Federal contract award
FA462523F0088
INSTALLATION OF TRANSFORMERS AND SWITCHES AT B44 AND NEAR B890
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA4625 509 CONS CC |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | FA462520D0002 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $499.9K |
| Current contract value | $499.9K |
| Potential contract value / ceiling | $499.9K |
| Start date | Aug 27, 2023 |
| Current end date | Apr 10, 2026 |
| Potential end date | Apr 10, 2026 |
| Latest award activity | Mar 27, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 27, 2026 | P00005 | $0 | ADDITIONAL INFORMATION PROJECT TITLE: INSTALL SWITCHES AND TRANSFORMERS NEAR B890 AND B44 WHITEMAN PROJECT: 1111693 A. INCORPORATE: STATEMENT OF WORK DATED DECEMBER 2022. B. INCORPORATE: FINAL REVISED NEGOTIATED COST FOR ORIGINAL LINE ITEMS DATE |
| Mar 26, 2026 | P00004 | $0 | ADDITIONAL INFORMATION PROJECT TITLE: INSTALL SWITCHES AND TRANSFORMERS NEAR B890 AND B44 WHITEMAN PROJECT: 1111693 A. INCORPORATE: STATEMENT OF WORK DATED DECEMBER 2022. B. INCORPORATE: FINAL REVISED NEGOTIATED COST FOR ORIGINAL LINE ITEMS DATE |
| Jan 15, 2026 | P00003 | $0 | ADDITIONAL INFORMATION PROJECT TITLE: INSTALL SWITCHES AND TRANSFORMERS NEAR B890 AND B44 WHITEMAN PROJECT: 1111693 A. INCORPORATE: STATEMENT OF WORK DATED DECEMBER 2022. B. INCORPORATE: FINAL REVISED NEGOTIATED COST FOR ORIGINAL LINE ITEMS DATE |
| Dec 12, 2025 | P00002 | $0 | ADDITIONAL INFORMATION PROJECT TITLE: INSTALL SWITCHES AND TRANSFORMERS NEAR B890 AND B44 WHITEMAN PROJECT: 1111693 A. INCORPORATE: STATEMENT OF WORK DATED DECEMBER 2022. B. INCORPORATE: FINAL REVISED NEGOTIATED COST FOR ORIGINAL LINE ITEMS DATE |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.