Federal contract award
FA301624F0459
THE SCOPE OF DESIGN PROJECT IS TO COMPLETE100% DESIGN FOR CONSTRUCTION PACKAGE TO INSTALL A SECTION OF THE CHILLED WATER LOOP (CWL) JOINING THE EAST/WEST-SIDE RANDOLPH SECTIONS INTO ONE CWL. THE SECTION WILL BE FROM BLDG 496 CW PLANT TO BLDG 100.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA3016 502 CONS CL |
| NAICS | 541330 — Engineering Services |
| PSC | C211 — Architect - Engineer Services (including landscaping, interior layout, and designing) |
| Parent award / vehicle | FA301620D0017 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $649.3K |
| Current contract value | $649.3K |
| Potential contract value / ceiling | $649.3K |
| Start date | Sep 30, 2024 |
| Current end date | Jan 28, 2026 |
| Potential end date | Jan 28, 2026 |
| Latest award activity | Dec 19, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 19, 2025 | P00004 | $0 | THE SCOPE OF DESIGN PROJECT IS TO COMPLETE100% DESIGN FOR CONSTRUCTION PACKAGE TO INSTALL A SECTION OF THE CHILLED WATER LOOP (CWL) JOINING THE EAST/WEST-SIDE RANDOLPH SECTIONS INTO ONE CWL. THE SECTION WILL BE FROM BLDG 496 CW PLANT TO BLDG 100. |
| Sep 29, 2025 | P00003 | $0 | THE SCOPE OF DESIGN PROJECT IS TO COMPLETE100% DESIGN FOR CONSTRUCTION PACKAGE TO INSTALL A SECTION OF THE CHILLED WATER LOOP (CWL) JOINING THE EAST/WEST-SIDE RANDOLPH SECTIONS INTO ONE CWL. THE SECTION WILL BE FROM BLDG 496 CW PLANT TO BLDG 100. |
| Jun 2, 2025 | P00002 | $0 | THE SCOPE OF DESIGN PROJECT IS TO COMPLETE100% DESIGN FOR CONSTRUCTION PACKAGE TO INSTALL A SECTION OF THE CHILLED WATER LOOP (CWL) JOINING THE EAST/WEST-SIDE RANDOLPH SECTIONS INTO ONE CWL. THE SECTION WILL BE FROM BLDG 496 CW PLANT TO BLDG 100. |
| Nov 21, 2024 | P00001 | $0 | THE SCOPE OF DESIGN PROJECT IS TO COMPLETE100% DESIGN FOR CONSTRUCTION PACKAGE TO INSTALL A SECTION OF THE CHILLED WATER LOOP (CWL) JOINING THE EAST/WEST-SIDE RANDOLPH SECTIONS INTO ONE CWL. THE SECTION WILL BE FROM BLDG 496 CW PLANT TO BLDG 100. |