Federal contract award
FA491124C0002
CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | FA4911 378 ECONS |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Z2BD — REPAIR OR ALTERATION OF AIRPORT RUNWAYS AND TAXIWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $716.7K |
| Current contract value | $716.7K |
| Potential contract value / ceiling | $716.7K |
| Start date | Sep 26, 2024 |
| Current end date | Apr 28, 2026 |
| Potential end date | Apr 28, 2026 |
| Latest award activity | Feb 14, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 14, 2026 | P00006 | $0 | CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW. |
| Nov 3, 2025 | P00005 | $0 | CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW. |
| Mar 14, 2025 | P00003 | $0 | CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW. |
| Mar 10, 2025 | P00002 | $0 | CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW. |
| Jan 8, 2025 | P00001 | $0 | CE PROJECT 23-1057 - THIS REQUIREMENT IS TO PROVIDE PRINCE SULTAN AIR BASE WITH A SAFE AND RELIABLE PAVEMENT SURFACE FREE OF JOINT SPALLS AND FOD AND REPLACE JOINTS SEALS THROUGHOUT 122,000 SM OF TAXIWAY PAVEMENTS. WORK WILL BE COMPLETED IAW SOW. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.