Federal contract award

DESC0004645

DECONTAMINATION AND DECOMISSIONING OF THE EAST TENNESSEE TECHNOLOGY PARK (ETTP)AT OAK RIDGE, TN.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Energy
OfficeEM-OAK RIDGE
NAICS562910 — Remediation Services
PSCF999 — Other Environmental Services, Studies, and Analytical Support
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeCOST PLUS AWARD FEE
Obligations$3.9B
Current contract value$4.2B
Potential contract value / ceiling$4.2B
Start dateApr 29, 2011
Current end dateJul 31, 2021
Potential end dateJul 31, 2022
Latest award activityDec 29, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 200 of 433 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 29, 2025484$6.9MTHE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $6,892,715.20
Aug 25, 2023483$-1.1MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 23, 2023423$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 23, 2023482$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 18, 2022481$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 30, 2022480$-41.6MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 2, 2022479$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 18, 2022478$1.8MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 17, 2022473$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 28, 2022421$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 28, 2022476$35.1MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 15, 2022474$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 25, 2022472$40.7MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 24, 2022439$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 28, 2022469$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 31, 2022465$-175.6KDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 17, 2021463$79.0MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 22, 2021460$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 18, 2021457$-22.4MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 28, 2021455$67.0MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 30, 2021452$187.7KDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 28, 2021450$12.4MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 31, 2021446$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 23, 2021442$117.3MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 30, 2021441$120.0KDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 24, 2021440$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 29, 2021437$64.1MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 16, 2021429$60.3MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 11, 2021424$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 26, 2021425$39.3MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 26, 2021422$51.8MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 14, 2021389$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 14, 2021391$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 14, 2021396$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 14, 2021416$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 14, 2021417$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 13, 2021401$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 12, 2021404$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 12, 2021406$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 18, 2020420$0DECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 10, 2020419$13.4MDECONTAMINATION & DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 20, 2020418$425.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 23, 2020415$71.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 1, 2020413$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 30, 2020414$3.4MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 3, 2020410$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 28, 2020411$145.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 12, 2020308$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 12, 2020408$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 31, 2020407$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 15, 2020405$130.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 30, 2020402$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 29, 2020403$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 9, 2020398$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 29, 2020400$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 10, 2020395$123.5MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 9, 2020394$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 26, 2020393$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 9, 2020392$33.4MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 4, 2020388$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 4, 2020390$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 14, 2020386$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 13, 2020387$34.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 16, 2020384$107.3MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 17, 2019383$32.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 16, 2019382$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 25, 2019381$-300.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 28, 2019379$16.5MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 22, 2019377$7.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 11, 2019376$49.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 27, 2019373$94.5KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 23, 2019371$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 20, 2019372$2.3MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 10, 2019370$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 3, 2019369$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 23, 2019368$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 19, 2019366$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 16, 2019359$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 16, 2019362$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 15, 2019367$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 25, 2019365$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 18, 2019364$69.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 21, 2019361$1.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 23, 2019358$1.4MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 17, 2019357$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 8, 2019356$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 17, 2019353$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 17, 2019354$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 16, 2019355$91.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 27, 2019349$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 27, 2019351$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 22, 2019352$4.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 21, 2019350$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 22, 2019348$1.0MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 21, 2019347$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 13, 2019346$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 7, 2019345$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 29, 2019342$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 25, 2019340$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 24, 2019344$102.8MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 20, 2018343$35.1MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 19, 2018338$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 21, 2018341$34.3MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 25, 2018336$41.5MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 28, 2018335$6.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 19, 2018333$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 14, 2018334$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 29, 2018332$16.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 23, 2018330$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 23, 2018331$84.5MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 20, 2018329$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 31, 2018328$2.3MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 27, 2018327$37.8MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 25, 2018326$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 19, 2018325$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 16, 2018323$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 16, 2018324$29.0MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 12, 2018322$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 29, 2018320$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 26, 2018321$17.3MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 1, 2018316$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 30, 2018317$25.9MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 8, 2018315$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 8, 2018318$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 26, 2018314$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 24, 2018313$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 17, 2018312$39.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 16, 2018311$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 6, 2018310$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 23, 2018309$2.2MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 22, 2018307$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 21, 2018304$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 12, 2018299$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 12, 2018302$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 9, 2018306$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 8, 2018305$38.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 28, 2018303$20.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 8, 2018301$40.0MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 7, 2018300$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 26, 2018298$735.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 23, 2018295$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 12, 2018297$18.8MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 11, 2018296$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 8, 2018294$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 27, 2017293$16.4MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 20, 2017292$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 12, 2017291$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 1, 2017290$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 30, 2017289$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 21, 2017288$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 8, 2017287$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Nov 1, 2017286$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 30, 2017285$1.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Oct 13, 2017284$49.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 29, 2017283$3.1MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 26, 2017282$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 22, 2017280$3.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 22, 2017281$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 19, 2017279$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Sep 11, 2017278$916.8KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 30, 2017277$72.7MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 23, 2017276$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 22, 2017275$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Aug 10, 2017274$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 31, 2017273$28.1MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 20, 2017272$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 13, 2017271$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jul 7, 2017270$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 21, 2017269$33.0MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 15, 2017268$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jun 12, 2017267$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 31, 2017266$10.6MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 26, 2017265$40.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 19, 2017262$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 19, 2017263$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 18, 2017264$20.1MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
May 4, 2017261$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 28, 2017260$4.0MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 24, 2017259$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 13, 2017257$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Apr 10, 2017258$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 31, 2017256$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 30, 2017255$700.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 10, 2017254$35.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Mar 1, 2017253$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 27, 2017252$20.0KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 16, 2017251$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 10, 2017250$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 6, 2017249$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 1, 2017247$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Feb 1, 2017248$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 30, 2017246$6.5KDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 24, 2017245$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Jan 11, 2017244$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 28, 2016243$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 22, 2016242$124.5MDECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 21, 2016241$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 20, 2016240$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 15, 2016239$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.
Dec 9, 2016237$0DECONTAMINATION&DECOMMISSIONING PROJECT FOR THE EAST TENNESSEE TECHNOLOGY PARK.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.