Federal contract award
89303523FEM400032
OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | EM-OAK RIDGE |
| NAICS | 562910 — Remediation Services |
| PSC | F999 — Other Environmental Services, Studies, and Analytical Support |
| Parent award / vehicle | 89303322DEM000067 |
| Set-aside | Not reported |
| Pricing type | COST PLUS AWARD FEE |
| Obligations | $2.5B |
| Current contract value | $3.3B |
| Potential contract value / ceiling | $3.3B |
| Start date | May 17, 2023 |
| Current end date | Feb 27, 2032 |
| Potential end date | Feb 27, 2032 |
| Latest award activity | Aug 28, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 122 of 122 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 28, 2026 | P00123 | $7.1M | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $7,122,472.57. TOTAL OBLIGATIONS HEREBY INCREASED FROM $2,533,722,927.43 TO 2,540,845,400.00. |
| Jul 31, 2026 | P00121 | $104.3M | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $104,349,019.43. TOTAL OBLIGATIONS HEREBY INCREASED FROM $2,429,373,908 TO $2,533,722,927.43. |
| Jun 30, 2026 | P00120 | $20.1M | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $20,125,000.00. |
| Jun 18, 2026 | P00119 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD STORAGE OF LLNL WASTE WITH NO CHANGE TO COST, SCHEDULE, OR FEE. |
| Jun 4, 2026 | P00117 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO AWARD THE NEGOTIATED AGREEMENT FOR SUBTASK PROPOSAL UCOR-T6-1A-001, WHITE WING SCRAP YARD REMOVAL ACTION(S), DATED JUNE 25, 2025. |
| May 22, 2026 | P00116 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A UNILATERAL CHANGE ORDER UNDER SUBTASK 6-1, Y-12 OPERATIONS AND CLEANUP END STATES, AUTHORIZING A NOT-TO-EXCEED VALUE OF $18,000,000 WITHIN SUBCLIN 000361. DETAILS IN THE ATTACHED CONTINUATION PAGES. |
| May 22, 2026 | P00118 | $90.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $90K. |
| Apr 30, 2026 | P00115 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE AN AMENDMENT TO CHANGE ORDER MODIFICATION P00108 UNDER SUBTASK 5-1, ORNL OPERATIONS AND CLEANUP END STATES, WITH NO INCREASE TO THE NOT-TO-EXCEED VALUE OF $867,838 WITHIN SUBCLIN 000351. |
| Apr 21, 2026 | P00111 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE DEFINITIZATION OF CHANGE ORDER MODIFICATIONS P00087/P00094 AND PROPOSAL UCOR-T4-1-006, REVISION 1; SETTLEMENT OF REQUESTS FOR EQUITABLE ADJUSTMENT UCOR-T5-009, 3517 HOT CELL INVESTIGATION; UCOR-T |
| Apr 15, 2026 | P00114 | $216.4M | THIS MODIFICATION PROVIDES INCREMENTAL FUNDING MID APRIL 2026. |
| Apr 10, 2026 | P00113 | $0 | THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE OF THE ENHANCED DISPERSION MODELING SCOPE IN SUBTASK 4-1. |
| Apr 2, 2026 | P00106 | $0 | THIS MOD INCORPORATES PARTIAL NEGOTIATION OF PROPOSAL UCOR T6-1-011, SUBTASK 6-1: ADDITION OF OUTFALL SITE AND EQUIPMENT MAINTENANCE SERVICES, AND SUBTASK 4-1: ADDITION OF CENTRAL WAREHOUSE LEASES AND UPPER EAST FORK POPULAR CREEK AND WEST END MERCUR |
| Mar 26, 2026 | P00108 | $0 | INCORPORATE NEGOTIATION OF PROPOSAL UCOR T8-2-003, ENVIRONMENTAL MANAGEMENT DISPOSAL FACILITY (EMDF) EAST SPOILS DESIGN COMPLETION, AND DEFINITIZATION OF UNILATERAL CHANGE ORDER MODIFICATION P100 FOR PROPOSAL UCOR-T8-2-001, ENVIRONMENTAL MANAGEMENT D |
| Mar 26, 2026 | P00109 | $0 | MOD INCORPORATES SETTLEMENT OF 3 REAS _UCOR T6-1-003, BETA-1_ 9204-1 DEAC HAZARD ABATEMENT; UCOR T6-1-007 BETA-4 SOIL SAMPLING AND PRELIMINARY HAZARD SCREENING; AND, UCOR T8-2-001, GRNDWTR FIELD DEMO ROCK ENCOUNTERED DURING EXCAVATION. |
| Mar 26, 2026 | P00112 | $8.2M | FUNDING MOD FOR MARCH 2026. |
| Feb 27, 2026 | P00110 | $49.7M | FEBRUARY 2026 FUNDING MODIFICATION |
| Jan 27, 2026 | P00107 | $885.0K | JANUARY 2026 FUNDING MODIFICATION |
| Dec 30, 2025 | P00104 | $0 | MODIFICATION TO DEFINITIZE CHANGE ORDER ISSUED IN MODIFICATION P00092/P00098 |
| Dec 30, 2025 | P00105 | $-3.4M | DECEMBER 2025 FUNDING MODIFICATION |
| Dec 23, 2025 | P00103 | $0 | MODIFICATION TO REVISE SUBTASK 17-1 SECTION C. TO CHANGE THE PURPOSE OF THE DARA FACILITY FROM TEST TO MAINTENANCE FACILITY AT NO EXTRA COST TO THE GOVERNMENT. |
| Dec 3, 2025 | P00087 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Dec 2, 2025 | P00102 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A CHANGE ORDER UNDER SUBTASK 6-1, Y-12 OPERATIONS AND CLEANUP END STATES, TO COMPLETE TREE FELLING ACROSS 39 ACRES WITHIN WHITE WING SCRAP YARD. |
| Nov 25, 2025 | P00100 | $0 | FUNDING MODIFICATION |
| Nov 24, 2025 | P00099 | $0 | CHANGE ORDER DEFINITIZATION AND ADMINISTRATIVE CORRECTIONS |
| Nov 24, 2025 | P00101 | $168.1M | MOD TO ADD INCREMENTAL FUNDING |
| Nov 19, 2025 | P00096 | $0 | CONTRACT MODIFICATION TO EXERCISE PRICED OPTIONAL SCOPE FOR ZONE 2 DUCT BANKS REMEDIAL ACTIONS. |
| Nov 19, 2025 | P00098 | $0 | SUBTASK 4-1 CHANGE ORDER TO EXTEND THROUGH DEC 28, 2025 |
| Oct 31, 2025 | P00097 | $-6.0M | FUNDING MODIFICATION |
| Sep 30, 2025 | P00094 | $0 | CHANGE ORDER MOD TO INCREASE THE NOT-TO-EXCEED VALUE ESTABLISHED VIA MODIFICATION P00087 FROM $200K TO $350K WITHIN SUBCLIN 000341. |
| Sep 30, 2025 | P00095 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE ESTIMATED COST AND FIXED FEE WITHIN SUBCLIN 000392A FOR PROJECT MANAGEMENT AND PROJECT SUPPORT SERVICES FOR JULY 2025 AND ADDITIONAL SERVICES FOR THE PERIOD OCTOBER 1, 2025, THROUGH DECEMBER 31, 2025. |
| Sep 26, 2025 | P00093 | $39.4M | ADDING INCREMENTAL FUNDING IN THE AMOUNT OF $39,376,682.67. |
| Sep 25, 2025 | P00092 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 29, 2025 | P00091 | $9.4M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 28, 2025 | P00090 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 27, 2025 | P00089 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jul 30, 2025 | P00088 | $163.7M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jul 28, 2025 | P00086 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 27, 2025 | P00085 | $69.5M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 26, 2025 | P00084 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 13, 2025 | P00083 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 11, 2025 | P00080 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 5, 2025 | P00082 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 30, 2025 | P00081 | $49.4M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 21, 2025 | P00079 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 13, 2025 | P00078 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 12, 2025 | P00077 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 30, 2025 | P00076 | $31.7M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 17, 2025 | P00075 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 16, 2025 | P00074 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 11, 2025 | P00058 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 10, 2025 | P00073 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 2, 2025 | P00072 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 31, 2025 | P00070 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 31, 2025 | P00071 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 27, 2025 | P00069 | $80.0K | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 26, 2025 | P00068 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 13, 2025 | P00067 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Mar 12, 2025 | P00066 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Feb 28, 2025 | P00057 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Feb 28, 2025 | P00065 | $500.0K | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jan 31, 2025 | P00064 | $134.1M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jan 16, 2025 | P00060 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Dec 31, 2024 | P00062 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDER |
| Dec 20, 2024 | P00063 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDER |
| Dec 4, 2024 | P00061 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDER |
| Nov 26, 2024 | P00059 | $40.0K | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Nov 19, 2024 | P00056 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Oct 31, 2024 | P00054 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Oct 30, 2024 | P00050 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Oct 30, 2024 | P00055 | $132.3M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Oct 15, 2024 | P00051 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Oct 15, 2024 | P00053 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Sep 27, 2024 | P00052 | $34.1M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Sep 24, 2024 | P00049 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Sep 6, 2024 | P00048 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Sep 4, 2024 | P00046 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 30, 2024 | P00047 | $16.2M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 23, 2024 | P00043 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 22, 2024 | P00045 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 13, 2024 | P00044 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 9, 2024 | P00042 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Aug 2, 2024 | P00041 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jul 29, 2024 | P00040 | $113.6M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jul 26, 2024 | P00039 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jul 11, 2024 | P00038 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 28, 2024 | P00037 | $57.3M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 25, 2024 | P00036 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 14, 2024 | P00035 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 13, 2024 | P00033 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 11, 2024 | P00031 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 11, 2024 | P00034 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Jun 10, 2024 | P00032 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 31, 2024 | P00030 | $46.6M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 24, 2024 | P00028 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| May 21, 2024 | P00029 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 29, 2024 | P00027 | $56.1M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 18, 2024 | P00026 | $0 | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
| Apr 4, 2024 | P00025 | $0 | ORRCC TASK ORDERS |
| Mar 29, 2024 | P00024 | $39.5M | ORRCC TASK ORDERS |
| Mar 26, 2024 | P00023 | $0 | ORRCC TASK ORDERS |
| Feb 29, 2024 | P00020 | $0 | ORRCC TASK ORDERS |
| Feb 29, 2024 | P00021 | $0 | ORRCC TASK ORDERS |
| Feb 29, 2024 | P00022 | $56.4M | ORRCC TASK ORDERS |
| Feb 28, 2024 | P00019 | $0 | ORRCC TASK ORDERS |
| Jan 31, 2024 | P00017 | $0 | ORRCC TASK ORDERS |
| Jan 31, 2024 | P00018 | $0 | ORRCC TASK ORDERS |
| Dec 22, 2023 | P00016 | $83.8M | ORRCC TASK ORDERS |
| Nov 24, 2023 | P00015 | $0 | ORRCC TASK ORDERS |
| Nov 22, 2023 | P00014 | $0 | ORRCC TASK ORDERS |
| Nov 21, 2023 | P00008 | $0 | ORRCC TASK ORDERS |
| Nov 16, 2023 | P00012 | $2.0M | ORRCC TASK ORDERS |
| Oct 27, 2023 | P00011 | $86.6M | ORRCC TASK ORDERS |
| Sep 28, 2023 | P00010 | $17.3M | ORRCC TASK ORDERS |
| Sep 20, 2023 | P00006 | $0 | ORRCC TASK ORDERS |
| Aug 31, 2023 | P00009 | $-0 | ORRCC TASK ORDERS |
| Aug 24, 2023 | P00007 | $0 | ORRCC TASK ORDERS |
| Jul 24, 2023 | P00003 | $0 | ORRCC TASK ORDERS |
| Jul 24, 2023 | P00005 | $174.2M | ORRCC TASK ORDERS |
| Jul 21, 2023 | P00004 | $0 | ORRCC TASK ORDERS |
| Jul 18, 2023 | P00002 | $0 | ORRCC TASK ORDERS |
| May 25, 2023 | P00001 | $122.1M | ORRCC TASK ORDERS |
| May 17, 2023 | 0 | $439.1M | OAK RIDGE RESERVATION CLEANUP CONTRACT TASK ORDERS |
Estimated positioning window
Feb 27, 2031 – Aug 27, 2031
40/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 40/100. Available recorded signals: 35 points.
- Contract end 2032-02-27 (1951 days from calculation)
- +5 points
- 2 historical awards in this buyer and category group
- +10 points
- 122 recorded award transactions
- +10 points
- Latest award action: 2026-08-28
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.