OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | EM-ENVIRONMENTAL MGMT CON BUS CTR |
| NAICS | 221121 — Electric Bulk Power Transmission and Control |
| PSC | S112 — Electric Services |
| Parent award / vehicle | Not reported |
| Set-aside | Not reported |
| Pricing type | COST NO FEE |
| Obligations | $203.9M |
| Current contract value | $222.8M |
| Potential contract value / ceiling | $222.8M |
| Start date | Apr 15, 2003 |
| Current end date | Dec 31, 2029 |
| Potential end date | Dec 31, 2029 |
| Latest award activity | Aug 17, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 200 of 219 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 8, 2026 | 219 | $400.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Aug 17, 2026 | 218 | $1.9M | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| May 18, 2026 | 217 | $2.0M | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Mar 20, 2026 | 216 | $900.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Feb 23, 2026 | 215 | $900.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Jan 21, 2026 | 214 | $865.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Dec 16, 2025 | 213 | $425.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Nov 5, 2025 | 212 | $285.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Sep 25, 2025 | 211 | $0 | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Sep 18, 2025 | 210 | $0 | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Aug 21, 2025 | 209 | $1.5M | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Jul 8, 2025 | 208 | $530.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| May 15, 2025 | 207 | $670.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Mar 24, 2025 | 206 | $653.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Jan 13, 2025 | 205 | $640.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Nov 18, 2024 | 204 | $470.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Sep 24, 2024 | 203 | $180.0K | OVEC: THIS IS A FIXED UNIT RATE CONTRACT TO PROVIDE ELECTRIC UTILITY SERVICE FOR THE PORTSMOUTH GASEOUS DIFFUSION PLANT IN PIKE COUNTY, OHIO. THIS MODIFICATION PROVIDES INCREMENTAL FUNDING. |
| Aug 20, 2024 | 202 | $750.0K | DOE PORTSMOUTH/PADUCAH PROJECT OFFICE (PPPO) FIXED UNIT RATE CONTRACT FOR THE SUPPLY OF ELECTRICITY. THIS MODIFICATION ADDS INCREMENTAL FUNDING. |
| May 15, 2024 | 201 | $590.0K | DOE PORTSMOUTH/PADUCAH PROJECT OFFICE (PPPO) FIXED UNIT RATE CONTRACT FOR THE SUPPLY OF ELECTRICITY. THIS MODIFICATION ADDS INCREMENTAL FUNDING. |
| Feb 29, 2024 | 200 | $810.0K | DOE PORTSMOUTH/PADUCAH PROJECT OFFICE (PPPO) FIXED UNIT RATE CONTRACT FOR THE SUPPLY OF ELECTRICITY. THIS MODIFICATION ADDS INCREMENTAL FUNDING. |
| Sep 30, 2023 | 199 | $25.0K | DOE PORTSMOUTH/PADUCAH PROJECT OFFICE (PPPO) FIXED UNIT RATE CONTRACT FOR THE SUPPLY OF ELECTRICITY. THIS MODIFICATION ADDS INCREMENTAL FUNDING. |
| Sep 26, 2023 | 198 | $30.0K | DOE PORTSMOUTH/PADUCAH PROJECT OFFICE (PPPO) FIXED UNIT RATE CONTRACT FOR THE SUPPLY OF ELECTRICITY. THIS MODIFICATION ADDS INCREMENTAL FUNDING. |
| Apr 27, 2023 | 197 | $2.0M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 10, 2023 | 196 | $2.5M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Oct 31, 2022 | 195 | $1.2M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 21, 2022 | 194 | $285.0K | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 12, 2022 | 193 | $2.0M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 10, 2022 | 192 | $1.1M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 15, 2022 | 191 | $1.1M | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 26, 2022 | 190 | $711.0K | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Dec 15, 2021 | 189 | $925.0K | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Nov 23, 2021 | 188 | $0 | EO14042 ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Oct 20, 2021 | 187 | $590.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 21, 2021 | 186 | $210.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 21, 2021 | 185 | $1.1M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 19, 2021 | 184 | $775.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 28, 2021 | 183 | $711.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Dec 2, 2020 | 182 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 29, 2020 | 181 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 15, 2020 | 180 | $865.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 21, 2020 | 179 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jun 3, 2020 | 178 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Apr 7, 2020 | 177 | $851.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 11, 2020 | 176 | $335.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 30, 2019 | 175 | $366.6K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Aug 26, 2019 | 174 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 12, 2019 | 173 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 21, 2019 | 172 | $1.3M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Apr 19, 2019 | 171 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Feb 7, 2019 | 170 | $2.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 2, 2019 | 169 | $800.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 26, 2018 | 168 | $2.1M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 6, 2018 | 167 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Aug 20, 2018 | 166 | $1.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Aug 2, 2018 | 165 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 22, 2018 | 164 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Feb 23, 2018 | 163 | $2.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 31, 2018 | 162 | $1.7M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Dec 6, 2017 | 161 | $600.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 25, 2017 | 160 | $375.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 19, 2017 | 159 | $1.1M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jun 22, 2017 | 158 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Apr 12, 2017 | 157 | $1.5M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 19, 2017 | 156 | $3.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 20, 2016 | 155 | $-2.8M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jun 13, 2016 | 154 | $3.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 4, 2016 | 153 | $2.5M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Feb 19, 2016 | 152 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 29, 2015 | 151 | $5.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 1, 2015 | 150 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 26, 2015 | 149 | $3.3M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 9, 2015 | 148 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Feb 12, 2015 | 147 | $1.7M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 30, 2014 | 146 | $0 | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jun 10, 2014 | 145 | $900.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 15, 2014 | 144 | $1.8M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 13, 2014 | 142 | $4.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 4, 2014 | 141 | $300.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 31, 2014 | 140 | $200.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 17, 2014 | 139 | $1.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Dec 3, 2013 | 138 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Nov 21, 2013 | 137 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 26, 2013 | 136 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Aug 23, 2013 | 135 | $3.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Aug 6, 2013 | 134 | $200.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jul 1, 2013 | 133 | $514.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 13, 2013 | 132 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 28, 2013 | 131 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Feb 22, 2013 | 130 | $6.9M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 15, 2013 | 129 | $100.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Dec 5, 2012 | 128 | $235.9K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 28, 2012 | 127 | $200.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Sep 24, 2012 | 126 | $2.7M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jun 28, 2012 | 125 | $550.0K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 24, 2012 | 124 | $2.0M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| May 7, 2012 | 123 | $112.3K | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Mar 27, 2012 | 122 | $2.3M | ELECTRIC POWER SERVICE TO THE DEPARTMENT OF ENERGY PORTSMOUTH, OHIO SITE. |
| Jan 25, 2012 | 121 | $2.1M | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Dec 21, 2011 | 120 | $305.4K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Nov 2, 2011 | 119 | $50.0K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Sep 30, 2011 | 118 | $310.1K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Aug 24, 2011 | 117 | $3.5M | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDING. |
| Jul 28, 2011 | 116 | $1.5M | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THE MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Jun 30, 2011 | 115 | $24.0K | ELECTRIC POWER SERVICE TO THE PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Jun 21, 2011 | 114 | $200.0K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Jun 6, 2011 | 113 | $0 | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS FOR AN ADMINISTRATIVE CHANGE. |
| May 31, 2011 | 112 | $400.0K | ELECTRONIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| May 2, 2011 | 111 | $100.0K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDING. |
| Apr 6, 2011 | 110 | $200.0K | ELECTRIC POWER SERVICE TO THE PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDING. |
| Mar 30, 2011 | 109 | $500.0K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL FUNDING. |
| Mar 15, 2011 | 108 | $1.0M | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO ADD FUNDING. |
| Mar 2, 2011 | 107 | $200.0K | ELECTRIC POWER SERVICE TO PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO ADD FUNDING. |
| Feb 2, 2011 | 106 | $512.9K | ELECTRICAL POWER FOR PORTSMOUTH, OHIO SITE. THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS. |
| Jan 18, 2011 | 105 | $1.8M | TO FURNISH POWER TO THE PORTSMOUTH/PIKETON PLANT (PPPO) |
| Dec 21, 2010 | 104 | $1.0M | POWER FOR PORTSMOUTH. |
| Oct 15, 2010 | 103 | $0 | TO FURNISH POWER TO PIKETON PLANT. |
| Sep 30, 2010 | 102 | $400.0K | TO FURNISH POWER TO PIKETON PLANT. |
| Sep 27, 2010 | 101 | $1.7M | TO PURCHASE POWER FOR THE PIKETON PLANT. |
| Aug 31, 2010 | 100 | $500.0K | TO PURCHASE POWER AT PORTSMOUTH, OHIO. |
| Jul 29, 2010 | 99 | $500.0K | TO PURCHASE POWER AT PORTSMOUTH, OHIO. |
| Jun 18, 2010 | 98 | $2.2M | PURCHASE OF POWER FOR PORTSMOUTH, OHIO |
| Jun 7, 2010 | 97 | $400.0K | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH, OHIO |
| May 3, 2010 | 96 | $1.4M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH, OHIO. |
| Mar 31, 2010 | 95 | $700.0K | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH. |
| Feb 25, 2010 | 94 | $1.3M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH. |
| Nov 12, 2009 | 93 | $3.0M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH SITE |
| Sep 30, 2009 | 92 | $1.6M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH SITE |
| Aug 18, 2009 | A091 | $1.4M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH SITE |
| Jun 17, 2009 | A090 | $1.2M | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH SITE |
| May 18, 2009 | A089 | $500.0K | OBLIGATE FUNDS FOR POWER AT PORTSMOUTH SITE |
| Mar 30, 2009 | A088 | $900.0K | |
| Mar 2, 2009 | A087 | $1.2M | |
| Feb 9, 2009 | A086 | $600.0K | |
| Jan 20, 2009 | A085 | $2.0M | |
| Nov 3, 2008 | A084 | $500.0K | |
| Sep 30, 2008 | A083 | $700.0K | |
| Aug 28, 2008 | A082 | $2.0M | |
| Jul 29, 2008 | A081 | $4.0M | |
| Jul 3, 2008 | A080 | $1.3M | |
| Apr 24, 2008 | A079 | $4.0M | |
| Jan 25, 2008 | A078 | $5.8M | |
| Jan 8, 2008 | A077 | $500.0K | |
| Sep 28, 2007 | A076 | $2.1M | |
| Aug 2, 2007 | A075 | $850.0K | |
| Jun 20, 2007 | A074 | $281.3K | |
| Jun 15, 2007 | A073 | $233.4K | |
| Jun 4, 2007 | A072 | $3.0M | |
| May 25, 2007 | A071 | $300.0K | |
| May 3, 2007 | A070 | $300.0K | |
| Apr 24, 2007 | A069 | $100.0K | |
| Apr 9, 2007 | A067 | $200.0K | |
| Apr 9, 2007 | A068 | $400.0K | |
| Mar 16, 2007 | A066 | $310.6K | |
| Feb 28, 2007 | A065 | $2.9M | |
| Feb 26, 2007 | A064 | $300.0K | |
| Feb 12, 2007 | A063 | $300.0K | |
| Jan 22, 2007 | A062 | $2.2M | |
| Jan 16, 2007 | A061 | $300.0K | |
| Jan 4, 2007 | A060 | $300.0K | |
| Dec 6, 2006 | A059 | $200.0K | |
| Nov 22, 2006 | A058 | $200.0K | |
| Nov 9, 2006 | A057 | $500.0K | |
| Oct 23, 2006 | A056 | $200.0K | |
| Sep 21, 2006 | A055 | $200.0K | |
| Sep 11, 2006 | A054 | $200.0K | |
| Aug 24, 2006 | A053 | $200.0K | |
| Aug 9, 2006 | A029 | $200.0K | |
| Aug 1, 2006 | A051 | $200.0K | |
| Aug 1, 2006 | A052 | $300.0K | |
| Jul 14, 2006 | A050 | $300.0K | |
| Jun 22, 2006 | A049 | $200.0K | |
| Jun 9, 2006 | A048 | $200.0K | |
| May 30, 2006 | A047 | $4.8M | |
| May 8, 2006 | A046 | $200.0K | |
| Apr 25, 2006 | A045 | $200.0K | |
| Apr 5, 2006 | A044 | $100.0K | |
| Mar 7, 2006 | A042 | $255.4K | |
| Mar 7, 2006 | A043 | $300.0K | |
| Feb 21, 2006 | A041 | $400.0K | |
| Feb 6, 2006 | A040 | $500.0K | |
| Jan 31, 2006 | A038 | $1.3M | |
| Jan 31, 2006 | A039 | $4.0M | |
| Jan 30, 2006 | A037 | $90.0K | |
| Dec 20, 2005 | A036 | $300.0K | |
| Dec 14, 2005 | A035 | $300.0K | |
| Dec 13, 2005 | A034 | $200.0K | |
| Dec 8, 2005 | A033 | $85.0K | |
| Nov 30, 2005 | A032 | $300.0K | |
| Nov 9, 2005 | A030 | $250.0K | |
| Nov 9, 2005 | A031 | $200.0K | |
| Sep 26, 2005 | A028 | $200.0K | |
| Sep 9, 2005 | A027 | $400.0K | |
| Aug 30, 2005 | A026 | $300.0K | |
| Aug 18, 2005 | A025 | $700.0K | |
| Aug 11, 2005 | A024 | $185.0K | |
| Jul 14, 2005 | A023 | $200.0K | |
| Jul 10, 2005 | A022 | $4.7M | |
| Jun 3, 2005 | A021 | $200.0K | |
| May 2, 2005 | A020 | $400.0K | |
| Apr 12, 2005 | A019 | $600.0K |
Estimated positioning window
Dec 31, 2028 – Jun 30, 2029
25/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 25/100. Available recorded signals: 20 points.
- Contract end 2029-12-31 (1156 days from calculation)
- +5 points
- 1 historical awards in this buyer and category group
- +0 points
- 219 recorded award transactions
- +10 points
- Latest award action: 2026-08-17
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Review the award scope and buyer evidence before making a bid/no-bid decision.