200112!001282!2100!CA63 !USA ENGINEER DISTRICT,FORT WORTH!DACA6301C0009 !A!N!*!N! !20010927!20020930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !2300 VICTORY DRIVE !COLUMBUS !GA!31901!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000500000!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !1000!NOT DISCERNABLE OR CLASSIFIED !221210!*!*!3! ! ! !*!*!*!B!*!*!A! !A !N!J!2!001!B! !Z!N!Z! ! !N!C!N! ! ! !C!C!A!A!000!A!A!N! ! ! ! ! ! !0001!
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QM MICC-FT BENNING |
| NAICS | 221210 — Natural Gas Distribution |
| PSC | S111 — Gas Services |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $88.4M |
| Current contract value | $38.2M |
| Potential contract value / ceiling | $38.2M |
| Start date | Sep 27, 2001 |
| Current end date | Sep 26, 2051 |
| Potential end date | Sep 26, 2051 |
| Latest award activity | Jun 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 197 of 197 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 4, 2026 | P00201 | $445.5K | LIBERTY GAS UTILITIES |
| Mar 11, 2026 | P00200 | $29.6K | LIBERTY GAS UTILITIES |
| Mar 10, 2026 | P00199 | $289.6K | LIBERTY GAS UTILITIES |
| Jan 22, 2026 | P00198 | $289.6K | LIBERTY GAS UTILITIES |
| Jan 13, 2026 | P00197 | $289.6K | LIBERTY GAS UTILITIES |
| Sep 30, 2025 | P00196 | $56.8K | FY25 O/M FUNDING REMAINDER FY25 JULY - SEPT |
| Sep 5, 2025 | P00195 | $-85.1K | FY25 O/M FUNDING REMAINDER FY25 JULY - SEPT |
| Aug 26, 2025 | P00194 | $0 | FY25 O/M FUNDING REMAINDER FY25 JULY - SEPT |
| Jul 10, 2025 | P00193 | $434.4K | FY25 O/M FUNDING REMAINDER FY25 JULY - SEPT |
| Jun 13, 2025 | P00192 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| Jun 11, 2025 | P00191 | $144.8K | INSTALL 10" STEEL MAIN SH TO HC |
| Apr 24, 2025 | P00190 | $-230.0K | INSTALL 10" STEEL MAIN SH TO HC |
| Apr 9, 2025 | P00189 | $3.2M | INSTALL 10" STEEL MAIN SH TO HC |
| Sep 13, 2024 | P00188 | $34.1K | INSTALL 10" STEEL MAIN SH TO HC |
| Aug 9, 2024 | P00187 | $11.5K | GAS SERVICE TO BUILDING 17 SECTIONS E&F |
| Aug 6, 2024 | P00186 | $57.8K | NATURAL GAS SERVICE TO BUILDING 2888 |
| Jul 22, 2024 | P00185 | $24.1K | INSTALL 10" STEEL MAIN SH TO HC |
| Jul 17, 2024 | P00184 | $-32.9K | INSTALL 10" STEEL MAIN SH TO HC - DEOB |
| Jun 21, 2024 | P00183 | $3.8M | FY 24 FUNDING FOR O&M AND R&R PROJECTS |
| Aug 18, 2023 | P00182 | $858.9K | ADD FUNDS FOR FY21 AND FY22 UNMETERED GAS USAGE. |
| Aug 11, 2023 | P00181 | $81 | INSTALL 10" STEEL MAIN SH TO HC |
| Jul 21, 2023 | P00180 | $9 | ADMIN MOD TO CORRECT TYPO, $9.00 DIFFERENCE AND ADD TIKTOK CLAUSE. |
| Jul 17, 2023 | P00179 | $-828.0K | DE-OBLIGATE FY18 UNUSED FUNDS. |
| May 24, 2023 | P00178 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| May 10, 2023 | P00177 | $102.1K | INSTALL GAS TO SOF BN HQ |
| Mar 28, 2023 | P00176 | $3.3M | FY23 YEAR 22 OF CONTRACT FOR OPERATION AND MAINTENQNCE (O&M) AND REPAIR AND REHAB (R&R). |
| Mar 27, 2023 | P00175 | $60.0K | INSTALL 10" STEEL MAIN SH TO HC |
| Mar 21, 2023 | P00174 | $1.2K | INSTALL GAS SERVICE TO MWR GOLF COURSE MAINTENANCE FACILITY. |
| May 5, 2022 | P00173 | $3.7M | INSTALL 10" STEEL MAIN SH TO HC |
| Mar 18, 2022 | P00172 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| Feb 7, 2022 | P00171 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| Dec 7, 2021 | P00170 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| Sep 24, 2021 | P00169 | $0 | ADD ANTI BYPASS AGREEMENT |
| Sep 14, 2021 | P00168 | $0 | INSTALL 10" STEEL MAIN SH TO HC |
| Jul 30, 2021 | P00167 | $3.8M | INSTALL 10" STEEL MAIN SH TO HC |
| Sep 30, 2020 | P00166 | $85.1K | INSTALL 10" STEEL MAIN SH TO HC |
| Apr 22, 2020 | P00165 | $20.9K | INSTALL 625' GAS LINE AT BLDG. 5502 |
| Mar 30, 2020 | P00164 | $3.5M | INSTALL 10" STEEL MAIN SH TO HC |
| Jul 18, 2019 | P00163 | $6.5M | INSTALL 10" STEEL MAIN SH TO HC |
| Apr 30, 2019 | P00162 | $22.5K | INSTALL 10" STEEL MAIN SH TO HC |
| Apr 12, 2019 | P00161 | $-545.0K | DEOBLIGATION OF FUNDS |
| Sep 21, 2018 | P00160 | $1.7M | INSTALL 10" STEEL MAIN SH TO HC |
| Aug 8, 2018 | P00159 | $-392 | DEOBLIGATE FUNDS. |
| Jun 13, 2018 | P00158 | $4.8M | INSTALL 10" STEEL MAIN SH TO HC |
| Sep 1, 2017 | P00157 | $608 | INSTALL 10" STEEL MAIN SH TO HC |
| Aug 25, 2017 | P00156 | $-608 | INSTALL 10" STEEL MAIN SH TO HC |
| Jun 1, 2017 | P00155 | $6.4M | INSTALL 10" STEEL MAIN SH TO HC |
| Jan 26, 2017 | P00154 | $0 | ADDED ANTIBYPASS AGREEMENT TO CONTRACT FOR 1 DECEMBER 2016 THROUGH 31 MAY 2017. |
| Dec 7, 2016 | P00153 | $44.5K | RELOCATE GAS LINE AT THE POST EXCHANGE AND INSTALL GAS LINE AND METERING IN BUILDING 9107. |
| Sep 27, 2016 | P00152 | $150.0K | INSTALL GAS METERS WITH REMOTE READ AND MONITORING CAPABILITIES. |
| Apr 25, 2016 | P00151 | $45.3K | INSTALL GAS LINES AND METERING IN BUILDINGS 3035 AND 3020. |
| Mar 31, 2016 | P00150 | $6.6M | ADD O&M AND R&R FUNDS YEAR 15 |
| Mar 9, 2016 | P00149 | $-16.6K | MODIFICATION TO DE-OB FUNDS FROM CLIN 0144. |
| Dec 15, 2015 | P00148 | $20.4K | ADD CLIN 0229 - INSTALL GAS AT MCBRIDE ELEMENTARY SCHOOL |
| Sep 30, 2015 | P00147 | $0 | NATURAL GAS ANTI-BYPASS AGREEMENT EFFECTIVE 1 OCTOBER 2015 |
| Sep 24, 2015 | P00146 | $140.0K | ADD CLIN 0228 |
| Sep 15, 2015 | P00145 | $6.1M | LIBERTY UTILITIES PRICE REDETERMINATION 1 APR 15 THRU 31 MAR 16 |
| Jul 13, 2015 | P00144 | $40.0K | ADD CLINS 0225 AND 0226 |
| Apr 13, 2015 | P00143 | $9.9K | ADD CLINS 0223 AND 0224 |
| Apr 2, 2015 | P00142 | $0 | ADD FAR CLAUSES 52.204-9 AND 52.222-50 |
| Mar 16, 2015 | P00141 | $232.8K | LIBERTY UTILITIES - ADD CLINS 0221 AND 0222 |
| Feb 9, 2015 | P00140 | $28.7K | ADD CLIN 0220 - INSTALL NATURAL GAS SERVICE TO B2834 |
| Jan 30, 2015 | P00139 | $9.6K | ADD CLIN 0219 - INSTALL NATURAL GAS SVC AT B3023 |
| Sep 30, 2014 | P00138 | $8.8M | INSTALL 10" STEEL MAIN SH TO HC |
| Sep 29, 2014 | P00137 | $2.5M | INSTALL NATURAL GAS SVC - ADD CLINS 0215, 0216 AND 0217 |
| Sep 25, 2014 | P00136 | $0 | NOVATION AGREEMENT - CHANGE-OF-NAME IAW FAR SUBPART 42.12 |
| Sep 23, 2014 | P00135 | $850.0K | ADD CLINS 0212, 0213 AND 0214 |
| Aug 19, 2014 | P00134 | $0 | MODIFICATION TO ADD CLIN 0211 - INSTALL NAT GAS SVC B2833 |
| Aug 13, 2014 | P00133 | $28.7K | MODIFICATION TO ADD CLIN 0211 - INSTALL NAT GAS SVC B2833 |
| Aug 7, 2014 | P00132 | $68.3K | MODIFICATION TO ADD CLIN 0210 - INSTALL NATURAL GAS SERVICE TO B2833 |
| Jul 22, 2014 | P00131 | $9.4K | INSTALL NATURAL GAS SERVICE TO BLDG. 4303 |
| May 12, 2014 | P00130 | $2.6K | GAS MAIN ALONG SIGHTSEEING RD |
| Mar 20, 2014 | P00129 | $0 | JAN 04 USAGE |
| Feb 27, 2014 | P00128 | $17.4K | NATURAL GAS SERVICE FOR BUILDINGS 5004, 5005, 5008, 5009, 5024, AND 5034. (LIBERTY UTILITIES) |
| Sep 13, 2013 | P00127 | $35.3K | INSTALL NATURAL GAS SERVICE TO BUILDING 3240, SAND HILL. |
| Sep 9, 2013 | P00126 | $204.3K | JAN 04 USAGE |
| Aug 20, 2013 | P00125 | $54.7K | MODIFICATION ADDING CLIN 0202 (INSTALL NATURAL GAS SERVICE TO STARSHIP BLDG 3245); AND CLIN 0203 (INSTALL NATURAL GAS SERVICE TO STARSHIP BLDG 3335). |
| Aug 12, 2013 | P00124 | $255.1K | UTILITY INFRASTRUCTURE |
| Jun 24, 2013 | P00123 | $0 | ADMINISTRATIVE MODIFICATION CORRECTING THE ADDRESS. ALSO IN AN EFFORT TO DELETE IDOC ERRORS DID A GLOBAL CHANGE ON THE DELIVERY DATE TO MATCH THE EXPIRATION OF THE CONTRACT VERSES EACH INDIVIDUAL MODIFICATION. |
| Jun 19, 2013 | P00122 | $2.8K | INSTALL NATURAL GAS, BLDG 5001, CAMP ROGERS - HARMONY CHURCH |
| Jun 5, 2013 | P00121 | $17.3K | INSTALL NATURAL GAS, BLDGS 9136&9137. |
| May 7, 2013 | P00120 | $72.9K | CLIN 0197, INSTALL NATURAL GAS SERCIE TO THE NEW MWR 860 ROOM LODGE, BLDG 1670. CLIN 0198, CLASSROOM&DINING REPLACEMENT OF GAS SERVICE FOR BUILDING 3210. |
| Apr 26, 2013 | P00119 | $0 | JAN 04 USAGE |
| Mar 22, 2013 | P00118 | $9.4K | MOD ADDING CLIN 0196 FOR THE INSTALLATION OF NATURAL GAS AT BUILDING 2762. |
| Feb 26, 2013 | P00117 | $29.2K | ADD CLIN(S) 0194 AND 0195 FOR INSTALLATION OF GAS LINES AND METERS. (ATMOS ENERGY) |
| Jan 2, 2013 | P00116 | $66.2K | MODIFICATION WAS ISSUED TO ADD CLINS 192 AND 193 |
| Nov 8, 2012 | P00115 | $22.5K | MODIFICATION TO ADD CLINS 0190 AND 0191 TO THE CONTRACT. |
| Sep 17, 2012 | P00114 | $288.6K | MODIFICATION TO ADD CLIN 0189 TO THE CONTRACT. |
| Aug 24, 2012 | P00113 | $95.5K | MODIFICATION TO ADD CLINS 0186 THROUGH 0188 TO THE CONTRACT. |
| Jul 20, 2012 | P00112 | $313.3K | MODIFICATION TO ADD CLIN 0185 FOR THE INSTALLATION OF NATURAL GAS TO THE NEW HOSPITAL. |
| Jun 29, 2012 | P00111 | $-2.4K | MODIFICATION TO DE-OBLIGATE FUNDS ON CLIN 0053. |
| Jun 5, 2012 | P00110 | $6.3K | MODIFICATION TO ADD CLIN 0184 TO THE CONTRACT FOR WORK WITHIN SCOPE. |
| Apr 19, 2012 | P00109 | $22.5K | MODIFICATION TO ADD CLINS 0182 AND 0183 TO THE CONTRACT |
| Mar 19, 2012 | P00108 | $487.4K | MODIFICATION TO ADD CLINS 0175 THRU 0181 FOR WORK WITHIN SCOPE. |
| Feb 6, 2012 | P00107 | $84.0K | MODIFICATION TO ADD CLINS 0173 AND 0174 FOR ADDITIONAL |
| Feb 1, 2012 | P00106 | $550.6K | MODIFICATION TO ADD CLINS 0170 THRU 0172 TO ADD WORK TO THE CONTRACT. |
| Jan 6, 2012 | P00104 | $737 | MODIFICATION TO ADD CLIN 0169 FOR SERVICE TO WORKING DOG KENNEL. |
| Jan 6, 2012 | P00105 | $-2.5K | MODIFICATION TO DELETE EXCESS FUNDS. |
| Sep 6, 2011 | P00103 | $24.0K | MODIFICATION TO ADD CLINS 0166, 0167 AND 0168 FOR THE INSTALLATION OF NATURAL GAS. |
| Aug 31, 2011 | P00102 | $81.9K | MODIFICATION TO ADD CLINS 0162 THROUGH 0165 FOR THE INSTALLATION OF NATURAL GAS. |
| Aug 23, 2011 | P00100 | $473.0K | MODIFICATION TO ADD CLINS 0160 AND 0161 TO THE CONTRACT. |
| Aug 23, 2011 | P00101 | $-9.2K | MODIFICATION TO DEOBLIGATE EXCESS FUNDS |
| Aug 10, 2011 | P00099 | $313.9K | MODIFICATION TO ADD CLINS 0157 - 0159 FOR ADDITIONAL WORK |
| Jun 9, 2011 | P00098 | $97.3K | MODIFICATION TO ADD CLINS 0151 THRU 0156 TO THE CONTRACT. |
| May 2, 2011 | P00097 | $1.5K | MODIFICATION TO ADD CLIN 0150. |
| Apr 12, 2011 | P00096 | $24.9K | MODIFICATION TO ADD CLINS 0148 AND 0149 FOR WORK WITHIN SCOPE OF CONTRACT. |
| Apr 5, 2011 | P00095 | $239.1K | MODIFICATION TO ADD CLINS 0146 AND 0147 TO THE CONTRACT FOR THE INSTALLATION OF NATURAL GAS. |
| Mar 21, 2011 | P00094 | $124.7K | MODIFICATION TO AD CLIN 0145 FOR INSTALLATION OF NATURAL GAS TO ECC. |
| Mar 3, 2011 | P00093 | $28.3K | MODIFICATION TO ADD CLIN 0144 TO THE CONTRACT FOR WORK WITHIN SCOPE. |
| Feb 17, 2011 | P00092 | $132.2K | MODIFICATION TO ADD CLINS 0142 AND 0143 TO THE CONTRACT FOR THE INSTALLATION OF NATURAL GAS TO BRAC PROJECTS. |
| Feb 14, 2011 | P00091 | $0 | MODIFICATION TO ADD DFARS CLAUSE 252.222-7006 |
| Dec 27, 2010 | P00090 | $5.9K | MODIFICATION TO ADD CLINS 0139-0141 FOR NATURAL GAS SERVICES. |
| Nov 23, 2010 | P00089 | $292.7K | MODIFICATION TO ADD CLINS 0137 AND 0138 FOR BRAC PROJECTS. |
| Sep 27, 2010 | P00088 | $12.6K | MODIFICATION TO ADD CLIN 0136 FOR THE INSTALLATION OF GAS SERVICE TO BUILDING 466. |
| Sep 21, 2010 | P00087 | $19.5K | MODIFICATION TO ADD CLIN 0134 AND 0135 FOR WORK TO BE PERFORMED ON BUILDING 4 RENOVATION PROJECT AND THE RELOCATION OF GAS LINE AT BLDG 3415. |
| Sep 15, 2010 | P00086 | $1.0M | MODIFICATION TO ADD CLINS 0131 BRAC BARRACKS PROJECT, 0132 BRAC WAREHOUSE COSTS AND 0133 CONSOLIDATED DINING FACILITY PROJECT. |
| Sep 13, 2010 | P00085 | $9.4K | JAN 04 USAGE |
| Aug 20, 2010 | P00084 | $400.8K | TO ADD CLINS 123 - 129 FOR NATURAL GAS INSTALLATIONS AND SERVICE. |
| May 26, 2010 | P00083 | $16.7K | INSTALL NATURAL GAS SERVICE TO WEAPONS REPAIR SHOP. |
| Apr 29, 2010 | P00082 | $702 | JAN 04 USAGE |
| Mar 18, 2010 | P00081 | $34.4K | INSTALL GAS SERVICE TO HARMONY CHURCH ACP. |
| Mar 3, 2010 | P00080 | $4.3K | JAN 04 USAGE |
| Jan 8, 2010 | P00079 | $14.0K | JAN 04 USAGE P00079 |
| Dec 30, 2009 | P00078 | $148.9K | JAN 04 USAGE |
| Dec 2, 2009 | P00077 | $13.7K | JAN 04 USAGE INSTALL NATURAL GAS TO BUILDINGS 2752 AND BUILDING 67. |
| Nov 24, 2009 | P00076 | $70.5K | JAN 04 USAGE |
| Nov 13, 2009 | P00075 | $157.2K | JAN 04 USAGE BRAC PROJECT 65041A. TO INSTALL NATURAL GAS TO THE NEW MATOC BARRACKS, HARMONY CHURCH. |
| Nov 10, 2009 | P00074 | $478.0K | ADDING MAY 2009 - AUG 2009 MONTHLY INVOICES TO CONTRACT. |
| Oct 30, 2009 | P00073 | $9.2K | JAN 04 USAGE MODIFICATION P00073 TO INSTALL NATURAL GAS TO THE ARMOR OFFICER BASIC COURSE BATTALION HQS |
| Sep 18, 2009 | P00072 | $71.2K | JAN 04 USAGE MODIFICATION 0072 |
| Jul 29, 2009 | P00071 | $53.5K | JAN 04 USAGE RELOCATION OF GAS |
| Jun 9, 2009 | P00070 | $8.9K | JAN 04 USAGE |
| Apr 29, 2009 | P00069 | $94.7K | JAN 04 USAGE |
| Apr 24, 2009 | P00068 | $12.0K | JAN 04 USAGE |
| Mar 16, 2009 | P00067 | $639 | JAN 04 USAGE |
| Feb 24, 2009 | P00066 | $239.4K | TO ADD CLINS 0092-0097 FOR A TOTAL COST OF $239,370.06. |
| Jan 30, 2009 | P00065 | $67.8K | TO ADD CLIN 0090 SERVICE TO 3 BLDGS FOR BRAC PROJECTS 65394 & 65397 FOR $34,19.12 AND CLIN 0091 DEC MONTHLY PAYMENT FOR $33,608.79. |
| Jan 7, 2009 | P00064 | $-80.5K | DECREASE SUBCLINS 0064AD AND 0064AE; MOVE ALL CLIN 0083 SUBCLINS TO CLIN 0063; MOVE ALL 0084 SUBCLINS TO CLIN 0062. ADD NEW CLINS 0086-0089. |
| Dec 19, 2008 | P00063 | $486.1K | THIS ADDS PHASE 3, 4 AND 5 TO BRAC PROJECT 65439 AS SUBCLINS 0064AD, AE AND AF. |
| Dec 16, 2008 | P00062 | $3.7M | ADD CLINS 0083/0083AA-0083AE, 0084/0084AA-AE AND 0085 TO CONTRACT. |
| Nov 25, 2008 | P00061 | $561.6K | JAN 04 USAGE |
| Oct 8, 2008 | P00060 | $33.6K | 1-31 AUG 08 MONTHLY BILL |
| Sep 30, 2008 | P00059 | $1.4K | ADDS CLIN 0077, SERVICE TO BLDG 2053 FOR $1408.83 AND CORRECTS AN ADMINISTRATIVE ERROR FROM P00050. |
| Sep 19, 2008 | P00058 | $20.0K | TO ADD CLIN 0076, INSTALL NEW GAS SERVICE TO BLDG 243 FOR $20,000.00. |
| Sep 3, 2008 | P00057 | $33.6K | NEW WORK. |
| Aug 22, 2008 | P00056 | $120.0K | NEW WORK. |
| Aug 21, 2008 | P00055 | $525 | NEW WORK. |
| Aug 1, 2008 | P00054 | $13.2K | TO ADD CLIN 0072, INSTALL NATURAL GAS SERVICE TO SOF REGIMENTAL HQ, BLDG 2931 FOR $13,164.63. |
| Jul 17, 2008 | P00053 | $67.2K | TO ADD CLIN 0070, MAY MONTHLY SERVICE FEE FOR $33,608.79 AND CLIN 0071, JUNE MONTHLY SERVICE FEE FOR $33,608.79. |
| Jun 10, 2008 | P00052 | $-22.4K | DECREASE SUBCLIN 0052AB FROM $182,376.00 BY $22,376.00 TO $160,000.00. |
| Jun 3, 2008 | P00051 | $1.4K | TO ADD CLIN 0068, NATURAL GAS SERVICE TO NEW COMBATIVE BUILDING IN SAND HILL BLDG 3820 FOR $701.53. |
| Apr 30, 2008 | P00050 | $489.1K | TO ADD CLIN 0066 AND SUBCLINS 0066AA-0066AE, NATURAL GAS INFRASTRUCTURE FOR COE BRAC PROJECT 65068, SAND HILL FOR A TOTAL OF $201,850.29. ADD CLIN 0067 AND SUBCLINS 0066AA-0066AE, NATURAL GAS INFRASTRUCTURE FOR COE BRAC PROJECT 64370, HARMONY CHURCH FOR A TOTAL COST OF $287,250.29. |
| Apr 18, 2008 | P00049 | $33.6K | NATURAL GAS DISTRIBUTION SYSTEM MAINTENANCE FEE FOR MARCH 2008 |
| Mar 26, 2008 | P00048 | $1.2M | TO ADD CLIN 0061, FEBRUARY MONTHLY MAINTENANCE PAYMENT FOR $33,608.79; CLIN 0062/SUBCLIN 0062AA RUSSELL RD/JAMESTOWN RD BRAC PROJECT FOR $175,811.35; CLIN 0063/SUBCLIN 0063AA HARMONY CHURCH BRAC PROJECT FOR $896,595.74 AND CLIN 0064/SUBCLIN 0064AA, SAND HILL BRAC PROJECT FOR $86,652.50. |
| Feb 29, 2008 | P00047 | $33.2K | JAN 08 MONTHLY O&M COSTS |
| Feb 25, 2008 | P00046 | $702 | ADD CLIN 0059, INSTALL SERVICE TO BLDG 2601 FOR $701.53. |
| Feb 22, 2008 | P00045 | $132.2K | TO DECREASE CLIN 0054 TO FINAL INVOICED AMOUNT OF PROJECT, TO ADD CLINS 0055 THRU 0058 FOR SEPTEMBER THUR DECEMBER MONTHLY BILLING. |
| Dec 21, 2007 | P00044 | $884 | REPAIR GAS LINE AT BLDG 3215 |
| Oct 16, 2007 | P00043 | $-40.6K | TO DELETE CLIN 0028 AS WORK WAS PERFORMED UNDER NORMAL MONTHLY MAINTENANCE. |
| Sep 30, 2007 | P00042 | $2.4K | TO ADD CLIN 0053, SERVICE TO BLDG 3250 SANDHILL FOR $2,391.00. |
| Sep 25, 2007 | P00041 | $22.1K | TO ADD $$22,100 TO SUBCLIN 0052AB TO HANDLE THE INCREASED COST OF BORING UNDER RAILROAD TRACKS IN THE VICINITY OF EISENHOWER EXCHANGE. |
| Sep 24, 2007 | P00040 | $276 | TO ADD $276.00 TO SUBCLIN 0052AB AS IT WAS INADVERTENTLY LEFT OFF FROM P00039. |
| Sep 22, 2007 | P00039 | $475.2K | TO ADD CLIN 0051, AUGUST 2007 MONTHLY MAINTENANCE FOR $33,178.74 AND CLIN 0052 WITH SUBCLINS 0052AA, 0052AB AND 0053AC, INTERCONNECT MAIN POST NATURAL GAS DISTRIBUTION SYSTEM TO SANDHILL NATURAL GAS DISTRIBUTION SYSTEM FOR $442,276.00. |
| Aug 27, 2007 | P00038 | $33.1K | TO ADD CLIN 0050, JULY 2007 MONTHLY MAINTENANCE FEE FOR $33,178.74. |
| Aug 20, 2007 | P00037 | $0 | TO ADD LOCAL CLAUSE LC-058 FT. BENNING CONTRACTOR BADGING POLICY |
| Aug 3, 2007 | P00036 | $33.2K | TO ADD CLIN 0049, JUNE 2007 MONTHLY NATURAL GAS DISTRIBUTION SERVICE FOR $33,178.74. |
| Jul 11, 2007 | P00034 | $0 | CHANGE PAYING OFFICE FROM DFAS ORLANDO TO DFAS INDIANAPOLIS. |
| Jul 11, 2007 | P00035 | $1.3K | TO ADD CLIN 0048 FOR $1296.21 |
| Jun 21, 2007 | P00033 | $33.2K | ADD CLIN 0047, MAY 2007 MONTHLY MAINTENENACE FEE. |
| Jun 1, 2007 | P00032 | $33.2K | APRIL 2007 MONTHLY MAINTENANCE FEE |
| May 16, 2007 | P00031 | $33.2K | MONTHLY GAS MAINTENANCE PAYMENT FOR MARCH 2007. |
| Apr 27, 2007 | P00030 | $-3.1K | ADD CLIN 0044, IN THE AMOUNT OF $2,390.22 FOR NATURAL GAS SVC TO BLDG. 3271, AND DEOBLIGATE CLIN 0035, AS WORK IS NO LONGER REQUIRED. |
| Apr 10, 2007 | P00029 | $65.9K | ADD CLIN 0042 JANUARY GAS BILL FOR $32754.39 AND CLIN 0043 FEB GAS BILL FOR $33,178.74. |
| Mar 26, 2007 | P00028 | $551 | TO ADD CLIN 0041, GAS SERVICE TO NEW CUSTER ROAD SHOPPETTE. |
| Feb 21, 2007 | P00027 | $85.3K | ADDS CLIN 0037, DISCONNECT NATURAL GAS TO 38 SERVICE CONNECTIONS FOR $15300; CLIN 0038, REMOVE/RELOCATE 4" CAST IRON NATURAL GAS PIPE AT CORNER OF EDWARDS AND VIBBERT FOR $4,470.33; CLIN 0039, NOV MONTHLY BILL OF $32,754.39 AND CLIN 0040, DEC MONTHLY BILL FOR $32,754.39 |
| Feb 8, 2007 | P00026 | $8.0K | TO ADD CLIN 0035, REENERGIZE GAS MAIN FOR BLDG 3520 FOR $5500 AND CLIN 0036, INSTALL GAS SERVICE TO BLDG 3256 SANDHILL FOR $2469.50. |
| Jan 4, 2007 | P00025 | $0 | TO CHANGE CLIN 0024 AND 0027 TO INFORMATIONAL CLINS AND ADD 3 SUBCLINS. THIS IS NECESSARY SINCE EACH SUBCLIN IS A PHASE AND THE CONTRACTOR NEEDS TO BILL FOR EACH PHASE. |
| Dec 22, 2006 | P00024 | $32.8K | TO ADD CLIN 0034, OCTOBER 2006 BILLING. |
| Nov 8, 2006 | P00023 | $-2.7K | TO DECREASE CLIN 0029 TO ITS FINAL INVOICED AMOUNT. |
| Nov 3, 2006 | P00022 | $2.5K | TO ADD CLIN 0033, NATURAL GAS SERVICE TO NEW EMERGENCY GENERATOR BLDG 2783. |
| Aug 30, 2006 | P00021 | $12.4K | ADD NEW SERVICE, CLIN 0030 |
| Aug 8, 2006 | P00020 | $32.8K | NATURAL GAS REPAIR AND MAINTENANCE |
| Jul 20, 2006 | P00019 | $1.4K | NATURAL GAS REPAIR AND MAINTENANCE |
| Jul 12, 2006 | P00018 | $249.2K | NATURAL GAS REPAIR AND MAINTENANCE |
| Jun 14, 2006 | P00017 | $32.8K | NATURAL GAS REPAIR AND MAINTENANCE |
| May 16, 2006 | P00016 | $5.0K | NATURAL GAS SERVICE |
| Dec 21, 2005 | P00015 | $400.7K | 200603!600061!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00015!20051221!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000400723!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !99990909!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| May 27, 2005 | P00014 | $606 | 200509!501381!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00014!20050527!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000000606!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| May 5, 2005 | P00013 | $-1.7K | 200511!501166!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00013!20050505!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !-000000001692!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Apr 8, 2005 | P00012 | $13.2K | 200509!501042!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00012!20050408!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000013242!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Jan 25, 2005 | P00009 | $756.9K | 200504!500189!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00009!20050125!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000756916!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Jan 24, 2005 | P00008 | $9.3K | 200504!500148!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00008!20050124!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000009290!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Nov 1, 2004 | P00007 | $162.7K | 200502!500045!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00007!20041101!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !5430 LBJ FREEWAY STE 700 !DALLAS !TX!75240!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000162666!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !20200930!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Sep 22, 2004 | P00006 | $395.5K | 200412!001848!2100!W911SF!ACA, FORT BENNING !DACA6301C0009 !A!N! !N! !P00006!20040922!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !2300 VICTORY DRIVE !COLUMBUS !GA!31901!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000395540!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !000 !* !221210!E! !3! ! !D! ! !99990909!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Sep 16, 2003 | P00005 | $410.3K | 200312!001329!2100!BK03 !ACA, FORT BENNING !DACA6301C0009 !A!N! !N!P00005 !20030916!20030930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !2300 VICTORY DRIVE !COLUMBUS !GA!31901!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000410284!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !1000!NOT DISCERNABLE OR CLASSIFIED !221210!E! !3! ! !D! ! !99990909!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! ! |
| Sep 16, 2002 | P00003 | $276.0K | 200212!001028!2100!BT10 !U.S. ARMY INFANTRY CENTER & FORT!DACA6301C0009 !A!N! !N!P00003 !20020916!20020930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !2300 VICTORY DR !COLUMBUS !GA!31901!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000275983!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !1000!NOT DISCERNABLE OR CLASSIFIED !221210!E! !3! ! !D! ! !99990909!B! ! !A! !A!N!J!2!002!A! !Z!N!Z! ! !N!C!N! ! ! !Z!Z!A!A!000!A!B!N! ! ! ! ! ! !0001! |
| Sep 27, 2001 | 0 | $500.0K | 200112!001282!2100!CA63 !USA ENGINEER DISTRICT,FORT WORTH!DACA6301C0009 !A!N!*!N! !20010927!20020930!042723650!042723650!108203241!N!ATMOS ENERGY CORPORATION !2300 VICTORY DRIVE !COLUMBUS !GA!31901!30760!215!13!FORT BENNING !MUSCOGEE !GEORGIA !+000000500000!N!N!000000000000!S111!GAS SERVICES !S1 !SERVICES !1000!NOT DISCERNABLE OR CLASSIFIED !221210!*!*!3! ! ! !*!*!*!B!*!*!A! !A !N!J!2!001!B! !Z!N!Z! ! !N!C!N! ! ! !C!C!A!A!000!A!A!N! ! ! ! ! ! !0001! |
Estimated positioning window
Sep 26, 2050 – Mar 26, 2051
25/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 25/100. Available recorded signals: 20 points.
- Contract end 2051-09-26 (9095 days from calculation)
- +5 points
- 0 historical awards in this buyer and category group
- +0 points
- 197 recorded award transactions
- +10 points
- Latest award action: 2026-06-04
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.