Federal contract award
FA441824F0051
REPAIR WATER DISTRIBUTION SYSTEM REDBANK AND ORDNANCE AREA PHASE 1
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA4418 628 CONS PK |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2NZ — REPAIR OR ALTERATION OF OTHER UTILITIES |
| Parent award / vehicle | FA441823D0009 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.1M |
| Current contract value | $3.1M |
| Potential contract value / ceiling | $3.1M |
| Start date | Apr 30, 2024 |
| Current end date | Jun 6, 2026 |
| Potential end date | Jun 6, 2026 |
| Latest award activity | Mar 26, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 26, 2026 | P00009 | $220.9K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND PERIOD OF PERFORMANCE TO 6 JUNE 2026 AND TO COMPLETE WORK ASSOCIATED WITH ADDENDUM 003 - CAPPING EXISTING WATERLINES 3 AND 4 FOR THE NEGOTIATED PRICE OF $220,867.78. |
| Dec 15, 2025 | P00008 | $0 | 1. THE PERIOD OF PERFORMANCE END DATE HAS BEEN EXTENDED FROM 1 AUGUST 2025 TO 7 NOVEMBER 2025. 2. THIS MODIFICATION IS AT NO ADDITIONAL COST TO EITHER PARTY. |
| Dec 1, 2025 | P00007 | $0 | 1. SUSPENSION OF WORK PENDING WATERLINE CAP ADDENDUM NEGOTIATION AND MODIFICATION. 2. THIS MODIFICATION IS AT NO ADDITIONAL COST TO EITHER PARTY. |
| Sep 30, 2025 | P00006 | $0 | THE PURPOSED OF THIS MODIFICATION IS TO EXTEND THE PERIOD PERFORMANCE (POP) END DATE BY 71 DAYS. THE NEW POP END DATE IS AUGUST 1, 2025. OF THE 71 ADDITIONAL DAYS, 48 DAYS ARE COMPENSABLE AND WILL BE FUNDED AT A LATER DATE. |
| May 28, 2025 | P00005 | $184.2K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE END DATE OF CLIN 0003 FROM 28 MARCH 2025 TO 22 MAY 2025. |
| May 1, 2025 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE END DATE OF CLIN 0003 FROM 28 MARCH 2025 TO 22 MAY 2025. |