Federal contract award
89503424PWA001816
SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | WESTERN-UPPER GREAT PLAINS REGION |
| NAICS | 335313 — Switchgear and Switchboard Apparatus Manufacturing |
| PSC | 5975 — Electrical Hardware and Supplies |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $331.3K |
| Current contract value | $331.3K |
| Potential contract value / ceiling | $331.3K |
| Start date | Apr 12, 2024 |
| Current end date | Dec 26, 2025 |
| Potential end date | Dec 26, 2025 |
| Latest award activity | Jul 31, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 31, 2026 | P00004 | $0 | MOD 004 - CLOSEOUT FOR MOD P00003 - EXTEND COMPLETION DATE TO 12/26/25. SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS. |
| Nov 19, 2025 | P00003 | $0 | MOD P00003 - EXTEND COMPLETION DATE TO 12/26/25. SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS. |
| Apr 29, 2025 | P00002 | $0 | MOD P00002 - EXTEND COMPLETION DATE TO NOV 2025. SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS. |
| Mar 9, 2025 | P00001 | $0 | MOD P0000001 - ADMIN MOD TO CHANGE INV APPROVING OFFICIAL. SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS. |
| Apr 12, 2024 | 0 | $331.3K | SF6 CIRCUIT SWITCHERS FOR USE ON BACK-TO-BACK OPERATED SHUNT CAPACITOR BANKS PER THE ASSOCIATED SPECIFICATIONS. |