Federal contract award
FA252124C0020
THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA2521 45 CONS PK |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2BZ — REPAIR OR ALTERATION OF OTHER AIRFIELD STRUCTURES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.5M |
| Current contract value | $1.5M |
| Potential contract value / ceiling | $1.5M |
| Start date | Jul 3, 2024 |
| Current end date | Mar 31, 2026 |
| Potential end date | Mar 31, 2026 |
| Latest award activity | Mar 16, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 16, 2026 | P00013 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Mar 2, 2026 | P00012 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Feb 9, 2026 | P00011 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Jan 12, 2026 | P00010 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Dec 19, 2025 | P00009 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Dec 15, 2025 | P00008 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Sep 16, 2025 | P00007 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Aug 15, 2025 | P00006 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Jul 28, 2025 | P00005 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Apr 4, 2025 | P00004 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
| Dec 18, 2024 | P00003 | $0 | THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF PROVIDING THE LABOR, EQUIPMENT, AND MATERIALS TO REPLACE THE EXISTING OVERHEAD AIRCRAFT PARKING LIGHTS FOR RAMP 750. SEE SPECIFICATIONS AND DRAWINGS FOR REQUIREMENT. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.