Federal contract award

DTFASA17C00667

IGF::OT::IGF REPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office697DCK REGIONAL ACQUISITIONS SVCS
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2NB — REPAIR OR ALTERATION OF HEATING AND COOLING PLANTS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$353.1K
Current contract value$353.1K
Potential contract value / ceiling$359.1K
Start dateAug 29, 2017
Current end dateAug 9, 2019
Potential end dateAug 9, 2019
Latest award activityAug 22, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Aug 22, 2026P00004$-1REPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.
Aug 14, 2019P00003$-6.0KREPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.
Jul 10, 2019P00002$1.4KREPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.
Sep 19, 2018P00001$33.9KIGF::OT::IGF REPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.
Aug 29, 20170$323.8KIGF::OT::IGF REPLACE THE HVAC SYSTEM INCLUDING DUCT WORK, CONTROLS, TAB, AND INSTALL NEW ELECTRICAL SYSTEM AT FAA QYS ARSR (ROGERS, TX) RADAR TOWER EQUIPMENT BUILDING. THE DESIGN&BUILD CONTRACTOR MUST SITE SURVEY AND DESIGN A NEW SYSTEM THAT MEETS THE REQUIREMENTS IN THE SOW/SPECIFICATIONS PROVIDED BY THE FAA. REPLACE NEW THE ENTIRETY OF THE HVAC SYSTEM INCLUDING DUCT WORK AND CONTROLS, TAB AND INSTALL NEW ELECTRICAL SYSTEM.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.