Federal contract award
FA448426P0007
THIS SOW DEFINES THE REQUIREMENT FOR A CONTRACTOR TO INSTALL AND TEST INTO SERVICE, A SECONDARY CRASH NETWORK (SCN) UPGRADE FOR MCGUIRE AIRFIELD AND A PRIMARY CRASH NETWORK (PCN) AND SECONDARY CRASH NETWORK (SCN) UPGRADE FOR LAKEHURST MAXFIELD FIELD.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA4484 87 CONS PK |
| NAICS | 517810 — All Other Telecommunications |
| PSC | 7G21 — Digital network communications hardware, software, and other equipment used within the core data centers and work areas, connecting end users to the organization's Local Area Network (LAN). Wide Area Network (WAN) digital transmission equipment, supporting hardware and software directly connecting data centers, offices and third parties. Includes 1) external digital network transport equipment (Outside Plant) physical communications infrastructure connecting to LAN/WAN end points 2) copper and fiber communications systems, and 3) cellular infrastructure such as towers, repeaters, switching systems dedicated for cellular communication. Products and tools that enable or distribute voice services through on-premise digital equipment including PBX, VoIP, voicemail and handsets. |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $95.0K |
| Current contract value | $95.0K |
| Potential contract value / ceiling | $95.0K |
| Start date | Jun 4, 2026 |
| Current end date | Sep 2, 2026 |
| Potential end date | Sep 2, 2026 |
| Latest award activity | Jun 2, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 1 of 1 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 2, 2026 | 0 | $95.0K | THIS SOW DEFINES THE REQUIREMENT FOR A CONTRACTOR TO INSTALL AND TEST INTO SERVICE, A SECONDARY CRASH NETWORK (SCN) UPGRADE FOR MCGUIRE AIRFIELD AND A PRIMARY CRASH NETWORK (PCN) AND SECONDARY CRASH NETWORK (SCN) UPGRADE FOR LAKEHURST MAXFIELD FIELD. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.