Federal contract award

FA282325F0161

PROJECT 23JG12, PROJECT SEEKER TEST AND EVALUATION FACILITY, GROUND PLANE (ASPHALT) REPAIR C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeFA2823 AFTC PZIO
NAICS236220 — Commercial and Institutional Building Construction
PSCZ1BZ — MAINTENANCE OF OTHER AIRFIELD STRUCTURES
Parent award / vehicleFA282322D0009
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$1.4M
Current contract value$1.4M
Potential contract value / ceiling$1.4M
Start dateJul 1, 2025
Current end dateJul 24, 2026
Potential end dateJul 24, 2026
Latest award activityJun 2, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 2, 2026P00004$202.9KPROJECT 23JG12 RPR, PROJECT SEEKER TEST AND EVALUATION FACILITY (STEF), GROUND PLANE (ASPHALT) REPAIR - TS C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.
May 21, 2026P00003$0PROJECT 23JG12 RPR, PROJECT SEEKER TEST AND EVALUATION FACILITY (STEF), GROUND PLANE (ASPHALT) REPAIR - TS C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.
May 5, 2026P00002$165.4KPROJECT 23JG12 RPR, PROJECT SEEKER TEST AND EVALUATION FACILITY (STEF), GROUND PLANE (ASPHALT) REPAIR - TS C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.
Aug 11, 2025P00001$0PROJECT 23JG12 RPR, PROJECT SEEKER TEST AND EVALUATION FACILITY (STEF), GROUND PLANE (ASPHALT) REPAIR - TS C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.
Jul 2, 20250$1.0MPROJECT 23JG12, PROJECT SEEKER TEST AND EVALUATION FACILITY, GROUND PLANE (ASPHALT) REPAIR C-52A, REPAIR OF THE RAIL SYSTEM INFRASTRUCTURE AT AREA C-52.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.