Federal contract award

89303022FMA400514

REQUISITION 22MA000606 WAS ISSUED TO CREATE A TASK ORDER UNDER IDIQ 89303020DMA000018 TO PERFORM WORK PER THE BATHROOM RENOVATION PROJECT AT THE GERMANTOWN BUILDING FOR THE FIRM-FIXED PRICE AMOUNT OF $4,338,103.00. THE PERIOD OF PERFORMANCE IS 06/

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeHEADQUARTERS PROCUREMENT SERVICES
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AB — REPAIR OR ALTERATION OF CONFERENCE SPACE AND FACILITIES
Parent award / vehicle89303020DMA000018
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$6.2M
Current contract value$6.2M
Potential contract value / ceiling$6.2M
Start dateJun 27, 2022
Current end dateDec 31, 2025
Potential end dateDec 31, 2025
Latest award activityJul 16, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 12 of 12 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 16, 2025P00011$0THIS MODIFICATION IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE TO 12/31/2025.
Mar 6, 2025P00010$121.5KREQUISITION 25MA000257 WAS ISSUED TO ADD SCOPE OF WORK TO THE GERMANTOWN RESTROOM RENOVATION PROJECT FOR THE FIRM FIXED PRICE $121,466.00. THIS MODIFICATION INCLUDES ADDITIONAL SCOPE OF WORK TO PCOS 37, 50, 54, 56, 57, 63 AND CREDITS BACK TO DOE F
Feb 21, 2025P00009$0REQUISITION 25MA000165 IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE FROM 06/29/2022 TO 12/31/2024 TO 06/29/2022 TO 06/30/2025
Jun 24, 2024P00008$0REQUISITION 24MA000509 IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE FROM 06/29/2022 TO 06/30/2024 TO 06/29/2022 TO 12/31/2024
Apr 22, 2024P00007$301.9KGERMANTOWN RESTROOM RENOVATION PROJECT
Feb 16, 2024P00006$200.0KREQUISITION 24MA000249 WAS ISSUED TO ADD SCOPE OF WORK TO THE GERMANTOWN RESTROOM RENOVATION PROJECT TO REMOVE AND REPLACE PIPES AND INSTALL 3 NEW BOTTLE FILLING STATIONS FOR THE FIRM-FIXED PRICE AMOUNT OF $199,986.00. TOTAL CONTRACT VALUE WILL I
Dec 11, 2023P00005$7.3KREQUISITION 24MA000090 WAS ISSUED TO ADD SCOPE OF WORK TO REMOVE PIPE FITTING CONTAINING ASBESTOS FOR THE FIRM FIXED PRICE AMOUNT OF $7,327.50. TOTAL CONTRACT VALUE WILL INCREASE FROM $5,598,811.85 BY $7,327.50 TO $5,606,139.35. TOTAL OBLIGATI
Nov 20, 2023P00004$0THIS MODIFICATION IS TO CHANGE THE COR FROM MIN CHUNG TO DAN HABEL.
Sep 26, 2023P00003$1.1MREQUISITION 23MA000808 WAS ISSUED TO MODIFY TASK ORDER 89303022FMA400514 TO ADD SCOPE OF WORK TO MODERNIZE RESTROOMS, UPDATE FIXTURES, ADDRESS ADA COMPLIANCE ISSUES AND IMPROVE HVAC AND PLUMBING FOR THE FIRM-FIXED PRICE AMOUNT OF $1,113,056.00. T
Jun 15, 2023P00002$147.7KREQUISITION 23MA000554 WAS ISSUED TO ADD SCOPE OF WORK TO MODERNIZE RESTROOMS, UPDATE FIXTURES, ADDRESS ADA COMPLIANCE ISSUES AND IMPROVE HVAC AND PLUMBING FOR THE FIRM-FIXED PRICE AMOUNT OF $147,652.85. TOTAL OBLIGATIONS ARE INCREASED FROM $4,338
Sep 1, 2022P00001$0REQUISITION 22MA001069 WAS ISSUED TO CHANGE THE COR AND IAO TO MIN CHUNG.
Jun 27, 20220$4.3MREQUISITION 22MA000606 WAS ISSUED TO CREATE A TASK ORDER UNDER IDIQ 89303020DMA000018 TO PERFORM WORK PER THE BATHROOM RENOVATION PROJECT AT THE GERMANTOWN BUILDING FOR THE FIRM-FIXED PRICE AMOUNT OF $4,338,103.00. THE PERIOD OF PERFORMANCE IS 06/

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.