Federal contract award
AID472TO1500003
IGF::OT::IGF - TO SUB-OBLIGATE FUNDS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Agency for International Development |
| Office | USAID/RDMA/THAILAND |
| NAICS | 541990 — All Other Professional, Scientific, and Technical Services |
| PSC | R425 — Engineering and Technical Services |
| Parent award / vehicle | AID486I1400001 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $1.8M |
| Current contract value | $1.8M |
| Potential contract value / ceiling | $1.8M |
| Start date | Apr 3, 2015 |
| Current end date | Sep 23, 2022 |
| Potential end date | Sep 23, 2022 |
| Latest award activity | Sep 23, 2022 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 23, 2022 | P00001 | $-32.1K | DE-OBLIGATING DUE TO CANCELLING FUNDS. |
| Jun 29, 2021 | 8 | $0 | PURPOSE OF THIS MODIFICATION IS TO REVISE THE SECTION 889 WAIVER IN GLAAS. |
| Aug 12, 2020 | 7 | $0 | AVANSA M&E TIME EXTENSION |
| Jul 18, 2019 | 6 | $0 | TO MODIFY THE CONTRACT BY EXTENDING THE END DATE WITH NO ADDITIONAL COST FROM APRIL 2, 2020 TO SEPTEMBER 30, 2020. |
| Nov 7, 2018 | 5 | $0 | IGF::OT::IGF - TO MODIFY THE CONTRACT BY REALIGNING THE BUDGET. |
| Aug 7, 2017 | 4 | $-176.7K | IGF::OT::IGF - TO MODIFY THE CONTRACT BY: 1. DE-SCOPING THE SOW, 2. REDUCING THE TEC; AND 3. DE-OBLIGATING $176,673.29. |
| Mar 20, 2017 | 3 | $400.0K | IGF::OT::IGF - TO MODIFY THE CONTRACT BY ADDING $400,000. |
| Sep 8, 2016 | 2 | $400.0K | IGF::OT::IGF - TO MODIFY THE CONTRACT BY ADDING $400,000. |
| Aug 11, 2015 | 1 | $0 | IGF::OT::IGF - TO MODIFY THE CONTRACT BY: (1)REVISING THE DEADLINE FOR THE DAC EVALUATION DESIGN TO WITHIN 4 MONTHS OF TASK ORDER START DATE (EFFECTIVE AUG 3); (2) REVISING THE DEADLINE FOR THE AVANSA AGRIKULTURA MID-TERM PE DESIGN TO EVALUATION DESIGN SUBMITTED AT LEAST 30 DAYS PRIOR TO MID-TERM PE FIELDWORK DATA COLLECTION (FIELD WORK DATA COLLECTION DATE TO BE DETERMINED BY USAID AT A LATER TIME); AND (3)REVISING THE DEADLINE FOR THE AVANSA AGRIKULTURA FINAL PE DESIGN TO EVALUATION DESIGN SUBMITTED AT LEAST 30 DAYS PRIOR TO FINAL PE FIELDWORK DATA COLLECTION (FIELD WORK DATA COLLECTION DATE TO BE DETERMINED BY USAID AT A LATER TIME). |
| Apr 3, 2015 | 0 | $1.2M | IGF::OT::IGF - TO SUB-OBLIGATE FUNDS. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.