Federal contract award
89303323FEM400390
SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | EM-ENVIRONMENTAL MGMT CON BUS CTR |
| NAICS | 562910 — Remediation Services |
| PSC | F108 — Hazardous Substance Removal, Cleanup, and Disposal Services and Operational Support |
| Parent award / vehicle | 89303322DEM000073 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $195.7M |
| Current contract value | $224.3M |
| Potential contract value / ceiling | $228.6M |
| Start date | Oct 1, 2023 |
| Current end date | Apr 30, 2027 |
| Potential end date | Nov 5, 2027 |
| Latest award activity | Jul 24, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 26 of 26 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 24, 2026 | P00025 | $5.5M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00025 ADDS MULTIPLE LINE ITEMS. |
| Jul 15, 2026 | P00024 | $182.8K | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| May 6, 2026 | P00023 | $18.8M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00023 IS A SUPPLEMENTAL AGREEMENT TO A DELIVERABLE. |
| Feb 5, 2026 | P00022 | $6.9M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00022 ADDS MULTIPLE LINE ITEMS. |
| Dec 3, 2025 | P00021 | $17.5M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Oct 23, 2025 | P00020 | $0 | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00020 MAKES AN ADMINISTRATIVE CHANGE TO APPROPRIATION DATA. |
| Oct 17, 2025 | P00019 | $4.8M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Sep 23, 2025 | P00018 | $1.2M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00018 EXERCISES AN OPTION WITH FUNDS AND ADMIN CHANGES. |
| Jul 22, 2025 | P00017 | $21.1M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Jul 2, 2025 | P00016 | $602.6K | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00016 ADDS MORE CELL ROCK COVER AND WORK. |
| Jun 23, 2025 | P00015 | $5.7M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| May 16, 2025 | P00014 | $5.2M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00014 IS A SUPPLEMENTAL AGREEMENT. |
| Apr 17, 2025 | P00013 | $4.9M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Mar 7, 2025 | P00012 | $4.4M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00012 ADDS A GROUNDWATER COMPLIANCE ACTION PLAN LINE ITEM. |
| Jan 7, 2025 | P00011 | $12.5M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Dec 20, 2024 | P00010 | $2.4M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00010 ADDS A HAUL ROAD DESIGN/BUILD LINE ITEM. |
| Oct 15, 2024 | P00009 | $9.9M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Sep 25, 2024 | P00008 | $986.2K | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Sep 3, 2024 | P00007 | $9.6K | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00007 ADDS A WETLANDS RECONNAISSANCE LINE ITEM. |
| Aug 23, 2024 | P00006 | $7.0M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00006 EXERCISES AN OPTION AND FUNDS THE TASK ORDER. |
| Jun 26, 2024 | P00005 | $10.4M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00005 ADDS SECURITY REQUIREMENTS AND INCREMENTAL FUNDING. |
| Apr 19, 2024 | P00004 | $8.4M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00004 ADDS MORE CELL ROCK COVER. |
| Feb 22, 2024 | P00003 | $12.5M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Dec 29, 2023 | P00002 | $15.7M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
| Nov 14, 2023 | P00001 | $9.0M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. MOD P00001 FUNDS, SPECIFIES, AND CORRECTS THE TASK ORDER. |
| Sep 29, 2023 | 0 | $10.1M | SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. |
Estimated positioning window
Nov 5, 2026 – May 5, 2027
65/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 65/100. Available recorded signals: 60 points.
- Contract end 2027-11-05 (376 days from calculation)
- +25 points
- 30 historical awards in this buyer and category group
- +15 points
- 26 recorded award transactions
- +10 points
- Latest award action: 2026-07-24
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.