Federal contract award

DENA0001919

ELECTRIC POWER SUPPLY CONTRACT FOR THE PURCHASE AND DELIVERY OF ELECTRIC POWER TO THE NEVADA NATIONAL SECURITY SITE FOR NEVADA SITE OFFICE - NSO.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeNNSA NON-MO CNTRCTNG OPS DIV
NAICS221122 — Electric Power Distribution
PSCS112 — Electric Services
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$13.1M
Current contract value$90.9M
Potential contract value / ceiling$90.9M
Start dateSep 30, 2012
Current end dateMar 31, 2026
Potential end dateMay 1, 2026
Latest award activityFeb 11, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 11, 202639$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE END DATE FROM JANUARY 31, 2026 TO MARCH 31, 2026 (60 DAYS).
Feb 11, 202640$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE END DATE FROM JANUARY 31, 2026 TO MARCH 31, 2026 (60 DAYS).
Jan 29, 202638$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE END DATE FROM JANUARY 31, 2026 TO MARCH 31, 2026 (60 DAYS).
Oct 14, 202537$0THE PURPOSE OF THIS MODIFICATION IS TO DE-SCOPE THE SCADA SYSTEM FROM THE CONTRACT.
Apr 2, 202536$0THE PURPOSE OF THIS MODIFICATION IS TO DE-SCOPE THE SCADA SYSTEM FROM THE CONTRACT.
Mar 5, 202535$0THE PURPOSE OF THIS MODIFICATION IS TO DE-SCOPE THE SCADA SYSTEM FROM THE CONTRACT.
Nov 25, 202434$0THE PURPOSE OF THIS MODIFICATION IS TO DE-SCOPE THE SCADA SYSTEM FROM THE CONTRACT.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.