SOUTH TABLE MOUNTAIN), AND CHANGE THE CS. ___ |
| Mar 14, 2023 | P00003 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO ADD A SECOND ESPC PROJECT TO THE SCOPE, EXERCISE OPTION PERIOD 2, AND EXERCISE TASK A4. ___ |
| Aug 4, 2022 | P00002 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 1, TASK A3.4, AND CHANGE THE CO AND CS. ___ |
| Nov 3, 2021 | P00001 | $0 | PF SERVICES FOR ESPC PROJECT PF 505, NREL ESPC, GOLDEN, CO THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE THE FUNDING OPTION FOR TASK AREA C AND CHANGE THE CONTRACTING OFFICER AND THE INVOICE APPROVING OFFICIAL. ___ |
| Aug 12, 2021 | 0 | $0 | FEMP PROJECT FACILITATION (PF) SERVICES FOR ENERGY SAVINGS PERFORMANCE CONTRACT (ESPC) PROJECT PF 505, NATIONAL RENEWABLE ENERGY LABORATORY (NREL) ESPC, GOLDEN, CO ___ |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
85/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 85/100. Available recorded signals: 80 points.
- Contract end 2027-02-11 (109 days from calculation)
- +35 points
- 26 historical awards in this buyer and category group
- +15 points
- 8 recorded award transactions
- +10 points
- Latest award action: 2026-08-14
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.