Federal contract award

89503420CWA000042

CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeWESTERN-UPPER GREAT PLAINS REGION
NAICS237130 — Power and Communication Line and Related Structures Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$971.6K
Current contract value$1.3M
Potential contract value / ceiling$1.3M
Start dateSep 8, 2020
Current end dateNov 30, 2023
Potential end dateNov 30, 2023
Latest award activityJul 16, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 16, 2026P00013$0CLOSEOUT MODIFICATION FOR CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22 CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA.
Nov 13, 2023P00012$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P0012 - ADD FUNDING FOR VIQ
Sep 26, 2023P00011$-13.8KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00011 - TRANSMITTAL 8 DEMOLITION DELETION CREDIT
Feb 7, 2023P00010$21.8KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00010 - ADDITIONAL BUS WORK, REMOBILIZATION DEMOBILIZATION AND COMPLETION DATE EXTENSIO
Sep 28, 2022P00009$2.7KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00009 - TRANSMITTAL 7 GROUNDING CHANGE AND ADDED 2-4" CONDUIT
Aug 25, 2022P00008$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00008 - TIME EXTENSION
Jul 12, 2022P00007$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00007 - TIME EXTENSION
Mar 18, 2022P00006$29.6KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00006 - VARIATION OF QUANTITIES AND REMOBILIZATION
Nov 8, 2021P00005$0EO14042 CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00005 - COMPLETION DATE EXTENSION
Sep 20, 2021P00004$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00004 - TRANSMITTAL 6 CONDUIT CHANGE.
Sep 2, 2021P00003$1.2KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00003 - EQUITABLE ADJUSTMENT FOR PRICE INCREASE IN PVC.
Aug 18, 2021P00002$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00002 - CONTRACT EXTENSION
Dec 9, 2020P00001$0CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA P00001 - CREDIT FOR REDUCED SIZE OF PULL BOXES SS1 AND SS2 OUTLINED IN TRANSMITTAL #1
Sep 8, 20200$930.0KCONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Jonathan DittmerContactDittmer@wapa.gov
6053532641
SourceAug 11, 2020
Jonathan DittmerContactDittmer@wapa.gov
6053532641
SourceJul 21, 2020
Jonathan DittmerContactDittmer@wapa.gov
6053532641
SourceJul 6, 2020

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.