FRENCHMAN CREEK SUBSTATION HVAC PROJECT - WESTERN AREA POWER ADMINISTRATION (WAPA) ROCKY MOUNTAIN REGION HAS A REQUIREMENT WITH THE PRINCIPLAL COMPONENTS OF WORK TO PROVIDE ALL MATERIALS, LABOR, AND EQUIPMENT FOR REMOVAL AND PROPER DISPOSAL OF EXISTI

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeWESTERN-ROCKY MOUNTAIN REGION
NAICS238220 — Plumbing, Heating, and Air-Conditioning Contractors
PSCN041 — Installation of Equipment: Refrigeration, Air Conditioning, and Air Circulating Equipment
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$34.7K
Current contract value$34.7K
Potential contract value / ceiling$34.7K
Start dateAug 13, 2025
Current end dateJun 18, 2026
Potential end dateJun 18, 2026
Latest award activityJun 18, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 18, 2026P00001$0MODIFICATION 001 - CLOSEOUT FRENCHMAN CREEK SUBSTATION HVAC PROJECT
Aug 13, 20250$34.7KFRENCHMAN CREEK SUBSTATION HVAC PROJECT - WESTERN AREA POWER ADMINISTRATION (WAPA) ROCKY MOUNTAIN REGION HAS A REQUIREMENT WITH THE PRINCIPLAL COMPONENTS OF WORK TO PROVIDE ALL MATERIALS, LABOR, AND EQUIPMENT FOR REMOVAL AND PROPER DISPOSAL OF EXISTI

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Pratt, John W.Contactjpratt@wapa.gov
720-962-7166
SourceJun 16, 2025
Pratt, John W.Contactjpratt@wapa.gov
720-962-7166
SourceJun 16, 2025