Federal contract award

AID294TO1700010

IGF::CL::IGF LOCAL CONSTRUCTION PROGRAM - SAQA CC IQC - JERICHO TO

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyAgency for International Development
OfficeUSAID/WEST BANK GAZA
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1NZ — CONSTRUCTION OF OTHER UTILITIES
Parent award / vehicleAID294I1300005
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$5.5M
Current contract value$6.5M
Potential contract value / ceiling$6.5M
Start dateSep 28, 2017
Current end dateFeb 17, 2023
Potential end dateFeb 17, 2023
Latest award activityFeb 15, 2023
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 15, 20239$-1.0MLOCAL CONSTRUCTION PROGRAM JERICHO COLLECTION SYSTEM EXPANSION PHASE 1B BRANCH SEWERS - DE-OBLIGATE EXCESS FUNDS
May 24, 20198$0LOCAL CONSTRUCTION PROGRAM JERICHO COLLECTION SYSTEM EXPANSION PHASE 1B BRANCH SEWERS - CHANGE ORDER NO .SEVEN
May 15, 20197$0LOCAL CONSTRUCTION PROGRAM JERICHO COLLECTION SYSTEM EXPANSION PHASE 1B BRANCH SEWERS - CHANGE ORDER
Mar 4, 20196$0LOCAL CONSTRUCTION PROGRAM JERICHO COLLECTION SYSTEM EXPANSION PHASE 1B BRANCH SEWERS - CHANGE ORDER
Jan 27, 201910$-263.7KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE EXPIRING FUNDS AND TO CHANGE THE CONTRACTING OFFICER'S REPRESENTATIVE.
Dec 17, 20183$0EGI JERICHO WW COLLECTION TO MAKE CHANGES TO SECTION J
Dec 17, 20184$0EGI JERICHO WW COLLECTION MODIFY THE FOLLOWING SECTIONS: 1. SUB-SECTION B.3 BUDGET 2. SUB-SECTION F.1 PERIOD OF PERFORMANCE 3. SECTION J LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
Dec 17, 20185$0LOCAL CONSTRUCTION PROGRAM JERICHO COLLECTION SYSTEM EXPANSION PHASE 1B BRANCH SEWERS
Dec 14, 20182$0EGI JERICHO WW COLLECTION TO MAKE CHANGES TO SECTION J
Jan 24, 20181$0IGF::CL::IGF LOCAL CONSTRUCTION PROGRAM - SAQA CC IQC - JERICHO TO WRI IGF::CL::IGF LOCAL CONSTRUCTION PROGRAM - SAQA CC IQC MAKE AN ADMINISTRATIVE MODIFICATION IN ORDER TO REFLECT THE CONTRACTOR'S DUNS NUMBER AS WELL AS REFLECT THE CONTRACTOR'S REGISTRATION IN THE SYSTEM FOR AWARD MANAGEMENT (SAM) IN THE GLAAS SYSTEM.
Sep 28, 20170$6.5MIGF::CL::IGF LOCAL CONSTRUCTION PROGRAM - SAQA CC IQC - JERICHO TO