Federal contract award
DEFE0011020
IGF::OT::IGF MANAGEMENT AND OPERATION OF THE STRATEGIC PETROLEUM RESERVE FACILITIES.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | STRATEGIC PETROLEUM RESERVE |
| NAICS | 561210 — Facilities Support Services |
| PSC | R799 — Other Management Support Services |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS AWARD FEE |
| Obligations | $2.0B |
| Current contract value | $3.4B |
| Potential contract value / ceiling | $3.4B |
| Start date | Apr 1, 2014 |
| Current end date | Dec 31, 2025 |
| Potential end date | Dec 31, 2025 |
| Latest award activity | Jan 13, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 183 of 183 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 11, 2026 | 182 | $115.9M | THIS ADMINISTRATIVE MODIFICATION IS ISSUED TO CORRECT MODIFICATION NUMBER 0181 DATED 01/13/2026 WHICH INADVERTENTLY IDENTIFIED THE $115,865,899.73 OF FUND TYPE 00705, 00706, AND 06850 OBLIGATIONS AS APPROPRIATED WITHIN THE STRATEGIC INTEGRATED PROCUR |
| Jan 13, 2026 | 181 | $-180.9M | THE PURPOSE OF THIS MODIFICATION IS TO RECAST THE UNCOSTED OBLIGATION BALANCE FROM THIS CONTRACT TO THE FOLLOW-ON CONTRACT 89243525CCR000073 IN THE AMOUNT OF $180,938,218.03. |
| Nov 18, 2025 | 180 | $1.7M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDING IN THE AMOUNT OF $1,730,641.00. |
| Oct 10, 2025 | 179 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FISCAL YEAR 2026 WORK AUTHORIZATION DIRECTIVES PURSUANT TO H.2 MODIFICATION AUTHORITY AND H.21 WORK AUTHORIZATION, AND CLARIFY FUNDS OBLIGATED IN MODIFICATION 0178, BLOCK 14. |
| Sep 25, 2025 | 178 | $12.6M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS IN THE AMOUNT OF $12,553,024.22 TO COVER ESTIMATED REQUIREMENTS FUNDS TO 99 PERCENT OF THE AOP. IT WILL TAKE FFPO THROUGH ALL OF NOVEMBER LABOR AND 33 PERCENT OF NOVEMBER NON-LABOR, AND TO I |
| Sep 19, 2025 | 177 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE FOR 3 MONTHS THROUGH DECEMBER 31, 2025 AND REVISE SECTION H TO REMOVE CLAUSE H.40 PROVISIONAL PAYMENT OF AWARD FEE, INCORPORATE SUBCONTRACTING PLAN, AND UPDATE WAGE DETE |
| Jul 16, 2025 | 176 | $40.0M | INCREMENTAL FUNDING MODIFICATION |
| Jul 2, 2025 | 175 | $4.8M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE OBLIGATED FUNDS, REVISE COST AND FEE TABLES, UPDATE WORK DIRECTIVES, AND WAGE DETERMINATIONS. |
| Jun 17, 2025 | 174 | $7.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $7,200,000.00 FROM $3,297,955,553.12 TO $3,305,155,553.12. |
| Jun 12, 2025 | 173 | $0 | EXTEND THE CONTRACT PERIOD OF PERFORMANCE FOR 3 MONTHS THROUGH SEPTEMBER 30, 2025. |
| Jun 4, 2025 | 172 | $0 | INCORPORATE FY25 PEMP |
| May 20, 2025 | 170 | $0 | SETTLEMENT OF FFPO'S CERTIFIED CLAIM ON EVMS ISSUES AND AWARD FEE LOSS |
| May 20, 2025 | 171 | $11.0M | INCREMENTAL FUNDING MODIFICATION |
| Apr 30, 2025 | 169 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATES THE M&O CONTRACT TO INCORPORATE FY25 WORK AUTHORIZATION DIRECTIVES REVISIONS 1 |
| Apr 15, 2025 | 168 | $12.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $12,000,00.00 FROM $3,274,955,553.12 TO $3,286,955,553.12. |
| Apr 14, 2025 | 167 | $20 | THIS ADMINISTRATIVE MODIFICATION IS ISSUED TO CORRECT MOD NO. 0164, WHICH INADVERTENTLY IDENTIFIED THE TOTAL FUNDS IN BLOCK 12, ACCOUNTING AND APPROPRIATION DATA, IN THE AMOUNT OF $36,068,335.00 TO REFLECT THE TOTAL OBLIGATED AMOUNT OF $36,068,355.00 |
| Mar 31, 2025 | 166 | $0 | MANAGEMENT AND OPERATIONS OF THE STRATEGIC PETROLEUM RESERVES. THIS MOD PROVIDES A 3 MONTH EXTENSION TO THE POP. |
| Mar 27, 2025 | 165 | $11.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATED FUNDS AND THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATED FUNDS AND TO REMOVE DEAR CLAUSE 970.5526 1 AND DEAR 970.5526 3, PURSUANT TO EXECUTIVE ORDER 14069. |
| Jan 31, 2025 | 164 | $36.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATED FUNDS AND INCORPORATE EXECUTIVE ORDER ON ENDING RADICAL AND WASTEFUL GOVERNMENT DEI PROGRAMS AND PREFERENCING, AND AGENCY WIDE POLICY TO PROMOTE EQUAL OPPORTUNITY, THE FOLLOWING CHANGES ARE INCORPORATE |
| Dec 23, 2024 | 163 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATED $7,500,000.00 IN TOTAL FUNDS FOR THE BRYAN MOUND LE 2 WORK PER BASELINE CHANGE PROPOSAL 01 (BCP-01) FUNDING MEMO DATED DECEMBER 3, 2024, AND TO INCORPORATE FY25 PERFORMANCE EVALUATION AND MEASUREMENT P |
| Nov 25, 2024 | 162 | $36.0M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE SEVERAL CHANGES UNDER SPECIFIC CLAUSES, INCLUDING INCREASES TO THE OBLIGATED FUNDS BY $36,000,000 (TOTALING $3,221,372,551.81) AND THE CONTRACT VALUE BY $67,991,936 (TOTALING $3,305,571,131.44). THES |
| Sep 26, 2024 | 161 | $-89.3K | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE TOTAL FUNDS OF $91,282.90 AND PROVIDE ADDITIONAL $2,000 WHICH WILL DECREASE THE TOTAL FUNDS OBLIGATED CONTRACT $89,282.90 FROM $3,185,461,834.71 TO $3,185,372,551.81. |
| Aug 29, 2024 | 160 | $0 | MANAGEMENT AND OPERATIONS OF THE STRATEGIC PETROLEUM RESERVES. THIS MOD PROVIDES A 6 MONTH EXTENSION TO THE POP. |
| Aug 15, 2024 | 159 | $46.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $46,527,265.80 FROM $3,138,934,568.91 TO $3,185,461,834.51. |
| Jun 26, 2024 | 158 | $14.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $14,500,000.00 FROM $3,124,434,568.91 TO $3,138,934,568.91. |
| Jun 10, 2024 | 157 | $0 | THE PERFORMANCE EVALUATION AND MEASUREMENT PLAN FOR THE PERIOD APRIL 1, 2024, THROUGH SEPTEMBER 30, 2024, IS HEREBY INCORPORATED. |
| Jun 3, 2024 | 156 | $0 | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD INCORPORATES THE SUBJECTIVE FEE MEASURES CLAIMS FOR FY 2020 AND FY 2021. |
| May 30, 2024 | 155 | $13.7M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $13,700,000.00 FROM $3,110,734,568.91 TO $3,124,434,568.91. |
| May 9, 2024 | 154 | $13.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE TOTAL FUNDS OF $13,500,000.00 FROM $3,097,234,568.91 TO $3,110,734,568.91. |
| May 8, 2024 | 153 | $0 | REFERENCE SECTION J, ATTACHMENT G KEY PERSONNEL THE LIST OF KEY PERSONNEL IS UPDATED TO REFLECT THE APPROVED CHANGES. |
| Mar 28, 2024 | 152 | $17.0M | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD PROVIDES INCREMENTAL FUNDING, OT PREMIUM, UPDATES ESTIMATED COSTS/FEES AND WORK AUTHORIZATION DIRECTIVES. |
| Mar 14, 2024 | 151 | $0 | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD PROVIDES A 6-MONTH EXTENSION TO THE ORIGINAL POP. |
| Feb 9, 2024 | 150 | $14.0M | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD PROVIDES INCREMENTAL FUNDING, UPDATES ESTIMATED COSTS/FEES, INCORPORATES OT PREMIUM AND WORK AUTHORIZATION DIRECTIVES. |
| Jan 3, 2024 | 149 | $0 | PURSUANT TO THE AUTHORITY OF H.14 FY24 PEMP, CONTRACT NUMBER DE-FE0011020 IS HEREBY MODIFIED TO INCORPORATE THE FOLLOWING CHANGE: REFERENCE SECTION J, ATTACHMENT J PERFORMANCE EVALUATION AND MEASUREMENT PLAN. THE PERFORMANCE EVALUATION AND MEASURE |
| Dec 19, 2023 | 148 | $23.0M | REFERENCE SECTION B, B.4: PURSUANT TO I.132, DEAR CLAUSE 970.5232-3 OBLIGATION OF FUNDS: THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE THE FOLLOWING FUNDING: THE TOTAL AMOUNT OF $23,000,000.00 IS HEREBY OBLIGATED TO FUND THE M&O CONTRACT TH |
| Oct 27, 2023 | 147 | $20.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE THE FOLLOWING FUNDING THE TOTAL AMOUNT OF $20,000,000.00 IS HEREBY OBLIGATED TO FUND THE M&O CONTRACT THROUGH DECEMBER 2023 AS WELL AS SOME ITEMS INTO JANUARY 2024. FUNDING INCLUDES CASING PURCHA |
| Oct 3, 2023 | 146 | $0 | PURSUANT TO THE AUTHORITY OF H.14 SMALL BUSINESS SUBCONTRACTING PLAN, CONTRACT NUMBER DE-FE0011020 IS HEREBY MODIFIED TO INCORPORATE THE FOLLOWING CHANGE: REFERENCE SECTION J, ATTACHMENT D SMALL BUSINESS SUBCONTRACTING PLAN: THE FY24 SUBCONTRACTIN |
| Sep 21, 2023 | 145 | $1.0M | REFERENCE SECTION B, B.4: PURSUANT TO I.132, DEAR CLAUSE 970.5232-3 OBLIGATION OF FUNDS: THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE THE FOLLOWING FUNDING: THE TOTAL AMOUNT OF $1,028,228.00 IS HEREBY OBLIGATED TO FUND THE FY 2023 M&O ANNU |
| Sep 11, 2023 | 144 | $-45.0M | THIS ADMINISTRATIVE MODIFICATION IS ISSUED TO CORRECT MODIFICATION NUMBER 0126 DATED 05/27/2022 WHICH INADVERTENTLY IDENTIFIED THE $45,000,000.00 OF FUND TYPE 00706 OBLIGATIONS AS APPROPRIATED WITHIN THE STRATEGIC INTEGRATED PROCUREMENT ENTERPRISE SY |
| Aug 18, 2023 | 143 | $36.6M | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND THE MANAGEMENT & OPERATION CONTRACT AWARD IN THE TOTAL AMOUNT OF $36,613,879.20. |
| Aug 17, 2023 | 141 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT ERROR IN MODIFICATION NO. 0140, UPDATE SECTION J ATTACHMENT D SMALL BUSINESS SUBCONTRACTING PLAN, UPDATE ATTACHMENT E WAGE DETERMINATIONS, AND UPDATE SECTION G KEY PERSONNEL. |
| Jun 2, 2023 | 142 | $0 | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD INCORPORATES THE FEE REDUCTION CLAIM SETTLEMENT. |
| May 15, 2023 | 140 | $36.0M | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD PROVIDES INCREMENTAL FUNDING, UPDATES ESTIMATED COSTS/FEES, INCORPORATES OT PREMIUM AND WORK AUTHORIZATION DIRECTIVES. |
| Mar 11, 2023 | 139 | $28.0M | MANAGEMENT & OPERATION OF THE STRATEGIC PETROLEUM RESERVE. THIS MOD PROVIDES INCREMENTAL FUNDING, UPDATES ESTIMATED COSTS/FEES, INCORPORATES OT PREMIUM AND WORK AUTHORIZATION DIRECTIVES. |
| Feb 8, 2023 | 138 | $0 | PURSUANT TO THE AUTHORITY OF FAR 43.103, CONTACT NUMBER DE-FE0011020 IS HEREBY MODIFIED TO REFLECT THE FOLLOWING CHANGES. REFERENCE SECTION G. A. REFERENCE SECTION G, G.1 TECHNICAL AND ADMINISTRATIVE CORRESPONDENCE MATTERS: UPDATE POINT OF CONT |
| Jan 24, 2023 | 137 | $15.1M | REFERENCE SECTION B, B.4: PURSUANT TO I.132, DEAR CLAUSE 970.5232-3 OBLIGATION OF FUNDS: THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE THE FOLLOWING FUNDING: AS RESULT OF THIS MODIFICATION, THE TOTAL AMOUNT OF $15,118,600.00 IS HEREBY OBLIGATED |
| Jan 18, 2023 | 136 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J, ATTACHMENT J TO INCORPORATE FY23 PEMP MEASURES INTO THE CONTRACT. REFERENCE SECTION J, ATTACHMENT J PERFORMANCE EVALUATION AND MEASUREMENT PLAN PEMP, THE PERFORMANCE EVALUATION AND MEASUREM |
| Oct 27, 2022 | 135 | $28.5M | INCREMENTAL FUNDING |
| Sep 29, 2022 | 134 | $79.9K | INCREMENTAL FUNDING |
| Sep 20, 2022 | 133 | $10.5M | INCREMENTAL FUNDING |
| Aug 19, 2022 | 132 | $0 | UPDATE SECURITY AND PAT WADS |
| Aug 10, 2022 | 131 | $24.1M | INCREMENTAL FUNDING |
| Jun 29, 2022 | 129 | $0 | UPDATE SECTION B TO INCORPORATE FINAL AOPS AND FY21 ACTUAL COSTS. |
| Jun 29, 2022 | 130 | $22.0M | INCREMENTAL FUNDING. |
| Jun 14, 2022 | 128 | $0 | UPDATE SECTION I TO INCORPORATE DOE POLICY FLASH 2022-5 CLASS DEVIATION TO IMPLEMENT THE OIG NEW AUDIT STRATEGY FOR M&O CONTRACTS. |
| Jun 10, 2022 | 127 | $20.8M | INCREMENTAL FUNDING. |
| May 27, 2022 | 126 | $45.0M | INCREMENTAL FUNDING. |
| Apr 27, 2022 | 125 | $19.3M | INCREMENTAL FUNDING. |
| Apr 26, 2022 | 124 | $0 | UPDATE SECTION J. |
| Apr 13, 2022 | 123 | $14.0M | OBLIGATE FUNDING |
| Mar 30, 2022 | 122 | $-800.0K | DEOBLIGATE FUNDING |
| Mar 8, 2022 | 121 | $7.6M | INCREMENTAL FUNDING |
| Jan 5, 2022 | 120 | $0 | INCORPORATE THE FY22 HURRICANE RECOVERY SUPPLEMENTAL WAD |
| Dec 22, 2021 | 119 | $30.0M | EO14042 INCREMENTAL FUNDING. |
| Dec 9, 2021 | 118 | $24.7M | EO14042 INCREMENTAL FUNDING |
| Nov 12, 2021 | 117 | $0 | EO14042 UPDATE SECTION I AND SECTION J ATTACHMENT D SMALL BUSINESS SUBCONTRACTING PLAN |
| Oct 22, 2021 | 115 | $0 | UPDATE SECTION J ATTACHMENT B FY22 WORK AUTHORIZATION DIRECTIVES |
| Oct 22, 2021 | 116 | $22.0M | ADD INCREMENTAL FUNDING AND UPDATE SECTION J ATTACHMENT A ADVANCED UNDERSTANDING |
| Oct 14, 2021 | 113 | $0 | INCORPORATE FY22 PERFORMANCE EVALUATION AND MEASUREMENT PLAN (PEMP) |
| Oct 14, 2021 | 114 | $0 | EO14042 UPDATE SECTION J, ATT F, DIRECTIVES, TO INCLUDE DOE O 350.5 COVID SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS |
| Sep 21, 2021 | 112 | $6.4M | UPDATE SECTION B (AOP FY22-24 & FEE), SECTION H, SECTION I, SECTION J ATT B AND ATT F, AND INCLUDE PAT WAD REV 1, TSM WAD REVISION 2 AND MAINTENANCE WAD REVISION 2. |
| Jul 21, 2021 | 111 | $32.8M | INCREMENTAL FUNDING. |
| Apr 30, 2021 | 110 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J, ATTACHMENT E SERVICE CONTRACT LABOR STANDARD WAGE DETERMINATIONS. |
| Apr 8, 2021 | 109 | $37.6M | ADD INCREMENTAL FUNDING. |
| Mar 18, 2021 | 108 | $11.0M | UPDATE SECTION B FY20 ACTUALS AND ADD INCREMENTAL FUNDING. |
| Mar 4, 2021 | 107 | $0 | UPDATE SECTION B. INCORPORATE WADS, SMALL BUSINESS SUBCONTRACTING PLAN AND PEMP |
| Feb 25, 2021 | 106 | $10.0M | ADD INCREMENTAL FUNDING |
| Jan 22, 2021 | 105 | $18.5M | UPDATE CONTRACT VALUE, UPDATE AWARD FEE, ADD INCREMENTAL FUNDING |
| Nov 19, 2020 | 104 | $29.1M | INCREMENTAL FUNDING |
| Sep 24, 2020 | 103 | $0 | INCORPORATE WAD REVISION DUE TO BCR. |
| Sep 17, 2020 | 102 | $13.3M | INCREMENTAL FUNDING |
| Aug 7, 2020 | 101 | $29.0M | INCREMENTAL FUNDING |
| Jun 9, 2020 | 100 | $0 | IMPLEMENTATION OF SECTION 3610 OF THE CARES ACT |
| May 23, 2020 | 99 | $886.0K | SUPPLEMENTAL FUNDING |
| May 7, 2020 | 98 | $1.8M | SUPPLEMENTAL FUNDING |
| Apr 21, 2020 | 97 | $44.4M | SUPPLEMENTAL FUNDING |
| Apr 17, 2020 | 96 | $0 | UPDATE SECTIONS B&G. INCORPORATE WAD REVISIONS AND WAGE DETERMINATIONS. |
| Mar 26, 2020 | 95 | $606.0K | INCREMENTAL FUNDING FOR SPR FILL OPERATIONS |
| Mar 16, 2020 | 94 | $12.0M | INCREMENTAL FUNDING. |
| Feb 7, 2020 | 93 | $48.7K | INCREMENTAL FUNDING AND INCORPORATE LE2 WAD REVISION 1. |
| Jan 28, 2020 | 92 | $27.1M | INCREMENTAL FUNDING |
| Dec 19, 2019 | 91 | $-264.0K | DECREASE FUNDING |
| Dec 13, 2019 | 90 | $11.1M | ADD FUNDING |
| Nov 5, 2019 | 89 | $20.0M | ADD FUNDING |
| Oct 31, 2019 | 88 | $0 | UPDATE CONTRACT VALUE, UPDATE AWARD FEE, INCORPORATE WORK AUTHORIZATION DIRECTIVES&UPDATE DIRECTIVES |
| Sep 20, 2019 | 87 | $12.9M | INCREMENTAL FUNDING |
| Jul 19, 2019 | 86 | $20.3M | INCREMENTAL FUNDING |
| Jun 26, 2019 | 85 | $0 | IGF::OT::IGF UPDATE SCA WAGE DETERMINATIONS |
| Apr 24, 2019 | 84 | $58.0M | IGF::OT::IGF FY19 INCREMENTAL FUNDING |
| Apr 15, 2019 | 83 | $74.0K | IGF::OT::IGF FY19 FUNDING FOR CELL PHONE CONTRACT |
| Mar 20, 2019 | 82 | $0 | IGF::OT::IGF CORRECTION TO MODIFICATION 0081 |
| Mar 19, 2019 | 81 | $4.1M | IGF::OT::IGF INCREMENTAL FUNDING AND INCORPORATE WORK AUTHORIZATIONS DIRECTIVE (WAD) REVISIONS. UPDATED FY18 ACTUAL COSTS AND AWARD FEE EARNED. |
| Jan 29, 2019 | 80 | $35.4M | IGF::OT::IGF INCREMENTAL FUNDING |
| Jan 7, 2019 | 79 | $12.4M | IGF::OT::IGF INCREMENTAL FUNDING |
| Dec 19, 2018 | 78 | $0 | IGF::OT::IGF INCORPORATE FY19 WORK AUTHORIZATION DIRECTIVES (WAD) |
| Nov 27, 2018 | 77 | $15.8M | IGF::OT::IGF INCREMENTAL FUNDING |
| Nov 21, 2018 | 76 | $0 | IGF::OT::IGF UPDATE FY17 ACTUAL COSTS IN SECTION B. |
| Oct 23, 2018 | 75 | $12.4M | IGF::OT::IGF INCREMENTAL FUNDING |
| Sep 27, 2018 | 74 | $9.6M | IGF::OT::IGF INCREMENTAL FUNDING |
| Aug 30, 2018 | 73 | $0 | IGF::OT::IGF CORRECT LANGUAGE IN MODIFICATION 0072 |
| Aug 28, 2018 | 72 | $32.0M | IGF::OT::IGF UPDATE CORRECTED CONTRACT VALUE AND AWARD FEE. PROVIDE INCREMENTAL FUNDING. |
| Aug 15, 2018 | 71 | $0 | IGF::OT::IGF EXERCISE OPTION |
| Aug 6, 2018 | 70 | $0 | IGF::OT::IGF UPDATE FY18 WORK AUTHORIZATION DIRECTIVES |
| Jul 16, 2018 | 69 | $12.5M | IGF::OT::IGF OBLIGATION OF FUNDS |
| Jun 28, 2018 | 68 | $7.5M | IGF::OT::IGF OBLIGATION OF FUNDS |
| Jun 15, 2018 | 67 | $5.4M | IGF::OT::IGF OBLIGATION OF FUNDS |
| May 24, 2018 | 66 | $13.2M | IGF::OT::IGF OBLIGATION OF FUNDS |
| May 17, 2018 | 65 | $13.7M | IGF::OT::IGF INCLUDE COST FOR LE 2 IN FY19. |
| Apr 11, 2018 | 64 | $0 | IGF::OT::IGF UPDATE CONTRACT CLAUSES, DIRECTIVES, WAGE RATES, AND KEY PERSONNEL. |
| Feb 23, 2018 | 63 | $20.0M | PROVIDE INCREMENTAL FUNDING. |
| Feb 2, 2018 | 62 | $9.0M | PROVIDE INCREMENTAL FUNDING. |
| Jan 12, 2018 | 61 | $12.8M | PROVIDE INCREMENTAL FUNDING. |
| Dec 28, 2017 | 60 | $6.3M | PROVIDE INCREMENTAL FUNDING. |
| Dec 7, 2017 | 59 | $2.0M | PROVIDE INCREMENTAL FUNDING THROUGH 3/31/19. |
| Nov 2, 2017 | 58 | $31.3M | PROVIDE INCREMENTAL FUNDING, INCORPORATE A CLAUSE REVISION IN SECTION H, INCORPORATE FY18 SB PLAN AND PEMP |
| Sep 28, 2017 | 57 | $6.2M | IGF::OT::IGF INCREMENTAL FUNDING PRE-FINANCING, UPDATES TO SECTION G - CORS, SECTION H - CORPORATE INFO, AND SECTION J, ATT B - FY18 WADS |
| Sep 22, 2017 | 56 | $0 | IGF::OT::IGF INCORPORATE FY18 FEE BASE AND AVAILABLE FEE; TO REFLECT FY18 AOP FOR FACILITIES AND LE 2 AND UPDATE CHARTS IN SECTION B. B.2 AND B.6 TO REFLECT ADJUSTMENTS |
| Sep 13, 2017 | 55 | $34.3M | IGF::OT::IGF ADJUST FY2018 ESTIMATED COSTS TO INCORPORATE FY 2018 INTERIM AOP AND LE2 COSTS AND PROVIDE INCREMENTAL FUNDING FOR ESTIMATED REQUIREMENTS THROUGH NOVEMBER 2017. |
| Jul 25, 2017 | 54 | $14.9M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED REQUIREMENTS THROUGH AUGUST 2017; UPDATE LISTS OF DIRECTIVES AND KEY PERSONNEL. |
| Jul 6, 2017 | 53 | $-6.7M | IGF::OT::IGF DEOBLIGATE A PORTION OF LE2 INCREMENTAL FUNDING AND PROVIDE INCREMENTAL FUNDING FOR ESTIMATED FACILITIES OPERATIONS REQUIREMENTS THROUGH JULY 2017, RESULTING A DECREASE IN OBLIGATIONS OF $6,709,077. CONTRACT VALUE REMAINS THE SAME. |
| Jun 9, 2017 | 52 | $15.0M | IGF::OT::IGF REVISE FY 2017 ESTIMATED COSTS TO REFLECT WAD REVISIONS AND PROVIDE INCREMENTAL FUNDING FOR ESTIMATED OPERATIONS REQUIREMENTS THROUGH JULY 2017. THE CONTRACT VALUE IS ALSO REVISED TO REFLECT THE CHANGES. |
| Apr 27, 2017 | 51 | $189.1M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR ESTIMATED OPERATIONS REQUIREMENTS THROUGH JUNE 2017 AND INCREMENTAL FUNDING FOR LE 2. |
| Mar 21, 2017 | 50 | $0 | IGF::OT::IGF UPDATE SERVICE CONTRACT LABOR STANDARDS AND DOE/SPRPMO DIRECTIVES |
| Feb 14, 2017 | 49 | $0 | IGF::OT::IGF REVISE CONTRACT VALUE TO REFLECT ACTUAL FY15 COST AND FEE EARNED; UPDATE FAR AND DEAR CLAUSES AND UPDATE LIST OF APPLICABLE DIRECTIVES. |
| Jan 11, 2017 | 48 | $61.0M | IGF::OT::IGF TO PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATION REQUIREMENTS AND INCORPORATE THE FY 17 REVISED SB PLAN AND FY 17 PEMP. |
| Nov 16, 2016 | 47 | $25.0M | IGF::OT::IGF TO PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATION REQUIREMENTS AND INCORPORATE THE FY 17 AUTHORIZED OT PREMIUM. |
| Oct 7, 2016 | 46 | $0 | IGF::OT::IGF UPDATE CONTRACT VALUE TO INCORPORATE FY 2016 CHANGES, FY 2017 AOP AND NEGOTIATED FEE, UPDATE LIST OF CORS, APPLICABLE DIRECTIVES AND KEY PERSONNEL, AND INCORPORATE FY 2017 SB PLAN. |
| Sep 26, 2016 | 45 | $3.4M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR FY 2107 PRE-FINANCING AND MISCELLANEOUS TASKS. |
| Jul 25, 2016 | 44 | $33.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS THROUGH FISCAL YEAR 2016. |
| Jul 13, 2016 | 43 | $0 | IGF::OT::IGF ADD/UPDATE CLAUSES AND DOE/SPRPMO DIRECTIVES. |
| May 6, 2016 | 42 | $30.1M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS, INCLUDING NEHHOR AND CELL PHONE FUNDING, AND TO INCORPORATE PEMP REV.1. |
| Mar 31, 2016 | 41 | $32.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Mar 29, 2016 | 40 | $0 | IGF::OT::IGF INCORPORATE UPDATED SERVICE CONTRACT LABOR STANDARDS WAGE DETERMINATIONS. |
| Mar 1, 2016 | 39 | $13.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Feb 12, 2016 | 38 | $0 | IGF::OT::IGF INCORPORATE REVISED CLAUSE AND UPDATE THE LIST OF APPLICABLE DIRECTIVES. |
| Jan 29, 2016 | 37 | $15.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Jan 26, 2016 | 36 | $0 | IGF::OT::IGF REVISE CONTRACT VALUE TO INCORPORATE CHANGES TO FYS 2014 AND 2015 COSTS/FEES, UPDATE FY2016 COSTS TO INCORPORATE CHANGES AND UPDATE LIST OF CORPORATE OFFICIALS. |
| Jan 7, 2016 | 35 | $12.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Dec 3, 2015 | 34 | $2.5M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS, UPDATE CONTRACT CLAUSES, DIRECTIVES, INCORPORATE THE FY 2016 SB PLAN AND PEMP. |
| Oct 14, 2015 | 33 | $25.5M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Sep 30, 2015 | 32 | $0 | IGF::OT::IGF UPDATE/INCORPORATE SECTION H CLAUSES. |
| Sep 21, 2015 | 31 | $1.7M | IGF::OT::IGF INCREMENTAL FUNDING, INCORPORATE FY 2016 WADS, AND FY 2016 AUTHORIZED OT PREMIUM. |
| Sep 10, 2015 | 30 | $3.0M | IGF::OT::IGF REVISE CONTRACT VALUE TO REFLECT APPROVED FY15 AOP CHANGES, INCORPORATE FY 16 AOP (ESTIMATED COSTS) AND NEGOTIATED AVAILABLE AWARD FEE, UPDATE FAR, DEAR, UPDATE LIST OF APPLICABLE DIRECTIVES, AND INCORPORATE REVISED PEMP. |
| Jul 28, 2015 | 29 | $20.0M | IGF::OT::IGF INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| May 11, 2015 | 28 | $20.0M | IGF::OT::IGF INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Apr 23, 2015 | 27 | $25.0M | IGF::OT::IGF INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Mar 23, 2015 | 26 | $20.0M | IGF::OT::IGF INCREMENTAL FUNDING TO COVER ESTIMATED RESERVATIONS. |
| Mar 20, 2015 | 25 | $0 | IGF::OT::IGF INCORPORATE UPDATED FAR CLAUSES, SCA WDS, AND DIRECTIVES. |
| Feb 27, 2015 | 24 | $2.4M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR THE MAJOR MAINTENANCE PROGRAM. |
| Feb 25, 2015 | 23 | $13.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING AND UPDATE CONTRACTOR POC. |
| Feb 4, 2015 | 22 | $12.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING. |
| Jan 30, 2015 | 21 | $0 | IGF::OT::IGF REVISE CONTRACT VALUE; UPDATE CLAUSES AND DIRECTIVES, AND INCORPORATE ADMIN CHANGES. |
| Jan 13, 2015 | 20 | $14.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING |
| Nov 17, 2014 | 19 | $0 | IGF::OT::IGF INCORPORATE UPDATES TO THE COR LIST, THE DIRECTIVES, AND INCORPORATE THE FY15 PEMP AND SB PLAN. |
| Oct 16, 2014 | 18 | $26.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR ESTIMATED RESERVATION REQUIREMENTS. |
| Sep 25, 2014 | 16 | $1.3M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR RESERVATION REQUIREMENTS THROUGH,UPDATE FY15 COST/FEE TO REFLECT INITIAL AOP AND NEGOTIATED FEE, INCORPORATE FY15 WADS AND AUTHORIZED OVERTIME PREMIUM. |
| Sep 25, 2014 | 17 | $737.0K | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR ESTIMATED RESERVATION REQUIREMENTS. |
| Sep 9, 2014 | 14 | $0 | IGF::OT::IGF INCORPORATE NERRPPR WAD, UPDATE CLAUSES,AND UPDATE DIRECTIVES. |
| Sep 9, 2014 | 15 | $12.5M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR RESERVATION REQUIREMENTS THROUGH NOVEMBER 2014. |
| Aug 26, 2014 | 13 | $1.8M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR NRRPPR AND PAT. |
| Aug 13, 2014 | 12 | $15.5M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING |
| Aug 12, 2014 | 11 | $0 | IGF::OT::IGF INCORPORATE AN ADVANCE UNDERSTANDING,UPDATE DIRECTIVES LIST AND CONTRACT CLAUSES. |
| Jul 17, 2014 | 10 | $10.0M | IGF::OT::IGF PROVIDE INCREMENTAL FUNDING FOR ESTIMATED RESERVATIONS. |
| Jun 24, 2014 | 9 | $0 | IGF::OT::IGF UPDATE CONTRACT CLAUSES, DIRECTIVES, AND KEY PERSONNEL. |
| Jun 5, 2014 | 8 | $11.5M | IGF::OT::IGF INCREMENTAL FUNDING TO COVER ESTIMATED REQUIREMENTS THROUGH JULY 2014. |
| Apr 29, 2014 | 7 | $-2.5M | IGF::OT::IGF DEOBLIGATE FUNDS TO BE REOBLIGATED PRIOR M&O CONTRACT. |
| Apr 24, 2014 | 5 | $19.5M | IGF::OT::IGF INCREMENTAL FUNDING AND INCORPORATE FY14 PEMP BY REFERENCE. |
| Apr 24, 2014 | 6 | $103.5M | IGF::OT::IGF RECAST UNCOSTED OBLIGATION BALANCE FROM PREVIOUS M&O CONTRACT TO THIS CONTRACT. |
| Apr 10, 2014 | 4 | $10.8M | IGF::OT::IGF INCREMENTAL FUNDING |
| Apr 9, 2014 | 3 | $2.0M | IGF::OT::IGF MANAGEMENT AND OPERATION OF THE STRATEGIC PETROLEUM RESERVE FACILITIES. INCORPORATE COR AND CONTRACTOR CONTACT INFORMATION,INCORPORATE TWO CLAUSES IN SECTION H AND PROVIDE INCREMENTAL FUNDING. |
| Mar 28, 2014 | 2 | $0 | IGF::OT::IGF MANAGEMENT AND OPERATION OF THE STRATEGIC PETROLEUM RESERVE FACILITIES. PROVIDE OT PREMIUM AUTHORIZATION FOR FY14 AND UPDATE SECTION J, ATTACHMENTS B,C,D,E,H. |
| Mar 24, 2014 | 1 | $0 | IGF::OT::IGF MANAGEMENT AND OPERATION OF THE STRATEGIC PETROLEUM RESERVE FACILITIES. UPDATE PERIOD OF PERFORMANCE, CLAUSES, DIRECTIVES, AND ESTIMATED COSTS/FEES. |
| Sep 18, 2013 | 0 | $1.5M | IGF::OT::IGF MANAGEMENT AND OPERATION OF THE STRATEGIC PETROLEUM RESERVE FACILITIES. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.